Technical bid evaluation (TBE): what EPC evaluators check and how manufacturers pass it

How EPC and owner engineers score an equipment offer, and what a valve, pump, actuator or instrument maker can do to clear the technical gate first time.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

Technical bid evaluation (TBE) is the step where the buyer's engineers check each vendor offer against the requisition, specifications and datasheets. They list deviations and clarifications, and decide which bids are technically acceptable. Only technically acceptable bids go on to commercial comparison, so a manufacturer passes TBE by making compliance easy to verify.

Key Takeaways

  • TBE is a pass/fail gate before price is compared; a technically unacceptable bid is not scored commercially.
  • Evaluators work clause by clause against the requisition issue and its reference documents.
  • The outputs are clarification requests, a list of unacceptable deviations and a technical bid comparison.
  • Manufacturers pass by declaring every deviation clearly, citing clauses and sending every mandatory document.

What is technical bid evaluation?

Technical bid evaluation is the buyer's structured check of whether each offer meets the technical requirements of a tender. In engineered-equipment purchasing, the buyer is usually an EPC contractor or an owner-operator. The documents are a material requisition, a project specification, owner standards, datasheets and any addenda.

A published EPC procedure describes the evaluator's job well. They check each vendor quote against the correct requisition issue and its reference documents. They review the technical details, the vendor's QA/QC manual and its deviations and exclusions. Then they produce clarification requests, a list of unacceptable deviations and a technical bid comparison sheet (Red Bag CM-PE-510).

For the manufacturer, the most important input to TBE is your own technical deviation list. It tells the evaluator where to look.

Who will evaluate the technical bids?

Typical roles around an equipment TBE (EPC side)
RoleWhat they do in TBE
Evaluator (discipline engineer)Reviews the technical part of each quotation, prepares clarification requests, lists unacceptable deviations, updates the technical bid comparison and decides technical acceptability.
Lead specialist engineerResponsible for the technical evaluation of vendor quotations in the discipline.
Discipline specialistsEvaluate their own item types, for example mechanical, electrical, control systems or vessels.
Project buyerIssues the clarification requests to vendors, asks for revised bids where deviations are unacceptable and chairs pre-award meetings.
Project managerHas overall responsibility for the technical and commercial evaluation and for vendor selection.

These roles are taken from the published Red Bag procedure (CM-PE-510); titles vary by company. On public and state-owned tenders, a formal technical evaluation committee often scores the bids instead.

What are the three main stages of bid evaluation?

StageQuestion it answersWhat the manufacturer controls
1. Responsiveness checkIs the bid complete, on time and on the right forms?Every mandatory document, signed forms, priced and unpriced copies that match.
2. Technical evaluation (TBE)Does the offer meet the specification, and are the deviations acceptable?A clear deviation list, cited clauses, datasheets and qualification evidence.
3. Commercial evaluationWhich technically acceptable bid gives the best value?Price, cost of withdrawal for each deviation, delivery and terms.

This three-stage split is a simplification; each buyer's procedure sets its own steps. In the Red Bag procedure, for example, purchasing preselects quotations on a commercial basis while the technical evaluation runs as a separate process. The order still matters, because some owners stop at stage 1 or 2. OGDCL, a Pakistani operator, uses a 70-point technical pass mark and rules a bid non-responsive if it scores zero in any key sub-category, even when the total clears 70; a missing API 6D certificate or manufacturer authorisation letter is a typical reason (OGDCL clarification; OGDCL evaluation report).

How to do technical bid evaluation?

From the evaluator's side, a TBE usually follows these steps. Knowing them tells you how your offer will be read.

  1. Confirm which requisition issue and which revisions of the reference documents apply.
  2. Build the evaluation sheet: one row per key requirement, one column per bidder. A practitioner on Eng-Tips describes taking the key data out of the datasheet and listing it in the first column (Eng-Tips).
  3. Fill each bidder's column from its datasheet, deviation list and supporting documents.
  4. Mark each cell as acceptable, needs clarification or unacceptable.
  5. Send clarification requests or technical queries to bidders, and record the answers.
  6. Issue the technical bid comparison with a recommendation: which bids are technically acceptable, and with which deviations.

A free TBE matrix template gives you the same layout an evaluator uses, so you can check your own offer the way it will be checked.

What are examples of evaluation criteria?

Typical technical criteria for an engineered valve or pump offer
CriterionWhat the evaluator checksEvidence they expect from you
Design standardProduct standard and edition named in the specDatasheet entry and certificate, for example an API 6D licence
Pressure and temperature ratingClass, design pressure and temperature rangeDatasheet values in the spec's units
MaterialsBody, trim, bolting, seals and sour-service requirementsMaterial list with grades
TestingShell, seat, fire and fugitive-emission testsTest procedure or type-test report, such as ISO 15848-1
Certificates and inspectionCertificate type, inspection and test plan, witness pointsEN 10204 certificate type, draft ITP
DocumentationVendor data requirements list (VDRL) items and their timingDocument list with submission dates
Quality systemQA/QC manual and certifications the spec asks forCurrent certificates
Approved vendor statusVendor and manufacturing location on the client's approved vendor listApproval reference for the product line and works
Performance (pumps)NPSH margin, performance curves, guaranteed vibration within API limitsCurves, NPSH data and test records
Scope and exclusionsSpares, accessories, site servicesClear "Not offered" rows in the deviation list

Every buyer has its own checklist; this table is a starting point. The approved-vendor, performance, testing and painting checks follow a practitioner guide to vendor offer review (What Is Piping).

How manufacturers pass TBE

  • Declare every deviation, with the clause, in the tender's own form. Owners such as BHEL reserve the right to accept or reject each deviation and ignore those that appear only in the priced copy (BHEL corrigendum).
  • State offered values in the same units and terms as the requirement, so the evaluator can compare without converting.
  • Give a technical justification and a cost of withdrawal for every deviation, so it can be accepted or priced without a clarification round.
  • Send every mandatory certificate and authorisation letter. A missing one can make the whole bid non-responsive.
  • Check the revision of every document you cite, especially after addenda.
  • Answer technical queries quickly and update the deviation list, not just the email thread.

The work is slow on both sides. In one vendor case study, a large EPC spent 15 to 20 minutes per datasheet review just extracting the data, across roughly 150 vendor RFPs that included valve datasheets; the vendor reports manual effort down 80% with AI (Botminds). Clause-by-clause review against specs and standards takes longer than extraction alone.

TBE templates and tools

Free TBE templates are scarce; most published examples are tender evaluation reports and government forms. Some engineering firms publish scored matrices, such as Vajra's valve vendor scoring matrix with 25 criteria and a total weight of 112 points (Vajra).

Several software vendors now sell TBE automation to EPCs. Pathnovo, for example, says it delivers a TBE-ready table in 24 hours for a typical 5 to 10 vendor evaluation, against 1 to 3 weeks for manual review; that is the vendor's own claim (Pathnovo). For an honest overview, see AI tools for datasheet-vs-specification deviation lists.

OdysseyGPT works on the manufacturer's side of the same problem. It checks each customer requirement against your own datasheets. It gives each one a status with a quote from the source page, sheet or cell. Then it exports an editable compliance matrix and deviations & clarifications list. Your bid engineers, proposal engineers or project managers decide every open item before the offer goes out. See OdysseyGPT for manufacturing.

Buyer questions

20 questions bid engineers, proposal engineers and buyers ask. Last reviewed:

What is the difference between TBE and CBE?

TBE, technical bid evaluation, decides whether each offer meets the technical requirements. CBE, commercial bid evaluation, compares price, terms and delivery. On most engineered-equipment tenders, only offers that pass TBE go on to a full commercial comparison. The two are often done by different teams, which is why technical and commercial offers are kept apart.

What is a two-envelope tender?

A two-envelope tender asks for the technical offer and the priced offer in separate packages. The buyer opens and evaluates the technical offer first. Price is opened only for bidders found technically acceptable. That is why the technical offer is often unpriced, and why prices must not appear in it, including in the deviation list.

What is an unpriced technical offer?

It is a full copy of the technical offer with prices removed, often marked 'priced' and 'unpriced' or 'price blanked'. It lets engineers evaluate without seeing price. The priced and unpriced copies must match line for line. Some buyers ignore deviations that appear only in the priced copy, so put every technical deviation in the unpriced one.

Can a bid pass TBE with deviations?

Yes. Most technically acceptable bids carry some accepted deviations or clarifications. What matters is that each one is declared, justified and acceptable to the buyer. Deviations on key points, such as the design standard, materials or a mandatory test, are the ones most likely to make an offer technically unacceptable.

Is a TBE scored or pass/fail?

It can be either. Many EPC evaluations treat technical acceptability as pass or fail, then compare price. Others, common in public and state-owned tenders, give weighted scores against set criteria with a pass mark. The tender documents usually say which method applies. Read them before you write the offer, because it changes what to stress.

How are weighted TBE criteria set?

The buyer sets them before the tender, often in the instructions to bidders. Each criterion, such as design compliance, experience or delivery, gets a weight. Evaluators score each bid against each one. Some schemes also need a minimum score on key criteria. If weights are published, make sure your strongest evidence lines up with the heaviest ones.

What documents should a manufacturer send for TBE?

Send everything the tender lists, in the order it asks. That usually means completed datasheets, a compliance matrix, a deviation list, drawings, a draft ITP, material and certificate details, references and quality certificates. A missing mandatory document can make a bid non-responsive before the technical review even starts.

What do TBE evaluators read first?

Most start with the deviation list and the completed datasheets, because that is where differences show up. They then check the key requirements against your evidence and spot-check rows you marked compliant. A clear, cited deviation list saves them time and reduces the number of questions they send back to you.

What is a technical clarification meeting?

It is a meeting, in person or online, where the buyer and bidder work through open technical points. It often follows written clarification requests. Agreed outcomes should be minuted and then reflected in a revised offer or deviation list. Do not rely on the meeting alone; what counts in the end is the written record.

What happens if a deviation is found unacceptable?

The buyer usually asks you to withdraw it and comply, often at the cost of withdrawal you stated. Some buyers allow a revised offer; others reject the bid if the deviation is on a key point. Respond in writing, update the deviation list and price any change the way the tender asks.

What is an approved vendor list in TBE?

An approved vendor list names the manufacturers, and sometimes the works and product lines, that an owner or EPC accepts. Some tenders only accept bids from listed vendors, or ask for approval to be in place before award. Check that your company, product and manufacturing site are listed for the item offered.

What is bid equalisation?

Bid equalisation, or bid levelling, adjusts offers so they can be compared on the same basis. If one bidder excludes spares or takes a deviation, the buyer may add a cost to bring it level with the others. A clear scope and a stated cost of withdrawal let the buyer equalise your bid fairly.

How can I run a TBE on my own offer before I submit?

Build the evaluator's sheet yourself. List the key requirements in one column and fill in your offer next to each, with the evidence. Mark anything that is not clearly compliant. Our TBE matrix template has the layout. Have someone outside the bid team read it cold, the way an evaluator would.

What are common reasons a bid fails TBE?

Common reasons include undeclared deviations found by the evaluator, missing mandatory certificates or documents, offers against the wrong revision, unacceptable deviations on key points and a vendor not on the approved list. Blanket exceptions such as 'as per our standard' are another. Most of these are avoidable with a full clause-by-clause check before submission.

Does TBE cover bought-out components?

Yes. The evaluator checks the whole scope of supply, including actuators, motors, seals, instruments and other items you buy in. Where the specification lists approved sub-suppliers or makes, the evaluator checks yours against it. State the make and model of key bought-out items, and include their datasheets if the tender asks.

What certificates do evaluators expect at TBE stage?

It depends on the specification. Typical requests are a product licence or monogram where the spec calls for one, type-test reports such as fire or fugitive emission tests, quality system certificates and a statement of the material certificate type offered. Send what the tender lists, and check that each certificate is current.

What happens if I answer a TBE clarification late?

Most clarification requests carry a deadline. A late answer may be ignored, and the offer evaluated as it stands, or the bid may slip in the queue. Answer on time, even if only to confirm when the full reply will follow, and update the deviation list rather than replying in email alone.

What does a TBE recommendation say?

It states which bids are technically acceptable, which are not, and on what basis. It usually lists the deviations accepted for each acceptable bid and any conditions, such as a document to be supplied after award. The commercial team then compares only the acceptable bids. Accepted deviations should carry through to the purchase order.

Does OdysseyGPT score bids for EPC buyers?

No. OdysseyGPT is built for the manufacturer's side of the tender. It checks one manufacturer's offer documents against the customer's requirements; it does not score or rank bidders against each other. EPC teams looking for bid-scoring tools should see our overview of AI tools for that category.

How does OdysseyGPT help a manufacturer prepare for TBE?

It reads the whole tender package and checks each customer requirement against your own datasheets, standard specifications and test procedures. Each requirement gets a status with a quote and the page, sheet or cell it came from. You export an editable compliance matrix and a deviations and clarifications list. Your engineers decide every open item before submission.

Frequently asked questions

What is technical bid evaluation?

It is the buyer's check of whether each vendor offer meets the technical requirements of a tender, done before prices are compared. It produces clarification requests, a list of unacceptable deviations and a technical bid comparison.

Who will evaluate the technical bids?

On EPC projects, a discipline engineer evaluates each quotation. The lead specialist engineer is responsible for the technical evaluation. The project buyer runs clarifications, and the project manager has overall responsibility. Public tenders often use a technical evaluation committee.

What does TBE mean in procurement?

TBE stands for technical bid evaluation. It is the technical half of a two-part evaluation, where technical acceptability is decided before the commercial comparison.

How can a manufacturer improve its TBE result?

Declare every deviation with its clause, justification and cost of withdrawal. Quote values in the specification's units. Include every mandatory certificate. Keep the deviation list up to date after each technical query.

Is TBE the same as tender evaluation?

Tender evaluation is the whole process, including commercial scoring. TBE is the technical part of it. UK and public-sector buyers often say tender evaluation for both.

References

CM-PE-510 Procedure for technical evaluation of quotations

Red Bag

Visit source

OGDCL tender clarification: technical pass mark

OGDCL

Visit source

OGDCL technical evaluation report

OGDCL

Visit source

BHEL corrigendum: deviation sheet rules

BHEL

Visit source

RFP presales abstraction case study

Botminds

Vendor case study; figures are the vendor's own

Visit source

Technical bid evaluation: guide for vendor offer review

What Is Piping

Visit source

Valve procurement vendor technical scoring matrix

Vajra Industrial Solutions

Visit source

Technical bid evaluation thread

Eng-Tips

Visit source

TBE automation