IQ, OQ and PQ

Installation, operational and performance qualification: the three stages in which a drug manufacturer shows that equipment is installed correctly, operates as designed and performs in use.

Last reviewed by the OdysseyGPT team

What it is

IQ, OQ and PQ are installation, operational and performance qualification. A drug manufacturer uses them to show that equipment is installed correctly, operates as designed across its limits and performs under normal conditions. The manufacturer is responsible; the equipment supplier supports with documents, FAT and SAT records and often draft protocols.

Key Takeaways

  • IQ: installed correctly. OQ: operates as designed. PQ: performs in use.
  • Qualification is the drug manufacturer's responsibility, not the supplier's.
  • Good FAT records can reduce what is repeated at IQ and OQ.
  • Supplier protocols need the customer's review and approval before use.

Why it matters

IQ, OQ and PQ are the qualification stages a drug manufacturer carries out on equipment, facilities, utilities and systems. Under EU GMP Annex 15, installation qualification (IQ) includes checking that components, instruments, pipework and services are installed correctly against the engineering drawings and specifications, collecting the supplier's operating and maintenance instructions, calibrating instruments and verifying materials of construction. Operational qualification (OQ) normally follows IQ and includes tests that show the system operates as designed, including tests at upper and lower operating limits or worst-case conditions. Performance qualification (PQ) normally follows a successful IQ and OQ and tests the equipment with production materials, qualified substitutes or simulated product under normal operating conditions. Annex 15 allows IQ and OQ to be combined, and allows PQ in some cases to be done together with OQ or process validation. Qualification is the user's responsibility. The equipment supplier supports it: with design documents and certificates, with FAT and SAT records, and often with draft IQ and OQ protocols. Annex 15 says protocols supplied by a third party must be confirmed as suitable by the manufacturing site before approval, and may be supplemented. It also allows documentation review and some tests done at the FAT to stand without repetition at IQ or OQ where that is appropriate and justified and transport and installation do not affect the function.

How OdysseyGPT uses it

OdysseyGPT does not perform IQ, OQ or PQ, and does not write, execute or approve qualification protocols. It works on the supplier's documents before that point. Document Review checks your documents against the customer's URS. FAT Readiness Check (beta) checks the FAT procedure, calibration evidence and open items before the test, and Calibration Validity Check (beta) checks that each test instrument was in calibration on the day it was used.

Evaluation questions

What does an equipment supplier provide for IQ and OQ?

Typically drawings, component and instrument lists, material and calibration certificates, operating and maintenance manuals, software records, FAT and SAT reports and, where the contract asks, draft IQ and OQ protocols.

What comes before IQ?

The user requirement specification, then design qualification, then factory and site acceptance testing where they apply. EU GMP Annex 15 describes these as stages of qualification before IQ.

Frequently asked questions

What do IQ, OQ and PQ stand for?

Installation qualification, operational qualification and performance qualification. IQ checks the installation, OQ checks operation across its limits, and PQ checks performance under normal operating conditions.

Who performs IQ, OQ and PQ?

The drug manufacturer is responsible. Suppliers often provide draft protocols or carry out tests under the customer's approval, but the customer's own staff must confirm the protocols are suitable and approve the results.

Is a FAT the same as an OQ?

No. The FAT is a supplier test at the factory before shipment. OQ is a qualification stage at the user's site. Some FAT tests can be reused at OQ where that is justified and transport and installation do not affect the result.

Can IQ and OQ be combined?

Yes. EU GMP Annex 15 allows qualification documents to be combined where appropriate, and IQ and OQ are often run as one combined stage, sometimes called IOQ, depending on the complexity of the equipment.

References

EudraLex Volume 4, Annex 15: Qualification and Validation

European Commission

Sections on installation, operational and performance qualification.

Visit source