FAT vs SAT

A factory acceptance test (FAT) proves equipment at the manufacturer's works before shipment. A site acceptance test (SAT) proves it again after installation at the buyer's site.

Last reviewed by the OdysseyGPT team

What it is

A factory acceptance test (FAT) is run at the manufacturer's works before shipment to show the equipment meets the order. A site acceptance test (SAT) is run after installation to show it works in its real setting. A passed FAT does not replace the SAT.

Key Takeaways

  • FAT: at the factory, before shipment. SAT: at site, after installation.
  • Faults are cheapest to fix at the FAT.
  • The order, specification and ITP say which tests are witnessed.
  • Most failed FATs fail on paperwork: procedures, calibration and open NCRs.

Why it matters

A factory acceptance test (FAT) is run at the manufacturer's works before the equipment ships. The buyer or an inspector witnesses the tests in an agreed procedure, such as pressure, function and performance tests, and reviews the supporting records. Faults found at the FAT are fixed where the tools, parts and people are. A site acceptance test (SAT) is run after delivery and installation. It confirms the equipment survived transport, was installed correctly and works with the site's own piping, power, controls and process conditions. The two tests answer different questions, so a passed FAT does not replace the SAT. The purchase order, the specification and the inspection and test plan say which tests are required at each stage and who must witness them.

How OdysseyGPT uses it

FAT Readiness Check (beta) reads the FAT procedure with the drawings, datasheets, inspection and test plan, calibration evidence, NCR register and punch list, and reports whether the test is ready to run, with blockers listed. It works on the documents before the FAT. It does not run tests, and OdysseyGPT has no site acceptance test tool.

Evaluation questions

What documents are needed before a FAT?

An approved FAT procedure, current drawings and datasheets, the inspection and test plan, valid calibration certificates for the test instruments, closed or agreed NCRs, and the witness notification sent in time.

Frequently asked questions

What is the difference between FAT and SAT?

Place and purpose. The FAT is at the factory before shipment and shows the equipment meets the order. The SAT is at site after installation and shows it works in its real setting.

Is a SAT needed if the FAT passed?

Usually yes, where the contract calls for one. Transport, installation and site interfaces can all introduce faults the FAT could not see. The contract and specification decide.

Who attends a FAT?

The manufacturer's test and quality staff, and the buyer's engineer or a third-party inspector where the inspection and test plan marks the test as a witness or hold point.