Protocol or readiness checklist: which one you need
Two different documents get called a FAT checklist. One is filled in during the weeks before the test and asks whether you are ready for the customer to arrive: procedure approved, instruments calibrated, earlier inspections closed. That is the FAT readiness checklist template. The other is the protocol on this page, run on the day itself: each test, its criterion, what was measured, and whether both sides accept it. A machine FAT needs both, in that order.
- Project managers and commissioning engineers at machine builders, who write the protocol and lead the test.
- The customer's project, production and maintenance staff, who watch the tests and sign.
- Quality engineers, who follow the punch list until the last item is closed.
What the machine must achieve, for how long and with which material is a matter for the contract and the customer's specification. Some contracts also name a standard or an industry guideline for a test method. Check the governing standard or contract. For how the factory test relates to the one at the customer's site, see FAT vs SAT and site acceptance test.
Header block
| Field | Example |
|---|---|
| Machine | Carton packing machine, type EX-CP-200 (fictional) |
| Serial no. | EX-M-3318 (fictional) |
| Customer | Example Consumer Goods Ltd (fictional) |
| Order | PO-EX-5860 (fictional) |
| Customer specification and revision | MS-EX-01 Rev 3 (invented machine specification) |
| Approved layout drawing | LD-EX-5860 Rev C |
| FAT date(s) | 2027-05-18 and 2027-05-19 |
| Location | Supplier's assembly hall |
| Participants, supplier | Project manager; commissioning engineer; controls engineer |
| Participants, customer | Project engineer; production lead; maintenance technician |
| Test material | Customer's cartons and leaflets, formats A and B, as delivered for the FAT |
| Protocol no. | FATP-EX-5860 Rev 0 |
Example tests: a carton packing machine
| Test no. | Requirement reference | Test description | Acceptance criterion (as written in the contract) | Measured or observed result | Result | Punch item |
|---|---|---|---|---|---|---|
| 1 | MS-EX-01 2.1 | Documents present at the FAT | Approved layout drawing, electrical diagrams and risk assessment available at the approved revision | All three present; revisions match the document list | Pass | |
| 2 | MS-EX-01 3.2 | Build check against the approved layout drawing | Machine built as LD-EX-5860 Rev C | Operator-side guard door hinged on the opposite side to the drawing | Fail | P-01 |
| 3 | MS-EX-01 5.1 | Emergency stops and guard interlocks, each one operated in turn with the machine running | Every emergency stop and every guard interlock stops the machine | 4 emergency stops and 6 interlocks operated; the machine stopped each time | Pass | |
| 4 | MS-EX-01 6.1 | Dry run at nominal speed, no product | 60 minutes with no fault stop (MS-EX-01, invented customer figure) | 60 minutes run; no stops | Pass | |
| 5 | MS-EX-01 6.2 | Output, format A, customer's cartons, one operator | At least 120 cartons per minute, averaged over 30 minutes (MS-EX-01, invented customer figure) | 123 cartons per minute over 30 minutes | Pass | |
| 6 | MS-EX-01 6.2 | Output, format B, customer's cartons, one operator | At least 90 cartons per minute, averaged over 30 minutes (MS-EX-01, invented customer figure) | 86 cartons per minute over 30 minutes | Fail | P-02 |
| 7 | MS-EX-01 6.3 | Rejected cartons during the format A output run | No more than 0.5 % of cartons rejected (MS-EX-01, invented customer figure) | 11 of 3,690 cartons rejected: 0.3 % | Pass | |
| 8 | MS-EX-01 6.5 | Missing-leaflet detection: 20 cartons without a leaflet fed in at random | 20 of 20 detected and rejected (MS-EX-01, invented customer figure) | 20 of 20 rejected | Pass | |
| 9 | MS-EX-01 6.6 | Changeover from format A to format B by one trained operator | No more than 20 minutes, with the supplied tools only (MS-EX-01, invented customer figure) | 24 minutes | Fail | P-03 |
| 10 | MS-EX-01 7.1 | Operator panel texts and alarm list | Panel texts in English and German; alarms as appendix B of MS-EX-01 | English complete; German text missing for 14 alarms | Open | P-04 |
| 11 | MS-EX-01 7.3 | Noise at the operator position | The level stated in MS-EX-01 7.3, measured by the method named there | Not measured: background noise in the assembly hall too high for a valid reading | Open | P-05 |
| 12 | MS-EX-01 8.2 | Compressed air consumption during the format A output run | Not above the figure on machine datasheet DS-EX-CP-200 (supplier's stated figure) | Below the datasheet figure; reading attached | Pass | |
| 13 | MS-EX-01 9.1 | Documents handed over at the FAT | Draft operating manual and spare parts list handed to the customer | Draft manual handed over; spare parts list not ready | Open | P-06 |
Every acceptance figure in the example, such as the output rates, the changeover time and the reject percentage, is an invented customer's figure from an invented specification (MS-EX-01) and is labelled that way. None is a requirement of any standard. Three tests failed and three are open, so the protocol ends with six punch items. Every example value is invented: the project, customer, bidders, purchase order, prices and every document, certificate, serial and report number do not exist. Standards are named but not quoted.
Punch list and sign-off block
| Item | Test no. | Description and agreed action | Category | Owner | Due date | Closed | Closure evidence |
|---|---|---|---|---|---|---|---|
| P-01 | 2 | Guard door hinged on the wrong side. Re-hang as the layout drawing and re-check the interlock. | A | Supplier, commissioning engineer | 2027-05-26 | No | |
| P-02 | 6 | Format B output below the contract figure. Find the cause, correct it and repeat test 6 with the customer present or by video, as agreed. | A | Supplier, project manager | 2027-06-02 | No | |
| P-03 | 9 | Changeover took longer than the contract figure. Supplier to propose quick-release fixings for the carton magazine; repeat at site acceptance. | B | Supplier, commissioning engineer | 2027-07-15 | No | |
| P-04 | 10 | German alarm texts missing. Customer to confirm the translations; supplier to load them. | B | Customer, project engineer | 2027-06-10 | No | |
| P-05 | 11 | Noise not measured. Measure at the customer's site during site acceptance, by the method the specification names. | B | Supplier, project manager | 2027-07-15 | No | |
| P-06 | 13 | Spare parts list not handed over. Send with the shipping documents. | B | Supplier, project manager | 2027-06-02 | Yes | Spare parts list SPL-EX-5860 Rev 0, sent 2027-05-21 |
| Category | Common meaning |
|---|---|
| A | Must be closed, and the affected test repeated, before the machine is released for shipment. |
| B | May be closed after shipment, by a date both sides agree, usually by the site acceptance test. |
| Field | Example |
|---|---|
| Outcome of the FAT | Accepted with punch list. Category A items to be closed and re-tested before shipment |
| Released for shipment | No: release follows closure of P-01 and P-02 |
| Open punch items | Category A: 2. Category B: 3 |
| Deviations from the test plan | Test 11 not run; moved to site acceptance by agreement |
| For the supplier (name, signature, date) | Project manager, 2027-05-19 |
| For the customer (name, signature, date) | Project engineer, 2027-05-19 |
| Attachments | Output run counts; air consumption reading; photographs of P-01 |
Category A and B are common labels, and contracts define them differently or use other names. Use the contract's definitions. If it has none, agree them in writing before the first test.
Result values
| Result | Use it when |
|---|---|
| Pass | The result meets the acceptance criterion as the contract writes it, and the customer's representative saw it or accepted the record. |
| Fail | The test was run and the result does not meet the criterion. Raise a punch item. |
| Open | The test was not run, not finished, or its result is disputed. Raise a punch item saying what is left to do and where. |
Columns and what to write
| Column | What to write |
|---|---|
| Test no. | Running number, in the order the tests are run. |
| Requirement reference | The clause of the customer's specification or contract that the test proves. A test with no reference is a test nobody ordered. |
| Test description | What is done: the format, speed, duration, material and who operates the machine. |
| Acceptance criterion (as written in the contract) | The criterion copied from the specification or contract, with its figure and unit. Agree it before the FAT; do not write it on the day. |
| Measured or observed result | What was measured or seen, with the figure and unit, written during the test. |
| Result | Pass, Fail or Open (drop-down). Fail rows turn red; Open rows amber. |
| Punch item | The punch list number raised for a Fail or Open result. Blank for Pass. |
| Column | What to write |
|---|---|
| Item | Punch item number, quoted in the test table. |
| Test no. | The test that raised the item. |
| Description and agreed action | What is wrong or unfinished, and what both sides agreed will be done about it. |
| Category | A or B (drop-down), as the contract defines them. Rows that are category A and not closed turn red. |
| Owner | The person who closes the item, supplier or customer. |
| Due date | The agreed date (YYYY-MM-DD). |
| Closed | Yes or No (drop-down). Set Yes only when the customer has seen the evidence. |
| Closure evidence | The re-test record, photograph, document or site check that shows the item is done. |
How to run a FAT with the protocol
- Before the FAT, fill in the header block and write one row per test, with the requirement reference and the acceptance criterion copied from the customer's specification or the contract.
- Send the protocol to the customer for agreement before the FAT date. A criterion argued over on the day is a test nobody can pass.
- On the day, record who is present, then run the tests in order. Write the measured or observed result as it happens, with figures and units.
- Set the result: Pass, Fail or Open. For every Fail or Open, raise a punch item on the second sheet and put its number in the test row.
- Agree a category for each punch item using the contract's definitions, then an owner and a due date. If the contract defines no categories, agree them in writing before the first test.
- At the end, fill in the sign-off block: the outcome, whether the machine is released for shipment, the count of open items, and any test that was left out or changed.
- Both sides sign and date the protocol before anyone leaves. Each takes a copy.
- As punch items close, set Closed to Yes and note the evidence. Take the open items to the site acceptance test.
Writing the test table from the customer's specification
The hard part of a FAT protocol is its second column: finding every clause in the customer's specification that needs a test, and copying the criterion correctly. In OdysseyGPT's Inspection & Testing module, FAT Readiness Check (beta) reads the customer's requirements, the ITP and the test procedure and lists what is not yet covered or not yet in place before the test. Customer Specification Review (beta) lists the customer's requirements with the page each one comes from. Your engineers write the tests and agree the criteria with the customer. Tools marked beta are open on request, and we onboard each team ourselves.