The short answer

Both are inspection certificates with specific test results for the delivered material. A 3.1 certificate is validated by the manufacturer's own authorised inspector, independent of production. A 3.2 certificate is validated by that inspector and also by the purchaser's inspector or a third party. If a tender asks for 3.2 and you offer 3.1, declare a deviation.

Key Takeaways

  • EN 10204 defines certificate types (2.1, 2.2, 3.1 and 3.2); it does not set the tests themselves.
  • The difference between 3.1 and 3.2 is who validates the certificate, not which tests are run.
  • A 3.2 requirement means an outside inspector must witness or review, which affects scheduling and cost.
  • Check which parts the requirement covers: pressure-containing parts only, or bolting and trim too.

What is the difference between a 3.1 and a 3.2 material certificate?

EN 10204 sets out the types of inspection document a manufacturer can supply with metallic products. The 2004 edition kept four types, 2.1, 2.2, 3.1 and 3.2, and dropped the older 2.3 and 3.1.A/B/C variants (Wermac). Types 3.1 and 3.2 both report the results of specific inspection on the products actually delivered (or on the same test unit). The difference is who signs off (Material Welding).

EN 10204 certificate types at a glance (own summary)
TypeTest resultsWho validates itTypical use in tenders
2.1 Declaration of complianceNone; statement onlyManufacturerLow-risk items, non-pressure parts
2.2 Test reportNon-specific (typical) resultsManufacturerCommodity items, some bolting
3.1 Inspection certificateSpecific results for the delivered materialManufacturer's authorised inspection representative, independent of the production departmentDefault for most pressure-containing parts
3.2 Inspection certificateSpecific results for the delivered materialManufacturer's authorised inspection representative and the purchaser's authorised representative or an inspector named in official regulationsCritical service, sour or low-temperature duty, owner specifications that require third-party validation

What is EN 10204 3.1 certification?

"3.1 certification" is shorthand for supplying a type 3.1 inspection certificate, often called a mill test certificate or material test report. It is not a certification of your company. It is a document per heat, batch or test unit that states the chemical and mechanical results and the order it relates to. It is signed by an inspector inside the producing company who is independent of manufacturing.

For a valve, the 3.1 certificates usually come from the foundry, forge or bar mill for each pressure-containing part, plus your own certificate for the assembled valve where the order asks for it. Your deviation list should say which of these you supply.

What does a 3.1 certificate certify?

  • That the delivered product meets the order requirements, based on specific inspection and testing.
  • The actual test results: typically chemical analysis, tensile properties and, where required, impact and hardness values.
  • Traceability to the heat or batch and to the marking on the part.
  • That the person validating it is authorised and independent of the production department.

It does not certify that a third party saw the tests. That is what 3.2 adds.

Why a 3.2 requirement matters to the manufacturer

A 3.2 requirement brings a second signatory into your supply chain. The purchaser's authorised inspection representative, or an inspector designated by official regulations, validates the certificate alongside your own inspector (projectmaterials). Depending on the order, that inspector may witness tests at the mill or foundry, or review the results before countersigning. Agree the arrangements, notice periods and who pays before you price.

Published sources disagree on how much this adds to cost and lead time, so quote your own figures from your sub-suppliers rather than a rule of thumb (projectmaterials). ValveIQ uses "one overlooked 3.2 material certification requirement" as its main example of a costly tender miss (ValveIQ), which shows how common the problem is.

What to flag in your offer and deviation list

Certificate checks to run on every tender
CheckWhere to lookWhat to flag
Certificate type requiredProject spec, material requisition, ITP, owner standard3.2 required where you plan to supply 3.1
Parts coveredSpec clause and ITPWhether bolting, trim, gaskets and seats are included or only pressure-containing parts
Who the 3.2 inspector isRequisition, ITPBuyer's inspector, named third party, or your choice from an approved list; who pays
Extra tests on the certificateSpec, datasheetImpact testing temperature, hardness limits, PMI, corrosion tests that must appear on the certificate
Conflicts between documentsSpec vs owner standard vs ITPDifferent certificate types in different documents; raise a TQ or a clarification
Documentation formatVDRLWhether certificates go in the final data book, and by when

A typical deviation row reads: requirement "EN 10204 type 3.2 for pressure-containing parts"; offered "type 3.1"; status Deviation; cost of withdrawal "3.2 available at an added cost and lead time, inspector fees by buyer". See the full worked example in the technical deviation list guide and the datasheet vs specification checklist.

Where OdysseyGPT fits

Certificate requirements are often scattered across the specification, the ITP and the owner standard, which is why they get missed. OdysseyGPT reads the whole package and lists each certificate requirement with the clause and page it came from, for an engineer to check and decide on. See OdysseyGPT for manufacturing.

Buyer questions

20 questions bid engineers, proposal engineers and buyers ask. Last reviewed:

What does EN 10204 cover?

EN 10204 defines the types of inspection document a manufacturer can supply with metallic products. It names four types: 2.1, 2.2, 3.1 and 3.2. It says who signs each one and whether it carries specific or non-specific test results. It does not set which tests to run or the acceptance values. Those come from the material standard, the product standard and the order.

Which edition of EN 10204 do tenders usually cite?

Most tenders cite the 2004 edition, which kept four document types and dropped the older 2.3 and 3.1.A, 3.1.B and 3.1.C variants. Old owner standards and legacy datasheets still ask for 3.1.B. Treat that as a clarification. State in your offer which current type you will supply, usually 3.1, so the buyer can confirm the mapping before order.

What is the difference between EN 10204 2.1 and 2.2?

Both are issued by the manufacturer alone and neither reports results for the specific items delivered. A 2.1 is a declaration of compliance with the order, with no test results. A 2.2 is a test report that adds non-specific results, such as typical values from the same production process. Neither is enough where a tender asks for type 3.1 or 3.2.

Which valve or pump parts usually need a 3.1 certificate?

Specifications most often ask for 3.1 on pressure-containing parts such as the body, bonnet or cover, and closure bolting. Some also ask for it on trim, stems and seats. Others accept 2.2 for non-pressure parts. Read the specification, the material requisition and the ITP together, because the parts list often differs between them. Record the parts you will cover in your offer.

What are the most common EN 10204 deviations in tenders?

The usual ones are offering 3.1 where 3.2 is required, covering only pressure-containing parts when the tender also names bolting or trim, and supplying sub-supplier certificates without your own final certificate. Another is missing results the specification wants on the certificate, such as impact values or hardness. Each one belongs as a row in your technical deviation list.

What do EPCs usually ask for on material certificates?

EPCs usually ask for the certificate type per part, traceability from heat number to part marking, and the specific results the project specification calls for. They also ask for the certificates in a set format and at a set time, often in the final data book listed in the VDRL. Check the VDRL guide for how those entries usually read.

Who pays for the third-party inspector on a 3.2 certificate?

EN 10204 does not decide that; the contract does. Some tenders name the buyer's inspector and the buyer pays. Others ask the manufacturer to hire a third party from an approved list and include the cost. If the tender is silent, raise a clarification and state your assumption in the offer, with notice periods for witness points.

Can a 3.1 certificate come from my foundry or forge instead of from me?

Often yes, for the raw material. The foundry, forge or mill issues the 3.1 for the castings, forgings or bar it produced. Many specifications also want a certificate from the valve or pump maker for the finished item, covering its own tests. Check whether the tender accepts sub-supplier certificates alone, and say clearly in the offer who issues which document.

What test results should appear on a 3.1 certificate?

The certificate should show the results the material standard and the order require, for the heat or test unit delivered. That usually means chemical analysis and tensile results, and often impact and hardness values. Some projects also want PMI, corrosion or NDE results on it. Compare the list in the specification against the template your mill or foundry actually issues.

How does EN 10204 relate to the Pressure Equipment Directive?

The Pressure Equipment Directive sets what material documentation pressure equipment needs; EN 10204 provides the document types that are commonly used to meet it. For the higher hazard categories, main pressure-bearing parts typically need a certificate of specific product control, which in practice is usually a 3.1. Confirm the category and the notified body's view for your own equipment.

Do tenders outside Europe still ask for EN 10204 certificates?

Yes. EN 10204 is used well beyond Europe, including in Middle East, Asian and many international oil and gas tenders. US-based specifications may instead ask for a mill test report to the ASTM or ASME material specification. Some ask for both. If the wording is loose, ask the buyer which document type they will accept and record the answer.

Is an EN 10204 3.1 the same as an ASTM mill test report?

Not automatically. A mill test report gives results to the material specification, but it only counts as a 3.1 if it states that type and is validated by an inspector independent of production. Many mills issue documents that state both. Check the type printed on the certificate before you list it as compliant against a 3.1 requirement.

How do I check my datasheet and offer against a certificate requirement?

List every place the tender names a certificate: specification, material requisition, ITP, datasheet notes and the owner standard. For each part, write the type required and the type you will supply. Note any extra results that must appear on it. Where documents disagree, raise a technical query. Where you cannot meet a requirement, declare a deviation with the cost of compliance.

What if the specification and the ITP ask for different certificate types?

Treat it as a conflict and ask before you price. Point to both locations and ask which one governs, or state that you have priced the stricter one. The order of precedence in the tender may settle it. See governing-document precedence. Never pick the easier option silently, because it will come back at inspection.

How does a 3.2 requirement affect lead time?

A 3.2 adds a second signatory, so tests at the mill or foundry may need to wait for the inspector to attend or review. That adds notice periods and the risk of a missed slot. The size of the effect depends on your supply chain. Use your own sub-supplier figures in the offer rather than a general rule of thumb.

Do bolts and nuts need EN 10204 3.1 certificates?

Often, for pressure-retaining bolting. Many specifications ask for 3.1 on body-to-bonnet and other closure bolting, and some ask for it on all fasteners. Others accept 2.2 for non-pressure fasteners. Check the bolting line in the specification and the ITP, and state which bolting you cover. Bolting is a frequent gap because it comes from a separate supplier.

What traceability do buyers expect on material certificates?

Buyers expect each certificate to trace to the part through a heat, cast or batch number that also appears on the part marking. They also expect the certificate to reference the order or the item. Some projects ask for a traceability record that links every part to its certificate. Confirm the format early, because rebuilding traceability after manufacture is slow.

How does OdysseyGPT check certificate requirements in a tender?

OdysseyGPT reads the whole tender package, including the specification, material requisition, ITP and datasheets. It lists each certificate requirement with a quote and the page it came from. It then checks each one against your own datasheets and procedures and gives it a status, such as complies, deviates or clarification. The results export to an editable compliance matrix and deviation list.

Can OdysseyGPT check the certificates themselves?

No. OdysseyGPT checks what the tender requires against what your documents say you will supply. It does not inspect issued certificates, validate test results or replace your inspector. It also does not hold a copy of EN 10204, so it relies on the documents you upload. An engineer decides every open item and owns what goes to the customer.

Frequently asked questions

Is EN 10204 3.2 better than 3.1?

Not in test content. Both report specific results for the delivered material. 3.2 adds validation by the purchaser's inspector or a third party, which gives the buyer more independent assurance.

Who issues an EN 10204 3.2 certificate?

It is prepared jointly. The manufacturer's authorised inspection representative validates it. So does the purchaser's authorised representative, or an inspector named in official regulations.

Can I replace a 3.2 certificate with a 3.1 certificate?

Only if the buyer accepts it. Declare it as a deviation in your offer with the cost of withdrawal for supplying 3.2.

Is a mill test certificate the same as a 3.1 certificate?

Often, yes. In practice "mill test certificate" usually means an EN 10204 3.1 certificate, but check the type stated on the document itself.

References

EN 10204 3.1 vs 3.2

projectmaterials

Visit source

Mill test certificates: EN 10204 3.1 and 3.2

projectmaterials

Visit source

EN 10204 certificate types

Wermac

Visit source

Material test certificates explained: 2.1, 2.2, 3.1 and 3.2

Material Welding

Visit source

ValveIQ home page (3.2 example)

ValveIQ

Visit source

EN 10204: Metallic products. Types of inspection documents