Glossary term
Type Test vs Routine Test
A type test proves a design and is made on a representative unit. A routine test checks manufacture and is made on every unit delivered. Electrical equipment standards use both terms.
Last reviewed by the OdysseyGPT team
What it is
A type test is made on a representative unit to prove that a design meets its ratings, and its report is reused as evidence. A routine test is made on every unit delivered to find manufacturing faults. IEC 60076 for transformers and IEC 62271 for switchgear both use the two terms, and tenders often add conditions to each.
Key Takeaways
- Type tests prove the design. Routine tests check each unit.
- IEC 60076-1 adds special tests, made only at the purchaser's request.
- IEC 61439 calls the same split design verification and routine verification.
- Check the age, laboratory and tested design of every type test report against the tender.
Why it matters
Standards for electrical equipment separate the tests that prove a design from the tests that check each unit built. A type test is made on one unit, or a small number, that represents the design. It shows that the design can meet its ratings. Because it can be long, costly or hard on the equipment, it is not repeated for every order. The result is a type test report that the maker offers as evidence in later tenders. A transformer type test such as the temperature rise test is a common example. For metal-enclosed switchgear under IEC 62271-200, type tests include dielectric tests, short-time and peak withstand current tests and, where a classification is claimed, the internal arc test. A routine test is made on every unit delivered. It is there to find faults in materials and workmanship and to confirm the unit matches the tested design. For a transformer the routine tests include loss, impedance and ratio measurements. For switchgear they include a dielectric test on the main circuit, a resistance measurement and mechanical operation tests. IEC 60076-1 adds a third category, the special test, made only when the purchaser asks. Low-voltage assemblies under IEC 61439 use different words for the same split: design verification and routine verification. In a tender the question is rarely the definition. It is whether the buyer accepts an existing type test report, how old it may be, which laboratory made it and how close the tested unit is to the one offered.
How OdysseyGPT uses it
Document Review compares the tender's test and evidence clauses with your list of type test reports, routine test procedure and offer text, and quotes both documents for each row. It can show that a report's date, laboratory or stated design differs from what the tender asks. It does not decide whether a tested design represents the unit you offer. That is an engineer's judgement.
Evaluation questions
What should a list of type test reports show in an offer?
For each report: the equipment and design tested, the standard and edition, the tests covered, the laboratory, the report number and the date. Add a line on how the tested unit relates to the one offered.
Frequently asked questions
Can an existing transformer type test report be used for a new order?
Often, if the contract allows it. Buyers usually set conditions: the tested unit must be of the same or a closely similar design, the report must be recent enough, and it must come from a laboratory they accept. Check the tender for each condition.
What is a special test?
In IEC 60076-1 it is a test other than a routine or type test that is made by agreement when the purchaser asks for it. Whether it is included in the price is a matter for the offer.
Is design verification the same as a type test?
It does the same job for low-voltage assemblies under IEC 61439, but it is wider. Design verification can be shown by test or by other routes the standard allows for each characteristic. Routine verification is then made on every assembly.
References
IEC 60076-1:2011 Power transformers. Part 1: General
IEC
Paid standard. Catalogue page and free preview used for scope and clause headings.
IEC 62271-200:2021 High-voltage switchgear and controlgear. Part 200: AC metal-enclosed switchgear and controlgear for rated voltages above 1 kV and up to and including 52 kV
IEC
Paid standard. Catalogue page and free preview used for clause headings.
Guide to switchgear and controlgear assemblies to BS EN 61439
BEAMA
A trade association guide to design verification and routine verification.