What it is for and who uses it
A factory acceptance test (FAT) that starts with a missing procedure approval or an expired gauge certificate wastes the inspector's trip and often the slot. This checklist is the go/no-go before the notification. For what the test itself covers, see the factory acceptance test checklist guide.
- Test engineers who prepare the bench and the procedure.
- Quality engineers who close NCRs and earlier ITP steps.
- Project managers who send the notification.
Example rows: pre-FAT check for a valve order
| Item | Category | Check | Required by | Evidence | Status | Remarks |
|---|---|---|---|---|---|---|
| 1 | Procedure | Test procedure approved by the customer, at the revision that will be used | VDRL B02 | TP-BV-02 Rev A, returned code 2 | Not ready | Rev B with comments answered to be issued. |
| 2 | Documents | ITP approved, and every step before the FAT is done or released | ITP-BV-01 | ITP-BV-01 Rev A, steps 1-6 | Not ready | Step 4 NDE reports pending for two bodies. |
| 3 | Logistics | Inspection notification sent to the customer and third party with the notice period the PO requires | PO clause 12 | Not ready | Send only when items 1-2 are ready. | |
| 4 | Calibration | Pressure gauges and recorders calibrated, with certificates valid on the test date and ranges suited to the test pressures | TP-BV-02 section 5 | Calibration certificates CAL-0412, CAL-0413 | Ready | CAL-0413 expires 2027-02-02: still valid on the test date. |
| 5 | Equipment | Test bench, blanks and fittings rated for the test pressure | TP-BV-02 section 4 | Bench rating plate record | Ready | |
| 6 | Equipment | Test medium meets the procedure (for example water quality where the specification sets limits) | TP-BV-02 section 6 | Water analysis WA-2027-01 | Ready | |
| 7 | Material | Material certificates for pressure-containing parts reviewed and accepted | ITP-BV-01 step 2 | Certificate review checklist MTRC-EX-3105 | Ready | |
| 8 | Quality | Open non-conformances closed, or concessions approved by the customer | QP-01 section 10 | NCR log | Not ready | NCR-118 awaiting customer concession. |
| 9 | Documents | Agreed deviations reflected in the test procedure and in the inspector's pack | TDL-EX-2291 Rev B | TP-BV-02; inspector pack | Ready | EX-08: API 6D tests accepted. |
| 10 | Documents | Inspector's pack prepared: approved drawings, ITP, procedure, certificates, calibration certificates, blank test reports | ITP-BV-01 | Not ready | ||
| 11 | Logistics | Safety briefing, access and PPE arranged for visitors | Site rules | Ready |
The file also has columns for owner and due date. Every example value is invented: the project, customer, purchase order and every document, certificate, heat and report number do not exist. Standards are named but not quoted.
Columns and what to write
| Column | What to write |
|---|---|
| Item | Running number. |
| Category | Documents, Procedure, Equipment, Calibration, Material, Quality or Logistics (drop-down). |
| Check | What must be true before the customer's inspector arrives. |
| Required by | PO clause, specification clause or ITP step that asks for it. |
| Evidence | The document or record that shows it is done, with number and revision. |
| Status | Ready, Not ready or Not applicable (drop-down). Not ready rows turn red. |
| Owner | Who closes the item. |
| Due | Date it must be closed, before the notification goes out (YYYY-MM-DD). |
| Remarks | Anything else the inspector should know. |
How to use the template
- Fill in the header block: purchase order, the tests to be witnessed, the ITP steps they cover and the planned FAT date.
- List every condition that must be true before the inspector arrives: approved procedure, completed earlier ITP steps, calibration, material, open NCRs, documents and logistics.
- For each row, name the PO clause, specification clause or ITP step that asks for it, and the evidence that shows it is done.
- Set the status. Not ready rows turn red. Give each one an owner and a due date before the notification goes out.
- Send the inspection notification only when every row is Ready or Not applicable, with the notice period the PO requires.
- Take the checklist to the pre-FAT meeting, and keep the final copy with the test records.
Checking readiness from the documents
In OdysseyGPT's Inspection & Testing module, FAT Readiness Check (beta) and Calibration Validity Check (beta) read the ITP, procedures, certificates and reports and show what is still missing or out of date before a FAT. Every finding cites the page it came from, and your engineers decide what to do with it. These tools are in beta: you can request access, and we onboard each team ourselves.