Machine builders: check the customer's requirement specification against your functional specification, line by line

For project and sales engineers at makers of production machines, packaging and assembly lines, test rigs and other one-off machinery who answer a customer's requirement specification and deliver a FAT, a SAT and a documentation package.

By Ademola Afolabi, Founder, New Odyssey Ltd ยท Last reviewed:

The short answer

A machine builder answers a customer specification by setting each line of the user requirement specification and the plant's factory standards against its own functional specification and quotation. OdysseyGPT drafts that comparison from the documents, with a quote from both sides for every row. Your engineers decide each status. It does no risk assessment and no CE work.

Key Takeaways

  • The customer writes what the machine must do. The builder's functional specification says how. The gaps between the two belong on a deviation list before the order.
  • Factory standards for components and controls often cost more than the requirement specification itself, because they set brands, platforms and software rules.
  • Acceptance figures such as cycle time and OEE mean little until the test conditions, the product and the duration are written down.
  • OdysseyGPT reads documents and quotes its sources. It does not assess risk, read schematics or PLC code, or write the technical file.

See how OdysseyGPT reviews a tender. Tell us how your team reviews tenders today. We can walk through an example together. Book a call

How do machine builders answer a customer specification?

An enquiry for a special-purpose machine rarely arrives as one document. The customer sends a requirement specification that describes the task: the product, the process steps, the output wanted and the space available. Many customers call it a user requirement specification, or URS. German-speaking customers call it a Lastenheft. Alongside it come the plant's own factory standards and the commercial terms.

The builder replies with a quotation and a functional specification, which in German practice is the Pflichtenheft. It describes the concept offered: stations, sequence, controls, guarding, interfaces and what is excluded. Once both sides sign it, the functional specification is normally the document the machine is accepted against. A requirement that was in the URS and never reached the functional specification is where most later arguments start.

The documents in a machine enquiry and what each one fixes (own summary)
DocumentWritten byWhat it fixes
Requirement specification (URS or Lastenheft)CustomerThe task: product range, process, output, changeover, footprint, utilities and the acceptance wanted
Factory standardsCustomer's plant or group engineeringApproved component brands, the control platform, software structure, electrical and pneumatic practice, colours, labelling and documentation format
Functional specification (Pflichtenheft)BuilderThe machine offered: concept, stations, sequence, safety concept, interfaces, exclusions and assumptions
Performance and acceptance criteriaBoth, agreed in the contractCycle time, output, availability or OEE, capability figures, and how, where and for how long each is measured
Deviation listBuilderEach point where the offer differs from the requirement specification or a factory standard, with the reason
  1. Split the requirement specification and every factory standard into single requirements, each with its section number.
  2. Mark each one against the functional specification: complies, deviates, needs clarification or not addressed.
  3. Check the performance figures separately. Write down the product, the operator count and the measuring period each figure assumes.
  4. Collect the open points into a deviation list and a list of questions, and send both with the quotation.
  5. After the customer replies, carry the agreed deviations into the signed functional specification so that one document governs acceptance.

The row-by-row record is a compliance matrix. A ready layout for a URS reply is on the URS response matrix template page.

Which rules and standards come up in a machine specification?

A requirement specification usually names the law of the country where the machine will run and then a short list of safety standards. The table gives the ones a builder meets most often, at name level only. It is our own summary and it is not legal advice. Work from the texts and editions your contract names.

Rules and standards named in machine specifications (own summary, name level)
Rule or standardWhat it isWhat to look for in the specification
Machinery Directive 2006/42/ECThe EU law that machinery placed on the EU market must meet today. It sets essential health and safety requirements and asks for a risk assessment, a technical file, a declaration and CE markingWhether you supply a complete machine with a declaration of conformity or partly completed machinery with a declaration of incorporation
Machinery Regulation (EU) 2023/1230The regulation that replaces the Directive. The Commission states that it applies from 20 January 2027The date the machine will be placed on the market. A long project can start under one text and deliver under the other. See the Machinery Directive and Regulation page
EN ISO 12100The general standard for risk assessment and risk reduction in machine designWhether the customer wants to see the risk assessment, and at which design review
EN 60204-1The standard for the electrical equipment of machinesConflicts between it and the plant's own electrical standard, and which one governs
Supply of Machinery (Safety) Regulations 2008 and UKCAThe Great Britain rules for new machinery. Government guidance says CE marking continues to be recognised thereWhich marking the customer asks for, and instructions in English
OSHA rules and NFPA 79For US buyers: federal workplace rules on machine guarding, and the NFPA electrical standard for industrial machineryThat CE marking is not a US requirement. The specification should say which US standards the buyer expects the machine to meet
The customer's factory standardsPrivate documents that sit on top of the lawThe order of precedence if a factory standard and a named safety standard disagree

Machines with a safety-related control system often also name a functional safety standard. Where a specification asks for a safety integrity level, the overview on IEC 61508 and IEC 61511 explains the terms. A machine that contains pressure equipment may also fall under the Pressure Equipment Directive.

What goes in a machine builder's deviation list?

On a machine project the costly deviations are seldom about the process. They are about the parts the customer's maintenance team wants to see when it opens the cabinet, and about how performance is proved. These are the areas to read first.

Where a machine offer most often differs from the customer's documents (own summary)
AreaWhat to check before you sign the functional specification
Brand and component listsNamed makes for PLC, drives, pneumatics, sensors, robots and safety devices. Check whether an alternative needs written approval and who pays if the listed part has a long lead time
Cycle time and outputThe product variant, the infeed quality, the operator count and whether the figure is gross or net of stoppages caused by the customer's material
OEE or availability guaranteesThe formula the customer uses, the length of the acceptance run, which stoppages count against the builder and what happens if the figure is missed
Capability figuresWhich characteristics are measured, the sample size, who supplies the parts and the gauges, and whether the figure is proved at FAT, at SAT or both
Controls standardsPLC platform and firmware level, software structure and naming rules, HMI layout, network and data interfaces to the plant systems, and remote access
Safety conceptGuard types, access and operating modes the customer wants. A plant standard may ask for more than your risk assessment needs, or for something it does not support
Documentation language and formatThe languages for instructions, HMI texts and drawings, the file formats, the plant's numbering scheme and the number of paper sets
Acceptance and handoverWhether FAT and SAT are both required, who supplies test product, and which documents must be complete before each test
Training and spare partsDays of training included, the spare and wear parts list wanted with the offer, and any stock the builder must hold

Put the test conditions next to every guaranteed figure

A cycle time or OEE figure with no stated product, duration and stoppage rules cannot be passed or failed. If the requirement specification gives a number and nothing else, raise a clarification and write your assumptions into the functional specification.

Which documents follow after the order?

After the order the customer's document list turns into dated submissions. Some are contract documents the customer approves. Others are legal documents the builder owes under the machinery rules whether the customer asks or not. The contract and the law that applies decide the list. A machine builder should expect these.

Post-order documents for a special-purpose machine (own summary)
DocumentWhat the customer looks for
Design review recordsMinutes of each layout, mechanical and controls review, with the actions agreed and who closes them
FAT protocolThe test steps, the acceptance figure for each, the product used and the requirement each step proves. See the machine FAT protocol template
FAT reportSigned results, the list of open points with owners and dates, and the release to ship
SAT protocol and reportTests repeated or added after installation, run with the plant's utilities and product. See site acceptance test
Declaration of conformityFor a complete machine: the builder's signed statement that it meets the machinery rules, issued with the machine
Declaration of incorporationFor partly completed machinery: the statement of which requirements are met, supplied with assembly instructions
InstructionsOperating and maintenance instructions in the language of the country of use, matching the machine as built
Technical fileKept by the builder for the authorities. The contract says which parts of it, if any, the customer receives
Spare and wear parts listPart numbers, makes and recommended quantities, in the plant's format
As-built drawings, schematics and software backupThe revision that matches the machine after SAT changes

The handover set is close to what process industries call a turnover package. The difference between the two acceptance tests is explained under FAT vs SAT, and the factory acceptance test checklist covers what to have ready before the customer travels.

How does OdysseyGPT help?

OdysseyGPT reads the documents you upload and sets them against the customer's written requirements. Every finding shows the passage it rests on in both documents, so an engineer can check it in seconds. Document Review takes the requirement specification and factory standards as the base and your functional specification and quotation as the documents to check. It also works in reverse, listing statements in your documents that the customer's text does not cover. The other tools each read a narrower set.

A machine builder's documents and the tool that reads each
Your documentToolWhat it reports
Requirement specification, factory standards and your functional specificationDocument ReviewA status and a pair of quotes for each customer requirement, plus assumptions and exclusions in your text that the customer has not answered
Requirement specification and factory standards on their ownCustomer Specification Review (beta)A register with one line per requirement, grouped as technical, quality, documentation, test or commercial, with unclear items flagged
The customer's machine data sheet and your filled copyDatasheet Comparison (beta)Matched fields and each difference in value, with the cell or line it came from
Deviation list and the customer's repliesDeviation Register (beta)One running record of each deviation through the clarification rounds to the customer's decision
The contract's list of documents to submitVDRL/MDR Tracker (beta)A register of each required document with its due date, revision and status
Your inspection and test plan and the customer's quality clausesITP Validator (beta)Stages the customer asks for that the plan leaves out, and witness points that do not match
FAT protocol with the test plan, calibration evidence and open-points listFAT Readiness Check (beta)Whether the documents the test depends on are in place, with blockers listed apart from review items
FAT measurement records and gauge certificatesCalibration Validity Check (beta)Each instrument named in a record matched to a certificate valid on the test date
The documentation folder and the customer's indexMRB Readiness Check (beta) and MRB Compiler (beta)Documents that are missing, unapproved or at the wrong revision, and a manifest in the customer's index order

The tools are grouped by project stage: tender, inspection and handover. The manufacturing page shows how they fit together. There is no tool for the site acceptance test itself.

What does a result look like?

The table below is an invented example. The customer, the machine, the section numbers, the builder's documents and every figure are made up to show how a result is laid out. Nothing in it comes from a real project, a real builder or a standard.

Invented example: a URS for an automatic assembly and test cell, checked against a builder's functional specification
Customer requirement (quoted)Builder's document (quoted)StatusNote
"The cell shall assemble housing variants A, B and C without tool change." (URS 3.1)"Variants A, B and C are processed on common nests. No change parts are required." (Functional specification 2.2)CompliesSame three variants and the same no-change statement in both documents.
"Cycle time shall not exceed 12 seconds per part, measured over an eight-hour production shift." (URS 4.2)"Technical cycle time: 12 s per part in automatic mode with parts supplied to drawing." (Functional specification 5.1)ClarificationThe figure matches. The builder states no measuring period and adds a condition on part quality.
"All PLC and drive components shall be taken from the approved list in Factory Standard FS-07." (URS 6.1)"Servo drives: builder's standard make, as listed in the component schedule." (Quotation Q-1182, item 14)DeviatesThe drive make offered is not on the customer's list. Declare it or price the listed make.
"Overall equipment effectiveness of at least 85 % shall be demonstrated during a three-shift acceptance run at site." (URS 4.5)"Availability of 95 % is demonstrated at FAT over a four-hour run." (Functional specification 9.3)DeviatesA different measure, a shorter run and a different place. This needs a decision before the order.
"HMI texts and operating instructions shall be supplied in English and Polish." (URS 8.3)"Documentation language: English." (Quotation Q-1182, item 22)DeviatesThe second language is not offered.
"The supplier shall provide the risk assessment for review at the design freeze meeting." (URS 7.2)No matching statement found in the documents supplied.Not addressedThe builder's documents do not say whether the risk assessment is shared. Answer it in the offer.
"Machine capability shall be proven on 50 consecutive parts for the press-in force." (URS 4.7)"Capability study on 50 parts for press-in force and press-in depth at FAT." (FAT plan FP-03, step 11)CompliesThe builder's study covers the characteristic asked for and one more.
"A recommended spare parts list with prices shall be submitted with the offer." (URS 9.1)"A spare and wear parts list is supplied with the final documentation." (Functional specification 11.4)DeviatesThe list is offered later than the customer asks, and prices are not mentioned.

A project engineer opens the two quotes on each row and confirms or changes the status. Rows left as deviates or clarification go to the deviation list and the question list. Rows marked not addressed show where the functional specification needs another paragraph.

Where OdysseyGPT falls short

  • It does no risk assessment. It does not identify hazards, choose protective measures or judge whether a safety concept is adequate.
  • It does no CE or UKCA conformity assessment and it does not tell you which legislation or which standards apply to your machine.
  • It does not write the technical file, the declaration of conformity, the declaration of incorporation or the instructions.
  • It does not read layout drawings, mechanical drawings, electrical or pneumatic schematics, or PLC and robot programs. A requirement that is answered only on a drawing or in code is not checked.
  • It cannot tell you whether a cycle time, an OEE figure or a capability figure is achievable. It shows what each document says. Your engineers judge the design.
  • It holds no standards and no factory standards. A rule that sits only inside a named document is checked only if you upload that document as readable text.
  • It can pair a requirement with the wrong passage or miss one, most often where a requirement specification repeats the same wording for several stations. The quotes are shown so a person can catch this.
  • It does not run a FAT or a SAT, record measurements or connect to the machine.
  • Tools carrying a beta marker on this page are available on request, and we set each team up ourselves.

Talk through your tender review

See how OdysseyGPT reviews a tender

Tell us how your team reviews tenders today. We can walk through an example together.

Book a call

Buyer questions

20 questions bid engineers, proposal engineers and buyers ask. Last reviewed:

What is in a customer's requirement specification for a special-purpose machine?

Usually the product and its variants, the process steps, the output and cycle time wanted, changeover, the space and utilities available, interfaces to other equipment, safety and legal requirements, documentation and the acceptance tests. It often refers to separate factory standards for components and controls. Read those as part of the specification, because they carry as many requirements as the main text.

What is the difference between a URS and a functional specification?

The user requirement specification is the customer's document and says what the machine must do. The functional specification is the builder's document and says how the machine offered will do it. German-speaking customers call them Lastenheft and Pflichtenheft. Once both parties sign the functional specification, acceptance is normally measured against it, so every agreed deviation should be written into it.

What are factory standards in a machine enquiry?

They are the customer's own rules for equipment bought for a plant. They typically set approved makes for controllers, drives, pneumatics and sensors, the control platform and software structure, electrical practice, colours, labelling and the format of documentation. They are contract requirements once referenced. Check each one against your standard design and list every difference before you quote.

How should a machine builder answer a customer specification?

Split the specification and each factory standard into single requirements. Mark each one against your functional specification as complies, deviates, clarification or not addressed, and note the reason. Send the deviations and questions with the quotation. A row-by-row compliance matrix gives the customer one place to see what is offered and gives you a record of what was agreed.

What goes in a machine builder's deviation list?

Each point where the offer differs from the requirement specification or a factory standard, with the section, what is offered and why. Typical entries cover component makes, the control platform, performance guarantees and how they are measured, the safety concept, documentation languages and spare parts. The technical deviation list guide shows a format.

What if the customer's brand list names a component we do not use?

Declare it. Either offer the listed make and price the engineering it needs, or offer your standard make as a stated deviation and ask for written approval. Do not leave it to the design review. A drive or controller swapped after the order affects software, spare parts and the customer's maintenance training, and it is costly to reverse.

How should a cycle time guarantee be written?

With its conditions. State the product variant, the quality of incoming parts, the number of operators, the operating mode and the period over which the time is measured. Say whether the figure is a technical cycle time or an average that includes minor stoppages. A number with no conditions cannot be passed or failed at acceptance.

What should we check before accepting an OEE guarantee?

Check the formula the customer uses, since definitions differ between companies. Check the length of the acceptance run, where it takes place, who supplies material and operators, which stoppages count against the builder, and what the contract says if the figure is missed. If the specification gives only a percentage, raise a clarification and state your assumptions in the functional specification.

What is a machine acceptance test?

It is the test at which the customer confirms the machine meets the agreed specification. Most machine contracts have two: a factory acceptance test at the builder's works before shipment, and a site acceptance test after installation. Each follows a written protocol with test steps, pass figures and a list of open points. See FAT vs SAT.

What does a FAT protocol for a machine contain?

The preconditions, the checks of scope and build against the functional specification, the safety function tests, each machine function in each operating mode, the performance run with its duration and pass figure, any capability study, a documentation check and a punch list. Each step should point to the requirement it proves. A layout is on the machine FAT protocol template page.

What does a SAT protocol cover that the FAT does not?

Everything that depends on the site: transport damage, installation, the plant's utilities, interfaces to neighbouring equipment and to the plant's control and data systems, and usually the longer performance run with production material and the customer's operators. The entry on the site acceptance test lists the usual contents and who signs.

Does the Machinery Directive apply to a one-off special-purpose machine?

A machine placed on the EU market or put into service there falls under the EU machinery rules whether one is built or a thousand. The manufacturer's duties include a risk assessment, a technical file, instructions, a declaration and CE marking. The Machinery Directive and Regulation page gives an overview. It is not legal advice, so check the legal text for your case.

When does the Machinery Regulation replace the Machinery Directive?

The European Commission states that Regulation (EU) 2023/1230 applies from 20 January 2027, and that machinery placed on the EU market before that date must comply with Directive 2006/42/EC. For a project that spans the date, what counts is when the machine is placed on the market, not when it was ordered. Agree in writing which text your declaration will cite.

Do we supply a declaration of conformity or a declaration of incorporation?

It depends on what you deliver. A complete machine that can perform its application gets a declaration of conformity. Partly completed machinery, which cannot work until it is built into something else, gets a declaration of incorporation and assembly instructions. Settle which applies when you define the scope of supply, because the customer's specification may assume the other.

Does the customer have a right to our technical file?

Not under the Machinery Directive, which asks the manufacturer to keep the technical file available for the authorities. The customer receives the instructions and the declaration. Anything more, such as the risk assessment, calculations, source code or detailed drawings, is a contract matter. If the specification asks for it and you will not supply it, list the point as a deviation.

Does a machine for a customer in Great Britain need UKCA or CE marking?

Great Britain has its own Supply of Machinery (Safety) Regulations 2008. The gov.uk guidance says a manufacturer may use the UKCA marking or the CE marking for the Great Britain market, and that recognition of CE marking has been extended. Rules have changed several times, so read the current gov.uk guidance and confirm which marking the customer's specification expects.

What changes when the customer is in the United States?

CE marking is not a US legal requirement. Workplace machinery falls under OSHA rules on machine guarding, and buyers commonly name NFPA 79 for the electrical equipment and other US consensus standards for safety. The specification should list the standards and any inspection the buyer expects. If it only says the machine must meet local regulations, ask for the list.

Which documents does a machine builder deliver after the order?

Typically design review records, the FAT protocol and report, the SAT protocol and report, the declaration of conformity or of incorporation, operating and maintenance instructions, as-built drawings and schematics, a software backup, and a spare and wear parts list. The contract's document list decides. The technical file stays with the builder unless the contract says otherwise.

How does OdysseyGPT help a machine builder with a customer specification?

Document Review takes the requirement specification and factory standards as the base and your functional specification and quotation as the documents to check. For each requirement it gives a status and a quote from both documents, and it lists statements in your text the customer has not addressed. Customer Specification Review (beta) builds the requirement register first. Engineers decide every status.

What does OdysseyGPT not do on a machine project?

It does not carry out a risk assessment or a CE conformity assessment. It does not read layout drawings, electrical schematics or PLC code, and it does not write the technical file, the declarations or the instructions. It cannot judge whether a cycle time is achievable. It reads documents, compares them with the customer's written requirements and shows its quotes.

Frequently asked questions

Who answers the requirement specification at a machine builder?

Usually a sales or project engineer, with mechanical design for the concept, controls engineering for the platform and software rules, and the person responsible for machine safety for the safety concept and the declarations.

Does OdysseyGPT do CE marking or risk assessment for machines?

No. It reads documents and checks them against the customer's written requirements, with a quote for every finding. Risk assessment, conformity assessment and the declarations stay with the manufacturer.

Can it read a customer's factory standards and brand lists?

Yes, if you upload them as PDF, Word, Excel or CSV files with readable text. A brand list in a spreadsheet is cited by sheet and cell. Drawings, schematics and PLC code are not read.

What is the difference between a Lastenheft and a Pflichtenheft?

The Lastenheft is the customer's requirement specification: what the machine must do. The Pflichtenheft is the builder's functional specification: how the machine offered will do it. Acceptance is normally measured against the agreed Pflichtenheft.

References

Directive 2006/42/EC on machinery (consolidated text)

EUR-Lex

Articles 5, 12 and 13 and Annexes I, II, VI and VII used for the manufacturer's duties and the documents named on this page.

Visit source

Regulation (EU) 2023/1230 on machinery

EUR-Lex

The regulation that replaces the Directive. Read with its corrigendum on the application date.

Visit source

Machinery

European Commission

States that the Regulation applies from 20 January 2027 and that machinery placed on the market before then follows the Directive.

Visit source

Harmonised standards: machinery (MD)

European Commission

Where to check which edition of a standard such as EN ISO 12100 or EN 60204-1 is currently cited.

Visit source

Supply of Machinery (Safety) Regulations 2008: Great Britain

Office for Product Safety and Standards (gov.uk)

Guidance dated March 2025 on the Great Britain rules, UKCA and CE marking.

Visit source

UK law on the design and supply of products

Health and Safety Executive

Summary of what new machinery must come with, including instructions in English.

Visit source

Machine guarding: standards

Occupational Safety and Health Administration (US)

The federal rules on machinery and machine guarding in 29 CFR 1910 Subpart O.

Visit source

NFPA 79: Electrical Standard for Industrial Machinery

National Fire Protection Association

Named only. Use the edition your contract or the local authority names.

Visit source