Glossary term
Guaranteed Technical Particulars
The schedule in an equipment tender where the bidder states the technical figures it guarantees, such as ratings, losses and impedance. Often shortened to GTP.
Last reviewed by the OdysseyGPT team
What it is
Guaranteed technical particulars, or GTP, are the schedules in an equipment tender where the bidder states the technical figures it guarantees, such as ratings, losses, impedance and temperature rise. The filled schedule becomes part of the contract, and test results are later compared with it. Requirements in the specification text still need a separate answer.
Key Takeaways
- A GTP is a schedule of figures the bidder commits to for one tender.
- Tested values in the routine test report are compared with it.
- Losses stated in it may be evaluated in money and carry penalties.
- It does not replace a clause-by-clause compliance matrix.
Why it matters
Guaranteed technical particulars, or GTP, are the schedules in a tender in which the bidder writes the technical data of the equipment it offers and commits to them. The term is common in utility and EPC tenders for transformers, switchgear, cables and other electrical equipment, for example in South Asia and Africa. Other buyers call the same thing technical schedules, technical data sheets or schedules of guaranteed particulars. A transformer GTP usually has a line for each rating, voltage, tapping range, connection symbol, impedance, no-load and load loss, temperature rise, insulation level, sound level, mass and dimension, plus the make and type of major components. The buyer may fill one column with its requirement and leave the next for the bidder. The word guaranteed matters. The filled schedule becomes part of the contract, and the tested values in the routine test report are later compared with it. Many tenders evaluate the stated losses in money when comparing bids, and set a penalty or a right to reject if the tested losses are worse than guaranteed. Some require the manufacturer to sign every page, and some state that an offer with blank lines may not be considered. A GTP is not a compliance matrix. It answers the buyer's data questions line by line, while the specification text around it carries requirements on tests, accessories, documents and evidence that have no line in the schedule. A complete offer answers both, and lists any difference as a deviation.
How OdysseyGPT uses it
Datasheet Comparison (beta) compares the buyer's schedule with your filled copy and lists the fields whose values differ, citing the cell each came from. Document Review checks the specification text around the schedules against your offer documents. Neither fills in the schedule or works out a figure for you, and neither can say whether a guaranteed value is achievable. Your design engineers own the numbers.
Evaluation questions
How do you check a GTP before submission?
Compare every line with the buyer's required value and with your design data. Check the units and the basis of each figure, confirm no line is blank, and make sure anything that differs from the requirement also appears in the deviation schedule.
Frequently asked questions
Is a GTP the same as a datasheet?
They hold similar data. The difference is the commitment. A datasheet may give typical values for a product. A GTP is filled in for one tender, and the bidder is held to the figures in it.
Is a GTP the same as a compliance matrix?
No. A GTP records the data of the equipment offered. A compliance matrix goes through the specification clause by clause and states whether the offer complies. Most tenders need both.
What happens if a tested value is worse than the guaranteed figure?
The contract decides. Depending on its wording and any tolerance it allows, the buyer may accept the unit, apply a penalty or reject it. Read those clauses before you fill in the schedule.
References
Guaranteed particulars for power transformer (tender annex)
Central Electricity Board, Mauritius
A public example of a guaranteed particulars schedule issued with a utility tender.
High energy consumption equipment: evaluation of capitalised losses
CERN Procurement Service
A public example of a buyer adding the cost of stated losses to the bid price.
IEC 60076-1:2011 Power transformers. Part 1: General
IEC
Paid standard. Catalogue page and free preview used for scope and clause headings.