Inspection and test plan (ITP) template for equipment manufacturers (Excel and CSV)

One row per inspection or test, in the order the work happens, with procedure, acceptance criteria source, record, and hold, witness and review points for each party.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

An inspection and test plan (ITP) lists every inspection and test on an order, in sequence, with its procedure, acceptance criteria, record, and the hold, witness or review point for the manufacturer, customer and third-party inspector. This free Excel template has those columns, intervention drop-downs and a filled-in valve example.

Key Takeaways

  • One check per row, in the order the work happens, from design approval to release for shipment.
  • Each party gets its own intervention column: H (hold), W (witness), R (review), S (surveillance) or none.
  • Point to where acceptance criteria come from; do not copy standard text into the plan.
  • The example has 12 steps for an invented ball valve order (PO-EX-3105).

Download the ITP template

Both files are free under CC BY 4.0, with no form to fill in. The XLSX opens in Excel, Google Sheets, LibreOffice and Numbers. The CSV carries the table only; the header block is in the XLSX.

What it is for and who uses it

Most purchase orders for engineered equipment ask for an ITP before manufacture starts. The customer approves it, then uses it to plan who attends which test. For the background, see the inspection and test plan guide.

  • Quality engineers who write the plan and keep it current.
  • Project managers who need to know which hold points stop production.
  • Customer and third-party inspectors who plan visits from it.

Example rows: 6-inch Class 600 ball valve order

Invented example rows for PO-EX-3105 (some columns omitted)
StepActivityAcceptance criteriaRecordMfrCustomerThird partyStatusRemarks
1Design documents approved (GA drawing, datasheet)PO and PS-VAL-001 3.1Returned drawings with review codeRR-Done
2Material certificates for pressure-containing parts reviewed against the POPS-VAL-001 4.2 and 7.2; material specificationCertificate review checklistHRRNot startedType 3.2 certificates required (PS-VAL-001 7.2).
3Positive material identification of alloy partsCustomer specification, where requiredPMI reportW--Not startedOnly where the PO calls for PMI.
4NDE of castings and forgingsPS-VAL-001 8.1; referenced acceptance standardNDE reportsHRRNot startedNDE operator qualifications to be on file.
5Dimensional check of machined partsDrawing tolerancesDimensional reportH--Not started
6Assembly check, including seat insert materialBOM-BV-0600; agreed deviation EX-03Assembly checklistH--Not startedRPTFE seats per accepted deviation EX-03.
7Shell pressure testProduct standard named in PS-VAL-001 9.4; agreed deviation EX-08Pressure test reportHWWNot startedGive the notice period the PO requires.
8Seat testsAs step 7Pressure test reportHWWNot started
9Operational and torque checkTorque calculation TQ-BV-06Functional test reportHW-Not started
10Painting: surface preparation and dry film thicknessPS-PNT-002 or agreed deviation EX-07Coating inspection reportHS-Not started
11Final inspection: marking, tagging, flange protection, packingPS-VAL-001 8.4 and 11Final inspection reportHWWNot started
12Documentation review and release for shipmentVDRL-VAL-001Inspection release noteHHRNot startedShipment held until the release note is signed.

The file also has columns for stage, procedure and record number. Every example value is invented: the project, customer, purchase order and every document, certificate, heat and report number do not exist. Standards are named but not quoted.

Intervention codes

CodeCommon meaning
H (hold)Work does not go past this step until the named party has attended or released it in writing.
W (witness)The named party is notified and may attend. If they do not attend after due notice, work may go on.
R (review)The named party reviews the record (certificate, report or procedure) rather than attending.
S (surveillance)The named party may monitor the activity at random, without a fixed notification.
-No intervention by that party at this step.

Projects define their own codes, and some use more levels. If the purchase order gives a legend, use it and edit the drop-downs to match.

Columns and what to write

ColumnWhat to write
StepStep number, in the order the work happens.
Activity / characteristicThe inspection or test, and what it checks.
StageWhen it happens: material receipt, machining, assembly, testing, painting, final, documentation.
Procedure / referenceThe procedure or document that says how the check is done.
Acceptance criteriaWhere the pass/fail criteria come from: specification clause, drawing, code or procedure. Do not copy standard text.
Verifying recordThe record the step produces, such as a certificate, report or checklist.
ManufacturerManufacturer's intervention: H, W, R, S or - (drop-down).
CustomerCustomer's intervention: H, W, R, S or - (drop-down).
Third partyThird-party inspector's intervention: H, W, R, S or - (drop-down).
Record no.Number of the record once it exists.
StatusNot started, Notified, Done, Released or NCR raised (drop-down). NCR rows turn red.
RemarksNotice period, agreed deviations that change the step, or anything else the inspector needs.

How to use the template

  1. Fill in the header block: purchase order, the specification and agreed deviation list the plan follows, and the ITP number and revision.
  2. List every inspection and test in the order the work happens, from design approval and material receipt to final release. One check per row.
  3. For each step, name the procedure, where the acceptance criteria come from and the record it produces. Point to clauses; do not copy standard text.
  4. Set the intervention for each party: H (hold), W (witness), R (review), S (surveillance) or - (none). Use the customer's own codes if the PO defines them.
  5. Where an agreed deviation changes a step, say so in the step and in Remarks, so the inspector checks what was agreed.
  6. Send the ITP for approval before manufacture starts. Do not pass a hold point without written release.
  7. As work goes on, add the record number and status for each step. Rows with an NCR raised turn red.
  8. Before release, filter Status for anything that is not Done or Released. Every such row needs an answer before shipment.

Checking an ITP against the customer's requirements

In OdysseyGPT's Inspection & Testing module, ITP Validator (beta) and Inspection Readiness Check (beta) check an ITP against the customer's quality requirements and show which records are still missing before an inspection. Every finding cites the page it came from, and your engineers decide what to do with it. These tools are in beta: you can request access, and we onboard each team ourselves.

Want us to run the check for you?

Send your ITP and the customer's quality requirements. We send back what is covered, what is missing and what still needs evidence before the FAT.

Get the free ITP and FAT readiness check

New templates by email (optional)

Your download does not depend on this.

We use your email only for this. See our privacy policy.

Frequently asked questions

Is there a free ITP template in Excel?

Yes. This XLSX template has a blank plan, a filled-in example for an invented valve order and a How to use sheet, with drop-downs for each party's intervention. A CSV of the same columns is also free under CC BY 4.0.

What is the difference between a hold point and a witness point?

At a hold point, work stops until the named party has attended or released it in writing. At a witness point, the party is notified and may attend; if they do not come after due notice, work may go on. Use the definitions in the purchase order where it gives them.