Site Acceptance Test (SAT)

The acceptance test run on a machine after it has been installed at the customer's site, following a written protocol that both parties sign.

Last reviewed by the OdysseyGPT team

What it is

A site acceptance test (SAT) is the acceptance test run on a machine after installation at the customer's site. It follows a written SAT protocol that lists preconditions, the checks on safety functions and interfaces, the performance run and its pass figures, and a punch list. The builder and the customer both sign it.

Key Takeaways

  • The SAT is a contract event, not a legal one.
  • The protocol lists preconditions, test steps, pass figures and open points.
  • State the product, duration and counting rules for every performance figure.
  • The contract says who signs and what the signature triggers.

Why it matters

A site acceptance test, or SAT, is the test at which the customer accepts a machine in its final place. It is a contract event. The machinery rules do not define it. The test follows a SAT protocol, which the builder normally drafts and the customer approves before installation is finished. A typical protocol opens with the preconditions: installation complete, utilities connected, the open points from the factory acceptance test closed or listed, and test product available in the agreed quantity and quality. It then sets out the checks. These usually cover transport damage and completeness, the safety functions as installed, the interfaces to upstream and downstream equipment and to the plant's control and data systems, and each function that could not be proved at the builder's works. Performance comes next: the acceptance run for cycle time, output, availability or OEE, and any capability study, each with its duration, the product used, the counting rules and the pass figure. The protocol closes with a documentation check, training records and a punch list of open points with owners and dates. Each step has a column for the result and for initials. The protocol should say who signs. Commonly the builder's project manager or commissioning lead signs for the builder and the customer's project engineer signs for the customer, with production, maintenance, quality or safety staff signing their own sections. The contract says what the signature triggers, which may be transfer of risk, a payment milestone or the start of the warranty period. For the difference between the factory and site tests, see the entry on FAT vs SAT. This entry describes common practice, not a standard.

How OdysseyGPT uses it

OdysseyGPT has no site acceptance test tool. Document Review can set the acceptance clauses of the customer's requirement specification against your functional specification or draft SAT protocol and show, with quotes, which required tests and figures the protocol does not mention. FAT Readiness Check (beta) works on the documents for the factory test only. OdysseyGPT does not run tests, record results or connect to the machine.

Evaluation questions

What should each step in a SAT protocol refer to?

The requirement it proves. A step that points to a section of the agreed functional specification or the customer's requirement specification is easier to pass or fail than one that stands alone.

Does the SAT repeat the tests from the FAT?

Only as far as the contract asks. Many protocols repeat a short set of function checks, then concentrate on what could not be shown at the works: plant interfaces, real utilities and the longer performance run.

Frequently asked questions

Who signs the SAT protocol?

The people the contract or the protocol names. Commonly a representative of the builder and the customer's project engineer, with the customer's production, maintenance, quality or safety staff signing the sections they witnessed.

Who writes the SAT protocol?

Usually the machine builder drafts it from the agreed functional specification and the customer approves it. Some customers issue their own protocol form. The contract should say which applies.

What happens to open points after a SAT?

They go on a punch list with an owner and a date for each. The protocol should say which open points prevent acceptance and which can be closed afterwards.

References

Directive 2006/42/EC on machinery (consolidated text)

EUR-Lex

Read to confirm that the Directive sets the manufacturer's duties and does not define a site acceptance test.

Visit source

Machinery

European Commission

Application date of the Regulation and the transition from the Directive.

Visit source

Related Pages