Power and electrical equipment manufacturers

Transformer and switchgear manufacturers: check every tender schedule and specification clause against your documents

For tender engineers, quality engineers and contract managers at makers of power and distribution transformers, switchgear and controlgear who answer utility, EPC and industrial tenders.

By Ademola Afolabi, Founder, New Odyssey Ltd ยท Last reviewed:

The short answer

Electrical equipment manufacturers answer a utility or EPC tender by checking the technical specification, the guaranteed technical particulars schedules and the named IEC or IEEE standards against their own datasheets and type test reports. OdysseyGPT drafts the compliance matrix and deviation list from those documents, with a source quote for every row. Your engineers set each status.

Key Takeaways

  • A transformer or switchgear tender is answered twice: in the schedules of guaranteed figures and clause by clause against the specification.
  • Deviations cluster around guaranteed losses, test scope, the age and source of type test reports, accessories and tolerances.
  • After award the buyer expects an ITP, routine test reports, type test reports, calibration certificates, witnessed test records and a final dossier.
  • OdysseyGPT reads documents and quotes its sources. It runs no test and reads no single-line diagram, and engineers decide every status.

See how OdysseyGPT reviews a tender. Tell us how your team reviews tenders today. We can walk through an example together. Book a call

How do transformer and switchgear makers answer a tender?

A utility, EPC contractor or industrial owner issues a package for each equipment lot. It normally holds a technical specification, one or more datasheets, a set of schedules the bidder must fill in, a list of the IEC or IEEE standards that apply, and the buyer's own standard specifications. The schedules go by several names. In many markets they are called guaranteed technical particulars, or GTP.

The bidder has two jobs. One is to fill every line of the schedules with a figure it is prepared to guarantee. The other is to read the specification text, where the buyer sets test scope, accessories, documents and evidence, and to say where the offer differs.

  1. List every requirement in the specification, with its clause, and every line in the schedules.
  2. Fill each schedule line from the design or the standard product datasheet, and note which figures are guaranteed and which are typical.
  3. Check each called-up standard for its edition. A buyer's specification may cite an edition older than the one your type tests were made to.
  4. Match the test requirements to the type test reports you hold and to the routine tests your works performs on every unit.
  5. Mark each row complies, deviates, clarification or not addressed, and write the reason.
  6. Price what the standard offer leaves out: repeated type tests, special tests, witnessed tests and extra accessories.

The output is a compliance matrix that covers every clause and a technical deviation list that carries only the differences. Some buyers ask for the deviations on their own schedule form and treat anything not listed there as accepted.

Which standards come up in transformer and switchgear tenders?

Most tenders name a product series and leave the bidder to work out which parts apply. The table lists the series that appear most often, at name level. It is our own summary. Use the edition your contract names.

Standards named in transformer and switchgear tenders (own summary)
SeriesWhat it coversWhere the tender usually pins it down
IEC 60076Power transformers: general requirements, temperature rise, insulation levels and dielectric tests, short-circuit withstand, sound levels, dry-type units and moreWhich tests are routine, type or special for this order, and which type test reports are accepted
IEC 62271High-voltage switchgear and controlgear above 1 kV: common specifications, circuit-breakers, disconnectors, metal-enclosed assemblies and gas-insulated switchgearRatings, internal arc classification, service continuity category and the type tests to be evidenced
IEC 61439Low-voltage switchgear and controlgear assemblies. Part 1 gives general rules and Part 2 covers power switchgear and controlgear assembliesDesign verification evidence for the assembly offered, and the routine verification done on each assembly
IEEE C57 seriesTransformers where the buyer works to IEEE. C57.12.00 gives general requirements for liquid-immersed units and C57.12.90 is the matching test codeWhether the whole order is to IEEE or a mix. The test categories and terms are not the same as in IEC
Component standardsBushings, tap-changers and insulating liquid each have their own IEC standard, and IEC 60076-1 refers to themNamed makes or approved-vendor lists for components, and the certificates wanted for each
Buyer and national specificationsUtility standard specifications and national adoptions that add to or change the IEC textExtra tests, lower loss limits, a maximum age for type test reports and a list of acceptable laboratories

A specification can name IEC and IEEE documents side by side. Do not assume the two give the same answer. If the order of precedence is not stated, ask.

What goes in the deviation list for electrical equipment?

The deviation list carries each point where the offer differs from the tender, with the clause, what is offered and why. For transformers and switchgear the same few areas come up in most offers.

Where transformer and switchgear offers most often differ from the tender (own summary)
AreaWhat to check before you sign the offer
Losses and other guaranteesWhether the no-load loss, load loss, impedance and sound figures in the schedule are guaranteed maximums, and what the tender says happens if the tested figure is worse
TolerancesWhether the buyer accepts the tolerances of the named standard or sets its own, including figures stated with no positive tolerance
Test scopeWhich tests the tender moves from type or special into the routine list for every unit, and which it wants witnessed
Type test evidenceWhether an existing report is accepted, how old it may be, how close the tested design must be to the one offered, and which laboratories the buyer accepts
Accessories and fittingsTap-changer, bushings, cooling equipment, monitoring and protection devices, cable boxes and terminals, compared with your standard scope
Components and sub-suppliersNamed makes for major components, and whether alternatives need approval before award
Service conditionsAltitude, ambient temperature, pollution and seismic figures that differ from the normal conditions the standard assumes
Documents and approvalDrawing approval steps, the document schedule, languages and the number of review cycles allowed in the programme

Read the evaluation clauses before you declare a deviation

Many utility tenders evaluate losses in money and add the result to the bid price. Some state that an offer with missing schedule entries or with deviations from named clauses may be rejected. Find those clauses first, then decide whether a gap goes in as a deviation, a clarification question or a priced alternative.

Which documents follow after award?

After the order, the buyer's document schedule turns the tender requirements into submissions. The contract decides the list. These are the ones a transformer or switchgear maker should expect.

Post-award documents for transformers and switchgear (own summary)
DocumentWhat the buyer looks for
Inspection and test plan (ITP)Every works inspection and test in order, the procedure and acceptance basis for each, and the buyer's hold and witness points
Type test reportsThe design tested, the standard and edition, the laboratory, the date and the tests covered, and a statement of how the tested unit relates to the one ordered
Routine test reportsOne report per unit by serial number, each required test present, and results set against the guaranteed figures
Calibration certificates for test instrumentsA valid, traceable certificate for each instrument named in a test report on the day it was used
Witnessed test and FAT recordsThe notice given, who attended, the signed results and a closed punch list. See FAT vs SAT
Component certificatesTest certificates for bushings, tap-changers, instrument transformers, relays and insulating liquid, as the contract lists them
Operation and maintenance manualsInstallation, commissioning, operation and maintenance instructions in the contract language, with as-built drawings
Final documentation dossierAll of the above in the buyer's index order, at the approved revision and signed where the contract says so

For the instrument evidence, see the guide to calibration certificates for test reports. A checklist for the reports themselves is on the routine test report checklist template page.

How does OdysseyGPT help?

OdysseyGPT reads the documents you upload and checks them against the customer's written requirements. Each finding shows the passage it rests on in both documents. Document Review takes the tender specification as the base and your datasheets, filled schedules, type test report summaries and standard offer text as the documents to check. It works forward and in reverse, and it exports an editable compliance matrix with a deviations and clarifications list. The other tools each take a narrower set of documents.

Transformer and switchgear documents and the tool that reads each
Your documentToolWhat it reports
Tender specification, schedules and your offer documentsDocument ReviewA status and a pair of quotes for each tender requirement, plus obligations in your documents the tender does not answer
Tender specification and the buyer's standard specificationsCustomer Specification Review (beta)A requirements register: one line per obligation for ratings, tests, accessories and documents, with its clause
The buyer's datasheet or schedule and your filled copyDatasheet Comparison (beta)Matched fields and every material difference in value, with the cell each figure came from
Offers from your component sub-suppliersTechnical Bid Evaluation (beta)Each sub-supplier's answer to one requirement baseline, with declared and undeclared deviations. It does not pick a winner
Offer, clarification replies and the deviation scheduleDeviation Register (beta)One running record of each deviation through the clarification rounds to the buyer's decision
The contract document scheduleVDRL/MDR Tracker (beta)A register of each contractual submission with its due date and status
Your ITP and the buyer's quality and test clausesITP Validator (beta)Tests the buyer asks for that the plan omits, and hold or witness points that do not match
Evidence for a witnessed inspection stageInspection Readiness Check (beta)A readiness verdict for the stage, with blockers listed apart from advisory items
Routine test reports and calibration certificatesCalibration Validity Check (beta)Each instrument named in a report matched to its certificate and checked for validity on the test date
FAT procedure, approved drawings, ITP status and open itemsFAT Readiness Check (beta)Whether the documents a witnessed test depends on are in place before the buyer travels
Final dossier folder and the buyer's indexMRB Readiness Check (beta) and MRB Compiler (beta)Documents that are missing, unapproved or at the wrong revision, and a manifest in index order

The tools sit in three stage groups: tender, inspection and handover. The wider picture is on the manufacturing page.

What does a result look like?

This table is an invented example. The utility, the transformer, the clause numbers, the maker's documents and every figure are made up to show the layout of a result. None of it comes from a real tender, a real manufacturer or a standard.

Invented example: a tender for a 40 MVA, 132/33 kV power transformer, checked against a maker's documents
Tender requirement (quoted)Maker's document (quoted)StatusNote
"Rated power 40 MVA at ONAF cooling, vector group YNd11." (Schedule A, lines 3 and 7)"Rating: 30/40 MVA ONAN/ONAF. Vector group: YNd11." (GTP schedule, lines 3 and 7)CompliesSame rating basis and vector group in both documents.
"No-load loss at rated voltage shall not exceed 18 kW. No positive tolerance is permitted." (Specification 5.2)"No-load loss: 18 kW, subject to IEC tolerance." (GTP schedule, line 21)DeviatesThe figure matches but the maker reserves a tolerance the tender excludes.
"The temperature rise test shall be carried out on one unit of the order." (Specification 9.3)"Temperature rise: type test report TR-2219 for an identical design is offered in lieu." (Offer letter, p. 4)DeviatesA report is offered in place of a new test. Decide whether to price the test as an option.
"Type test reports shall be from an independent accredited laboratory and not more than five years old at bid opening." (Specification 9.1)"Short-circuit withstand test report, dated March 2019." (List of type test reports, item 2)ClarificationThe report date falls outside the stated period. The laboratory's accreditation is not stated in the list.
"The on-load tap-changer shall be of a make listed in Annex C." (Specification 6.4)"On-load tap-changer: vacuum type, 17 positions." (Datasheet DS-40-132, p. 3)ClarificationThe make is not stated in the datasheet.
"Frequency response measurement shall be made on each unit before dispatch and the records supplied." (Specification 9.6)No matching statement found in the documents supplied.Not addressedNot in the maker's routine test list. Add it to the offer or declare it.
"Routine tests shall be witnessed by the Purchaser. Fourteen days' written notice shall be given." (Specification 9.8)"The purchaser may witness routine tests. Notice of test: 7 days." (Quality plan QP-11, p. 6)DeviatesThe notice period offered is shorter than the tender asks for.
"Calibration certificates for all instruments used in the tests shall be included in the test report." (Specification 9.9)"Test instruments are calibrated at intervals set by our procedure." (Quality plan QP-11, p. 7)ClarificationThe maker's text does not say the certificates are supplied with the report.

A tender engineer opens the two quotes on each row and confirms or changes the status. The rows that stay as deviates or clarification feed the deviation schedule and the list of questions to the buyer.

Where OdysseyGPT falls short

  • It performs no test and measures nothing. It is not test-bay software, it does not connect to test equipment, and it does not produce a test report.
  • It does no design work. It does not calculate losses, impedance, temperature rise, short-circuit forces or busbar ratings, and it cannot tell you whether a guaranteed figure is achievable.
  • It does not read single-line diagrams, general arrangement drawings, wiring diagrams or rating plate drawings. A requirement that appears only on a drawing is not checked.
  • It does not judge whether a type test report covers the design you offer. It can show what the report states and what the tender asks for. An engineer decides whether the tested unit is close enough.
  • It holds no standards. A limit that sits only inside IEC 60076, IEC 62271 or an IEEE document is checked only if you upload the edition and it is readable text.
  • It can pair a requirement with the wrong line or miss one, most often in long schedules with repeated row labels. The quotes are there so that a person can catch this.
  • It does not fill in the buyer's schedules for you, submit anything to a tender portal or set a price.
  • Tools carrying a beta marker on this page are available on request, and we set each team up ourselves.

Talk through your tender review

See how OdysseyGPT reviews a tender

Tell us how your team reviews tenders today. We can walk through an example together.

Book a call

Buyer questions

20 questions bid engineers, proposal engineers and buyers ask. Last reviewed:

What is in a transformer tender technical specification?

Usually a scope of supply, service conditions, ratings, the standards that apply, construction and accessory requirements, a test section, and the documents wanted with the offer and after award. Beside it sit the schedules the bidder fills in with guaranteed figures. Read both. Requirements on tests, evidence and documents often appear only in the text and have no schedule line.

What are guaranteed technical particulars?

They are the tender schedules in which the bidder states the technical figures it commits to, such as ratings, losses, impedance and temperature rise. The filled schedule becomes part of the contract, and test results are compared with it later. See the glossary entry on guaranteed technical particulars for how they differ from a datasheet and a compliance matrix.

Which standards does a transformer tender usually name?

Most name the IEC 60076 series for the transformer, plus separate IEC standards for bushings, tap-changers and insulating liquid. Buyers who work to North American practice name IEEE C57 standards. Utilities often add their own standard specification on top. Check each for its edition and ask which document governs if they conflict. See the IEC 60076 page.

Which standards does a switchgear tender usually name?

For equipment above 1 kV, the IEC 62271 series: Part 1 for common specifications, Part 100 for circuit-breakers and Part 200 for metal-enclosed assemblies up to 52 kV are the usual ones. Low-voltage assemblies fall under IEC 61439. Some buyers use IEEE C37 standards. The IEC 62271 page lists the parts tenders cite most often.

What is the difference between routine, type and special tests?

Routine tests are made on every unit to check manufacture. Type tests are made on one representative unit to prove the design. Special tests, a category in IEC 60076-1, are made only when the purchaser asks for them. A tender can move a test from one category to another, so compare its test list with the standard. See type test vs routine test.

Can we offer existing type test reports in place of new tests?

Only if the tender allows it. Buyers commonly accept a report for the same or a closely similar design, and many add conditions on its age and on the laboratory that issued it. If your report does not meet a condition, say so in the deviation list and offer the test as a priced option. Do not leave it for the buyer to find.

What goes in the deviation list for a transformer offer?

Every point where the offer differs from the tender, with the clause, what you offer and why. Common entries are guaranteed losses and tolerances, tests offered by report in place of a new test, special tests not included, alternative component makes, accessories outside your standard scope and document approval terms. The technical deviation list guide gives a format.

How are transformer losses treated in a tender?

The bidder states guaranteed no-load and load losses in the schedule. Many buyers convert those figures to money with a stated rate and add the result to the bid price when comparing offers. The contract may then set a penalty, or a right to reject, if the tested losses are worse than guaranteed. Read the evaluation and penalty clauses before fixing the figures.

Do the standard's tolerances apply to our guaranteed values?

Only where the contract does not say otherwise. IEC 60076-1 has a tolerances clause, but many utility specifications replace it, and some allow no tolerance above the guaranteed loss. If your schedule says a figure is subject to the standard tolerance and the tender excludes it, that is a deviation. State it openly or change the figure.

What if the buyer specifies IEEE standards and our design is to IEC?

Treat it as a deviation or a clarification, not a detail. IEEE C57.12.00 and its test code C57.12.90 use different test categories, names and rating conventions from IEC 60076. An IEC type test report may not answer an IEEE requirement line for line. Ask the buyer whether IEC equipment is acceptable and on what evidence, before you price.

What does an internal arc classification in a switchgear tender mean?

It is a classification under IEC 62271-200 for metal-enclosed switchgear that has passed an internal arc test. The designation gives the accessibility type, the sides that met the criteria, and the arc current and duration tested. It concerns the protection of people near the assembly. Check each element of the tender's designation against your type test report and its installation conditions.

Which documents does the buyer expect after award?

Drawings for approval, an inspection and test plan, type test reports, a routine test report for each unit, calibration certificates for the test instruments, records of witnessed tests, component certificates, manuals and a final dossier in the buyer's index order. The contract's document schedule sets the exact list, the due dates and how many review cycles each submission gets.

What should a routine test report contain?

The unit's serial number and rating, the standard and edition, each test made with its result, the guaranteed figure it is compared with, the instruments used, the date and the signatures the contract asks for. Buyers reject reports where a required test is missing or an instrument cannot be traced to a certificate. A checklist is on the routine test report checklist template page.

Why do buyers ask for calibration certificates with test reports?

A measured loss or a dielectric test result is only as good as the instrument behind it. Buyers want a traceable certificate for each instrument, valid on the day of the test. Calibration Validity Check (beta) reads the test reports, lists the instruments named and matches each to its certificate. It flags any that had expired or cannot be matched.

What does the buyer check in a transformer or switchgear ITP?

That every test in the contract appears in the plan, with its procedure, acceptance basis and record, and that hold and witness points match the buyer's quality clauses. ITP Validator (beta) compares your plan with those clauses and lists tests the plan omits and intervention points that differ. Your quality engineer decides what to change.

How do we prepare documents for a witnessed factory test?

Confirm the test procedure and drawings are approved, the ITP stage is released, instruments are in calibration, non-conformances are closed and the notice has been given. FAT Readiness Check (beta) reads those documents and returns a readiness verdict, with blockers listed apart from review items. It checks paperwork only. It does not run or supervise the test.

How does OdysseyGPT review a transformer or switchgear tender?

Document Review takes the tender specification as the base and your datasheets, filled schedules and offer text as the documents to check. For each requirement it gives a status and quotes both documents. It also lists statements in your documents the tender does not answer. It exports an editable compliance matrix and a deviations and clarifications list. Engineers confirm every row.

Does OdysseyGPT read single-line diagrams and drawings?

No. It reads text documents: PDF, Word, Excel and CSV. It does not interpret single-line diagrams, general arrangement drawings, wiring diagrams or rating plate drawings. A requirement that appears only on a drawing will not be checked, so an engineer still has to review the drawings. Requirements written in a specification, schedule or datasheet are within reach.

Does OdysseyGPT calculate losses or run tests?

No. It does not perform design calculations, and it cannot tell you whether a guaranteed loss, impedance or temperature rise is achievable. It is not test-bay software and does not connect to test equipment. It compares what your documents state with what the customer's documents require, and shows the quote behind each finding so that an engineer can decide.

Which OdysseyGPT tools can a transformer or switchgear maker use now?

Document Review is generally available. The tools named on this page with a beta marker, such as Datasheet Comparison (beta) and ITP Validator (beta), are offered on request, and we set each team up ourselves. Ask through the product page for the tool you need, and say which documents you want to check.

Frequently asked questions

Who prepares the technical offer at a transformer or switchgear manufacturer?

Usually a tender or proposals engineer, working with electrical design for the guaranteed figures, the test department for test scope and type test evidence, and quality for the ITP, certificates and document schedule.

Does OdysseyGPT test transformers or switchgear?

No. It reads documents such as specifications, schedules, datasheets and test reports, and checks them against the customer's written requirements with a quote for every finding. Tests are carried out by the manufacturer or a laboratory.

Can OdysseyGPT read guaranteed technical particulars schedules in Excel?

Yes. It reads PDF, Word, Excel and CSV files and cites the sheet and cell for a value taken from a spreadsheet. It does not read drawings or single-line diagrams.

What if a tender names both IEC and IEEE standards?

Raise a clarification on which governs and in what order. The two families use different test categories and terms, so an offer written to one may not answer the other.

References

IEC 60076-1:2011 Power transformers. Part 1: General

IEC

Paid standard. Catalogue page and public preview used for scope, clause headings and the informative checklist of information for enquiry and order.

Visit source

IEC 62271-200:2021 High-voltage switchgear and controlgear. Part 200: AC metal-enclosed switchgear and controlgear for rated voltages above 1 kV and up to and including 52 kV

IEC

Paid standard. Catalogue page and public preview used for scope and clause headings.

Visit source

IEC 62271 series: High-voltage switchgear and controlgear, all parts

IEC

List of the parts in the series.

Visit source

IEC 61439-1: Low-voltage switchgear and controlgear assemblies. Part 1: General rules

IEC

Paid standard. Use the edition your contract names.

Visit source

IEEE Transformers Committee

IEEE Power & Energy Society

Home of the IEEE C57 transformer standards, including C57.12.00 and C57.12.90.

Visit source

High energy consumption equipment: evaluation of capitalised losses

CERN Procurement Service

A public example of a buyer adding the cost of losses to the bid price.

Visit source