FAT readiness checklist template: what must be ready before the inspector arrives (Excel and CSV)

A pre-FAT checklist for equipment manufacturers: approved procedure, earlier ITP steps closed, calibration valid on the test date, material accepted, NCRs closed, documents and logistics.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

A FAT readiness checklist confirms, before you notify the customer, that a factory acceptance test can go ahead: approved procedure, earlier inspection steps closed, instruments calibrated for the test date, material accepted, open non-conformances resolved and the inspector's pack ready. This free Excel template lists those checks with owners and due dates.

Key Takeaways

  • Complete it before the inspection notification goes out, not on the morning of the test.
  • Every row names the PO clause, specification clause or ITP step that asks for it, and the evidence.
  • Calibration must be valid on the test date, not only on the day you check.
  • The example has 11 checks for an invented ball valve order (PO-EX-3105).

Download the FAT readiness checklist

Both files are free under CC BY 4.0, with no form to fill in. The XLSX opens in Excel, Google Sheets, LibreOffice and Numbers. The CSV carries the table only; the header block is in the XLSX.

What it is for and who uses it

A factory acceptance test (FAT) that starts with a missing procedure approval or an expired gauge certificate wastes the inspector's trip and often the slot. This checklist is the go/no-go before the notification. For what the test itself covers, see the factory acceptance test checklist guide.

  • Test engineers who prepare the bench and the procedure.
  • Quality engineers who close NCRs and earlier ITP steps.
  • Project managers who send the notification.

Example rows: pre-FAT check for a valve order

Invented example rows for PO-EX-3105 (some columns omitted)
ItemCategoryCheckRequired byEvidenceStatusRemarks
1ProcedureTest procedure approved by the customer, at the revision that will be usedVDRL B02TP-BV-02 Rev A, returned code 2Not readyRev B with comments answered to be issued.
2DocumentsITP approved, and every step before the FAT is done or releasedITP-BV-01ITP-BV-01 Rev A, steps 1-6Not readyStep 4 NDE reports pending for two bodies.
3LogisticsInspection notification sent to the customer and third party with the notice period the PO requiresPO clause 12Not readySend only when items 1-2 are ready.
4CalibrationPressure gauges and recorders calibrated, with certificates valid on the test date and ranges suited to the test pressuresTP-BV-02 section 5Calibration certificates CAL-0412, CAL-0413ReadyCAL-0413 expires 2027-02-02: still valid on the test date.
5EquipmentTest bench, blanks and fittings rated for the test pressureTP-BV-02 section 4Bench rating plate recordReady
6EquipmentTest medium meets the procedure (for example water quality where the specification sets limits)TP-BV-02 section 6Water analysis WA-2027-01Ready
7MaterialMaterial certificates for pressure-containing parts reviewed and acceptedITP-BV-01 step 2Certificate review checklist MTRC-EX-3105Ready
8QualityOpen non-conformances closed, or concessions approved by the customerQP-01 section 10NCR logNot readyNCR-118 awaiting customer concession.
9DocumentsAgreed deviations reflected in the test procedure and in the inspector's packTDL-EX-2291 Rev BTP-BV-02; inspector packReadyEX-08: API 6D tests accepted.
10DocumentsInspector's pack prepared: approved drawings, ITP, procedure, certificates, calibration certificates, blank test reportsITP-BV-01Not ready
11LogisticsSafety briefing, access and PPE arranged for visitorsSite rulesReady

The file also has columns for owner and due date. Every example value is invented: the project, customer, purchase order and every document, certificate, heat and report number do not exist. Standards are named but not quoted.

Columns and what to write

ColumnWhat to write
ItemRunning number.
CategoryDocuments, Procedure, Equipment, Calibration, Material, Quality or Logistics (drop-down).
CheckWhat must be true before the customer's inspector arrives.
Required byPO clause, specification clause or ITP step that asks for it.
EvidenceThe document or record that shows it is done, with number and revision.
StatusReady, Not ready or Not applicable (drop-down). Not ready rows turn red.
OwnerWho closes the item.
DueDate it must be closed, before the notification goes out (YYYY-MM-DD).
RemarksAnything else the inspector should know.

How to use the template

  1. Fill in the header block: purchase order, the tests to be witnessed, the ITP steps they cover and the planned FAT date.
  2. List every condition that must be true before the inspector arrives: approved procedure, completed earlier ITP steps, calibration, material, open NCRs, documents and logistics.
  3. For each row, name the PO clause, specification clause or ITP step that asks for it, and the evidence that shows it is done.
  4. Set the status. Not ready rows turn red. Give each one an owner and a due date before the notification goes out.
  5. Send the inspection notification only when every row is Ready or Not applicable, with the notice period the PO requires.
  6. Take the checklist to the pre-FAT meeting, and keep the final copy with the test records.

Checking readiness from the documents

In OdysseyGPT's Inspection & Testing module, FAT Readiness Check (beta) and Calibration Validity Check (beta) read the ITP, procedures, certificates and reports and show what is still missing or out of date before a FAT. Every finding cites the page it came from, and your engineers decide what to do with it. These tools are in beta: you can request access, and we onboard each team ourselves.

Want us to run the check for you?

Send your ITP and the customer's quality requirements. We send back what is covered, what is missing and what still needs evidence before the FAT.

Get the free ITP and FAT readiness check

New templates by email (optional)

Your download does not depend on this.

We use your email only for this. See our privacy policy.

Frequently asked questions

What should be checked before a factory acceptance test?

That the test procedure is approved, earlier inspection steps are closed, instruments are calibrated and valid on the test date, material certificates are accepted, open non-conformances are closed or conceded, agreed deviations are reflected in the procedure, and the inspector's pack is ready.

Is there a free FAT checklist template in Excel?

Yes. This XLSX template has a blank checklist, a filled-in example for an invented valve order and a How to use sheet. A CSV of the same columns is also free under CC BY 4.0.