Download the URS response matrix
XLSX
URS response matrix (Excel)
Header block, 9 columns, drop-downs for category, must or want and status, colour-coded Deviates, Clarification and Not addressed rows, frozen header row, filters and a How to use sheet.
CSV
URS response matrix (CSV)
The example rows as plain CSV (UTF-8), for Google Sheets or any other tool.
Both files are free under CC BY 4.0, with no form to fill in. The XLSX opens in Excel, Google Sheets, LibreOffice and Numbers. The CSV carries the table only; the header block is in the XLSX.
What it is for and who uses it
A user requirement specification (URS) is the customer's numbered list of what the equipment must do. Most enquiries ask the supplier to answer it point by point, and the answer later becomes the starting point for design qualification and the traceability matrix. This template is that answer. It follows the same idea as the general compliance matrix template, with the columns a URS needs: must or want, and where each requirement will be verified.
- Proposal and sales engineers at equipment suppliers, who answer the URS in the offer.
- Validation and quality engineers, who check that every requirement has a verification stage.
- Customers writing a URS, who can use the first four columns as the requirement list and send the rest for suppliers to fill in.
If the customer supplies its own response form, copy your rows into that form. See also pharmaceutical equipment manufacturers.
Header block
| Field | Example |
|---|---|
| Project | Example Biologics Facility, Suite 2 (fictional) |
| Customer | Example Pharma Ltd (fictional) |
| URS no. and revision | URS-EX-5120 Rev 2 (fictional) |
| Equipment | Stainless steel process vessel skid, 500 L (fictional) |
| Supplier | Example Process Equipment Ltd (fictional) |
| Quotation no. | Q-EX-5120 Rev A |
| Matrix no. | URM-EX-5120 |
| Revision | A |
| Date | 2027-01-18 |
| Prepared by | Proposal engineer |
| Checked by | Validation engineer |
Example rows: a URS for a stainless process vessel skid
| URS ID | Requirement | Category | Must / want | Supplier response | Status | Reference document | Verified at | Remarks |
|---|---|---|---|---|---|---|---|---|
| URS-001 | The vessel shall have a working volume of 500 L and a minimum working volume of 100 L. | Process | Must | 500 L working volume; minimum stirred volume 90 L. | Complies | DS-EX-5120 Rev A, line 4 | DQ; IQ | |
| URS-002 | The vessel and jacket shall be designed for the pressures and temperatures in URS table 2, including full vacuum. | Process | Must | Design conditions as URS table 2. | Complies | DS-EX-5120 Rev A, lines 7 to 10; GA-EX-5120 Rev A | DQ; IQ | |
| URS-003 | The skid shall be cleaned in place (CIP) and steamed in place (SIP) without dismantling. | Process | Must | CIP by spray ball; SIP through the vessel and the sterile boundary valves. | Clarification | PID-EX-5120 Rev A | FAT; OQ | Customer to confirm CIP supply flow and pressure at the skid inlet. Clarification C-01. |
| URS-004 | The agitator speed shall be adjustable from 20 to 200 rpm. | Process | Want | Adjustable from 30 to 250 rpm with the offered drive. | Deviates | DS-EX-5120 Rev A, line 15 | FAT; OQ | Lower limit is 30 rpm. Deviation D-01. |
| URS-005 | Product-contact metal parts shall be 316L stainless steel, with material certificates of the type the URS names. | Materials and surface finish | Must | 316L for all product-contact metal parts; certificates as requested. | Complies | BOM-EX-5120 Rev A | DQ; IQ | |
| URS-006 | Product-contact surfaces shall be finished to 0.5 micrometres Ra or better and electropolished. | Materials and surface finish | Must | Mechanically polished to 0.5 micrometres Ra. Electropolishing is not in the base offer. | Deviates | Q-EX-5120 Rev A, section 3.2 | FAT; IQ | Electropolishing offered as a priced option. Deviation D-02. |
| URS-007 | Elastomers in product contact shall carry the compliance certificates listed in URS section 6. | Materials and surface finish | Must | EPDM and PTFE seals, with the certificates listed. | Complies | Seal list SL-EX-5120 Rev A | IQ | |
| URS-008 | The control system shall keep an audit trail and electronic records that meet the customer's data integrity policy DI-EX-01. | Automation | Must | Supplier's standard audit trail and user management offered. | Clarification | FS-EX-5120 Rev 0, section 8 | DQ; FAT; OQ | Policy DI-EX-01 was not in the enquiry. Clarification C-02. |
| URS-009 | Alarms shall be raised for high temperature, high pressure and agitator fault, and logged with time and user. | Automation | Must | Alarms as listed, logged with time stamp and user. | Complies | Alarm list AL-EX-5120 Rev 0 | FAT; OQ | |
| URS-010 | The skid shall send batch data to the site historian. | Automation | Want | Not addressed | Not covered in Q-EX-5120. Answer before the offer is issued. | |||
| URS-011 | The supplier shall deliver a functional specification, design specification, P&ID, material certificates, weld documentation and calibration certificates in the turnover package. | Documentation | Must | All listed documents included. Weld documentation covers product-contact welds: weld map, weld log and inspection records. | Complies | Document list DL-EX-5120 Rev A | DQ; IQ | |
| URS-012 | The supplier shall provide IQ and OQ protocols for the customer's approval before they are executed. | Documentation | Must | IQ and OQ protocols included, in the supplier's standard format. | Clarification | Q-EX-5120 Rev A, section 5 | IQ; OQ | Customer to confirm the supplier's protocol format is acceptable. Clarification C-03. |
| URS-013 | A factory acceptance test (FAT) shall be run to an approved protocol and witnessed by the customer. | Testing | Must | FAT to a protocol issued for the customer's approval before the test. | Complies | Q-EX-5120 Rev A, section 6 | FAT | |
| URS-014 | Spray coverage of the vessel interior shall be demonstrated at the FAT. | Testing | Must | Coverage test included in the FAT. | Complies | Q-EX-5120 Rev A, section 6 | FAT | |
| URS-015 | The supplier shall carry out a site acceptance test (SAT) after installation, repeating the loop checks and alarm tests. | Testing | Must | SAT support quoted at a day rate; not in the fixed price. | Deviates | Q-EX-5120 Rev A, section 7 | SAT | Deviation D-03. |
Three rows deviate, three need a clarification and one is not yet addressed. The requirement values are the invented customer's own and are not taken from any standard or guideline. Every example value is invented: the project, customer, bidders, purchase order, prices and every document, certificate, serial and report number do not exist. Standards are named but not quoted.
Status values
| Status | Use it when |
|---|---|
| Complies | The offer meets the requirement as written. Point to the document and line that shows it. |
| Deviates | The offer does not meet the requirement as written. Say what is offered instead and carry the item into the deviation list. |
| Clarification | The requirement is unclear, depends on information the customer has not sent, or is met in a different way that the customer should confirm. |
| Not addressed | The offer does not yet answer the requirement. Every such row needs an answer before the offer goes out. |
Where each requirement is verified
| Stage | Common meaning |
|---|---|
| DQ (design qualification) | Documented check that the proposed design meets the URS, usually by reviewing specifications and drawings. |
| FAT (factory acceptance test) | Tests at the supplier's works before shipment. |
| SAT (site acceptance test) | Tests at the customer's site after installation. |
| IQ (installation qualification) | Documented check that the equipment is installed as specified. |
| OQ (operational qualification) | Documented check that the equipment operates as specified across its operating ranges. |
These are common meanings. The customer's validation plan and the contract decide which stages apply and who runs them, so agree the split before you fill in the column. Performance qualification (PQ) is usually run by the customer on its own process, so the template leaves it out; add it if your contract covers it. See IQ, OQ and PQ and FAT vs SAT.
Columns and what to write
| Column | What to write |
|---|---|
| URS ID | The requirement's own number in the URS. Do not renumber. |
| Requirement (verbatim) | The requirement text, copied word for word. One requirement per row; split a paragraph that holds several. |
| Category | Process, Materials and surface finish, Automation, Documentation or Testing (drop-down). |
| Must / want | Must or Want, as the URS marks it (drop-down). Use the customer's own classes if the URS defines others. |
| Supplier response | What you offer against this requirement, in one or two lines. |
| Status | Complies, Deviates, Clarification or Not addressed (drop-down). Deviates rows turn red, Clarification amber, Not addressed grey. |
| Supplier reference document | The document, revision and line that supports the response: datasheet, P&ID, functional specification, quotation section. |
| Verified at | The stage or stages where the requirement will be verified: DQ, FAT, SAT, IQ or OQ. Separate more than one with a semicolon. |
| Remarks | The deviation list item, the question for the customer, or what is still missing. |
How to use the template
- Fill in the header block: the URS number and revision you are answering, the equipment, and your quotation number and revision.
- Add one row per URS requirement, with the URS's own ID and the text copied word for word. Split a paragraph that holds several requirements, and keep the URS ID on each part.
- Set the category and whether the URS marks the requirement Must or Want. Use the customer's own classes if the URS defines others.
- Write what you offer and set the status: Complies, Deviates, Clarification or Not addressed.
- For every row, name the document, revision and line that supports the response. A status with no reference is a claim the customer cannot check.
- Enter where each requirement will be verified: DQ, FAT, SAT, IQ or OQ. Agree the split with the customer; their validation plan decides it.
- Carry every Deviates row into your deviation list and every Clarification into your clarification list, and put the item number in Remarks.
- Before the offer goes out, filter Status for Not addressed. Every such row needs an answer.
Starting from a draft
In OdysseyGPT's Tender & Quotation module, Document Review and Customer Specification Review (beta) read the customer's URS and your own datasheets and specifications, list each requirement and show what your documents say against it, with a quote from the source page. Your engineers decide every status and response. Tools marked beta are open on request, and we onboard each team ourselves.
See how OdysseyGPT reviews a tender