What a factory acceptance test is
A factory acceptance test is a set of tests at the manufacturer's works that shows the equipment meets the purchase order before it ships. The customer, its inspector or a third-party inspector often witnesses it. For valves this is usually the pressure tests and functional checks; for pumps it often includes a performance test and, where ordered, vibration, noise or mechanical run tests. The order's own procedure decides what is in scope.
The FAT is normally a witness or hold point in the inspection and test plan (ITP). After it, the customer may sign an inspection release that lets you ship. A site acceptance test (SAT) comes later, after installation.
Documents checklist
- FAT procedure approved by the customer, at the current revision, with the acceptance criteria stated.
- Approved drawings and datasheets at the revision the procedure refers to.
- The ITP, with every earlier hold point signed off.
- Material certificates and NDE reports for the parts under test, checked and filed.
- Calibration certificates for every gauge, transducer and recorder you will use.
- Test record sheets ready to fill in, with tag and serial numbers already entered.
- Agreed deviations and concessions that change what is tested or how.
Instruments and calibration
Inspectors check that each instrument on the test record was in calibration on the day of the test, has a range suited to the test, and traces to a national standard. An expired gauge can void the result and force a repeat. List each instrument by its ID, check its certificate expiry against the planned date, and have a spare ready. See calibration certificates for test reports.
Open issues: NCRs and punch list
Go through the NCR register and the punch list. Any nonconformance on a part under test should be closed or have a disposition the customer has agreed before the FAT. Other open items should be listed, so the witness sees them on paper first. A surprise during the test costs more time than a known item on a list.
Notice and witness arrangements
The ITP or purchase order sets how much notice the customer needs for a witness point. Send the notice in writing, with the date, the tests, the procedure revision and the location. Confirm who is coming, including any third-party inspector, and whether they need site safety induction. If the date moves, send a new notice.
On the day
- Hold a short start meeting: scope, procedure revision, safety and the order of tests.
- Show the inspector the instrument list and calibration certificates before testing starts.
- Record the actual values, not just pass or fail, on the agreed sheets.
- Log any failure or deviation as it happens, with what was done next.
- Get the records signed before the inspector leaves, and agree any open items in writing.
Valve and pump specifics
For valves, the test standard is usually named in the order, such as API 598 or the tests in API 6D. Check which one governs, the test media and the durations in the approved procedure. See API valve standards. For centrifugal pumps to API 610, the datasheet says which tests are witnessed or observed. See API 610 pump datasheet review. Do not rely on generic test values; use the order's procedure.
Doing it with OdysseyGPT
The FAT Readiness Check (beta) reads the FAT procedure with the drawings, datasheets, ITP, calibration evidence, NCR register and punch list. It gives a readiness verdict and keeps hard blockers apart from review items, each with a citation. The Calibration Validity Check (beta) checks each instrument against its certificate on the test date. Your test and quality team decides whether to go ahead.