Structural steel fabrication documentation: from the fabrication specification to the final dossier

For contracts, bid and quality engineers at structural steel fabricators and skid or module builders who work to a customer's fabrication specification.

By Ademola Afolabi, Founder, New Odyssey Ltd ยท Last reviewed:

The short answer

Steel fabricators answer an enquiry by reading the fabrication specification with the welding, NDE, coating and tolerance requirements, and listing where their shop practice differs. After award they owe an inspection and test plan, welding qualifications, a weld log, material certificates to the traceability level specified, NDE, dimensional and coating records, and a final dossier.

Key Takeaways

  • The welding code and the execution class or inspection level set most of the quality cost in a steel enquiry.
  • Traceability level is a priced item. Piece-by-piece traceability costs far more than traceability by grade.
  • A skid adds piping, mechanical and E&I records to the steelwork records, all under one dossier index.
  • OdysseyGPT checks documents against the customer's requirements. It does not read drawings or models.

Free sample: a certificate check report. Send up to 20 material certificates and the PO. Get a certificate check report. Get the free result

How do steel fabricators answer an enquiry?

A steelwork enquiry arrives as drawings and a tonnage, but the price is decided in the specifications behind them. The estimator prices tonnes and hours. The contracts or quality engineer has to find the clauses that change those hours.

What a structural steel or skid enquiry usually contains
DocumentWhat it decidesQuestion to settle before pricing
Fabrication specificationThe governing code, the execution class or inspection category, and which document takes precedenceIs your shop certified or qualified for the class asked for?
Design drawings and material take-offMembers, connections, steel grades and the tonnageWho produces the fabrication drawings, and who approves them?
Welding and NDE specificationPermitted processes, procedure and welder qualification rules, NDE methods, extent and personnel certificationDo your existing welding procedures cover the grades and thicknesses on the take-off?
Painting or galvanising specificationSurface preparation, the coating system, film thickness checks and repair rulesIs the system one your coating line or subcontractor applies today?
TolerancesFabrication and trial-assembly tolerances, often tighter at interfaces and machinery supportsAre any limits tighter than the code you normally work to?
Traceability and certificate requirementsThe level of traceability and the certificate type for each class of materialIs traceability by grade, by heat, or piece by piece?
Documentation requirementsWhich records are submitted, which need approval before work starts, and the dossier indexWhich approvals hold cutting or welding?

Two clauses deserve a second read. The first is the execution class or its equivalent, because it sets how much inspection, traceability and welding control the whole job carries. The second is the list of documents that need customer approval before fabrication. Each one is a date on your programme that someone else controls.

Which codes and standards come up in steel fabrication?

Standards often named in structural steel and skid enquiries (own summary; use the edition your contract names)
StandardWhat it isWhy a fabricator cares
AWS D1.1The American Welding Society's structural welding code for steelIt covers welded connection design, procedure and welder qualification, fabrication and inspection in one document. AWS notes that makers of skids and modules use it too
EN 1090-1Conformity assessment of structural steel and aluminium componentsIt is the basis for the declaration of performance and CE or UKCA marking of fabricated steelwork
EN 1090-2Technical requirements for the execution of steel structuresIts requirements scale with the execution class, EXC1 to EXC4, which the designer specifies
ISO 3834Quality requirements for fusion welding of metallic materials, in several parts at different levelsEN 1090 work is run under a welding quality system to the relevant part, with a responsible welding coordinator
EN 10204Types of inspection document for metallic products: 2.1, 2.2, 3.1 and 3.2The enquiry states which type each class of plate, section and bolt must come with
ISO 12944Corrosion protection of steel structures by protective paint systemsCustomers either call it up or replace it with their own coating specification, which then governs
Customer and owner specificationsProject documents that add to the standardsExtra NDE, tighter tolerances, approved mills, and more records than the standard asks for

Some enquiries mix families: an American welding code with European material certificates, or the reverse. That is workable, but say in your offer which standard you will use for welding procedures, welder qualification and NDE personnel. These standards are paid documents. This page names them and does not reproduce their tables or limits.

What goes in a steel fabricator's deviation list?

A deviation row states the clause, what it asks for, what you offer instead and why. In steelwork the rows tend to gather around a few subjects.

  • Execution class or inspection category: you hold certification for a lower class than the one specified, or the class is missing and you state your assumption.
  • Welding procedures: the specification wants procedures qualified by test where your shop uses prequalified or existing procedures, or it asks for impact testing your records do not include.
  • NDE: the extent or method goes beyond the code, or the specification wants a personnel certification scheme your technicians do not hold.
  • Steel supply: a named mill, a certificate type, or through-thickness or impact properties that stockholder material may not carry.
  • Traceability: piece-by-piece traceability requested where you offer traceability by heat or by grade.
  • Tolerances: limits at interfaces, base plates or equipment supports tighter than the code values you normally hold.
  • Coating: a paint system, film thickness regime or galvanising requirement that your line does not run as standard, and the rules for site touch-up.
  • Trial assembly, load testing of lifting points and the format of the final dossier.

The format is covered in the technical deviation list guide. After award, the Deviation Register (beta) holds the agreed rows, so the shop builds to what was negotiated and not to the unamended specification.

Which documents does a steel fabricator produce after award?

Records in a typical structural steel quality dossier
RecordWhat it showsCommon gap
Inspection and test plan (ITP)Each inspection stage, the acceptance reference and who holds, witnesses or reviewsA hold point in the customer's quality specification shown as review only. See the structural steel ITP template
WPS, PQR and welder qualificationsEvery joint type has a procedure, and every welder is qualified for itA procedure that does not cover the thickest flange or the higher steel grade. See WPS, PQR and WPQ
Weld map or weld logWhich welds exist, who made them and to which procedureWelds identified on the drawing only, with no list behind it. See weld map
Mill test certificatesGrade, heat number, chemistry and mechanical results for plate, sections and boltsThe wrong EN 10204 type, or a subgrade that does not match the order
Traceability recordsThe link from a member or piece mark to its heat number, to the level specifiedOffcuts and small plates that lost their identity at the saw
NDE reportsVisual, magnetic particle, ultrasonic or other examination of the welds that need itA repaired weld with no later report
Dimensional reportsMembers and assemblies measured against the tolerancesInterface dimensions not recorded for trial-assembled frames
Coating or galvanising recordsSurface preparation, conditions during application and film thickness readingsNo record of the conditions on the day the primer went on
Declaration of performance and CE or UKCA markingWhere EN 1090-1 applies, the fabricator's declared performance for the componentsA declaration that names a different execution class from the project's
Final dossierAll of the above, indexed the way the customer askedIndex headings with nothing filed under them

Structural work differs from pressure work in one useful way: the customer chooses the traceability level. A building frame may need only proof that the right grade was used. An offshore module or a lifting frame may need every plate tied to its heat. Read the clause, price it, and build the cutting and marking routine around it before the first plate is cut.

What changes when the job is a packaged skid?

A skid package puts equipment, piping, instruments and cabling on one steel base frame so it can be tested in the shop and lifted into place. The skid builder becomes the single point of contact for records from several disciplines, many of them written by sub-suppliers.

Where the records in a skid dossier come from
DisciplineTypical recordsWho usually writes them
StructuralBase frame welding records, mill certificates, NDE and dimensional reports, lifting point design and load test certificatesThe skid builder
MechanicalData books for pumps, vessels, exchangers and filters, with their own certificates and test reportsEquipment sub-suppliers
PipingWeld logs, material certificates, NDE reports and pressure test records for the interconnecting pipeworkThe skid builder or a spool fabricator
Electrical and instrumentationInstrument datasheets and calibration certificates, cable schedules, loop check sheets and hazardous-area certificatesInstrument suppliers and the E&I contractor
Whole skidCoating records, factory acceptance test report, weight report, preservation and packing recordsThe skid builder

Two things go wrong. Sub-supplier data books arrive late and in the supplier's own layout, so the dossier index has gaps on the day of the acceptance test. And the structural frame is built to a structural welding code while the piping on it follows a piping code, so two sets of welding qualifications and NDE rules run side by side. State in the ITP which code governs which weld.

How does OdysseyGPT help?

OdysseyGPT reads the documents and compares them with what the customer asked for. Each finding quotes the passage behind it, and your engineers accept or reject it. It needs text and tables: specifications, registers, logs, certificates and reports. It does not read fabrication drawings, erection drawings or 3D models.

Steel fabrication documents and the OdysseyGPT tool that checks them
WhenWhat you uploadToolWhat comes back
Before the offerThe fabrication, welding, NDE and coating specifications, with your quality plan and standard proceduresDocument ReviewA compliance matrix and a draft list of deviations and clarifications, quoting both documents in each row
Before the offerThe customer's specification package aloneCustomer Specification Review (beta)The requirements listed by type, with unclear or missing items marked, such as an execution class that is never stated
At awardThe specification, your offer and the clarification correspondenceDeviation Register (beta)A single register of what was agreed, with repeated items merged
At awardYour document register and the contract's documentation clausesVDRL/MDR Tracker (beta)Late documents and documents the contract asks for that the register does not list
Before fabricationThe customer's quality specification and your ITPITP Validator (beta)Stages the ITP leaves out, hold or witness points shown at a lower level, and stages with no acceptance reference
Steel receiptMill certificates, the purchase requirements and the material listMaterial Certificate Review (beta)A grade or subgrade that differs from the order, the wrong certificate type, and tests the order required that the certificate does not show
Steel receiptThe material list, heat register and certificatesMaterial Traceability Check (beta)Heat numbers without a certificate and certificates that match no listed piece
WeldingWelding procedures, qualification records, welder certificates and the weld log as a tableWelding Qualification Review (beta)Welds that fall outside a procedure's qualified range, and welders whose qualification had lapsed on the weld date
ExaminationThe weld log, NDE reports and repair recordsNDE Coverage Review (beta)Welds with no report, the wrong method, less coverage than specified, and repairs with no follow-up examination
Before the inspector visitsProcedures, certificates, qualifications and the open non-conformance listInspection Readiness Check (beta)What would stop the inspection, and what is only a warning
DossierThe customer's dossier index and your document folderMRB Readiness Check (beta)Index lines with no document, superseded revisions and unapproved records
DossierThe compiled dossier, weld log and ITPMRB Traceability Verification (beta)Breaks in the chain from weld to procedure and welder, and from piece to heat and certificate

Coating and dimensional reports have no dedicated check. The MRB Readiness Check (beta) confirms they are present, current and approved against the index. It does not judge the film thickness readings or the measurements. The MRB Compiler (beta) then lists the dossier contents against the customer's index. For a skid, the same checks run over sub-supplier data books once they are in the folder.

What does a result look like for steelwork?

The example below is invented. The project, member marks, welders, procedure numbers, heat numbers and dates do not come from any real job. It shows the shape of the output and nothing more.

Invented example: the quality records for a pipe rack module checked against the customer's structural fabrication specification
IDFindingWhy it was raisedCategorySeverityConfidence
F-WLD-01WPS-ST-12 does not cover the flange splice weld on column C-104The weld log gives a flange thickness of 50 mm. The qualification record behind WPS-ST-12 states an upper thickness limit below that.Unsupported WPSCriticalHigh
F-WLD-02Welder S-23 has no valid qualification for the welds made on beam B-217The welder's certificate lists fillet welds only. The weld log records two full penetration butt welds by S-23 on 2026-04-09.Welder qualificationCriticalHigh
F-NDE-01Moment connection weld MC-06 on rafter R-031 has no ultrasonic reportThe fabrication specification requires ultrasonic examination of every full penetration weld in primary members. No report in the set refers to MC-06.Missing reportCriticalHigh
F-NDE-02Repaired weld on lifting lug LL-02 was not examined againThe repair record is dated 2026-04-22. The only magnetic particle report for LL-02 is dated 2026-04-18.Unclosed repairHighMedium
F-MTR-01Plate certificate states S355JR where the order requires S355J2The purchase requirement for base plates gives grade S355J2. The certificate for heat 91K447 gives S355JR and reports no impact test at the lower temperature.Grade mismatchCriticalHigh
F-MTR-02Bolt assembly certificate is EN 10204 type 2.1The fabrication specification asks for type 3.1 inspection certificates for structural bolting. The supplier's document is a declaration of compliance with no test results.Certificate typeMediumHigh
F-TRC-01Heat 58D902 on stiffener plates for girder G-12 has no mill certificateThe cutting list records heat 58D902 for six stiffeners. No certificate in the set carries that heat number.Unlinked heatHighHigh
F-ITP-01ITP shows coating film thickness inspection as a review pointThe customer's quality specification marks final dry film thickness measurement as a witness point for the purchaser's inspector.Downgraded inspection pointMediumHigh

Behind each row sit the document name, the page or cell and the quoted words, so the person checking can go straight to the record. Some findings will turn out to be clerical: a certificate filed in the wrong folder, a weld log typed with the wrong welder stamp. Those are still worth finding before the customer's inspector does.

Where OdysseyGPT falls short

  • It does not read fabrication drawings, erection drawings, general arrangements or 3D models. Weld numbers and piece marks have to reach it as a table.
  • It does no structural design or connection design, and it does not check a design against a design code.
  • It is not fabrication management software. It does not nest plate, plan production, drive machines, track pieces through the shop or manage stock. See steel fabrication software compared.
  • It does not write welding procedures or qualification records, and it does not replace your responsible welding coordinator or welding engineer.
  • It reads the result written on an NDE, dimensional or coating report. It does not interpret ultrasonic data or re-measure anything.
  • It does not issue or assess a factory production control certificate, a declaration of performance or a CE or UKCA mark.
  • It only knows the documents you upload. A requirement in a referenced specification that is not in the set will be missed.
  • The fair test is one of your own completed jobs: run its records through a review and compare the findings with what you already know went wrong.

Which tools are available now

Document Review is generally available. The other tools on this page are in beta: you request access and we onboard each team ourselves. See OdysseyGPT for manufacturing and the manufacturing module.

Try it on your own documents

Free sample: a certificate check report

Send up to 20 material certificates and the PO. Get a certificate check report.

Get the free result

Buyer questions

20 questions bid engineers, proposal engineers and buyers ask. Last reviewed:

What documentation does structural steel fabrication need?

You start from the fabrication specification, the design drawings and the welding, NDE and coating requirements. During the job you produce an inspection and test plan, welding procedures and welder qualifications, a weld log, mill certificates, traceability records, NDE reports, dimensional reports and coating records. Work to EN 1090 adds a declaration of performance. The customer's documentation clause sets the final list and the dossier index.

What does quality control mean in steel fabrication?

It means checking the work at set stages and keeping a record of each check. The usual stages are material receipt, cutting and marking, fit-up, welding, visual and non-destructive examination, dimensional survey, surface preparation and coating. The inspection and test plan lists each stage, the document that gives the acceptance limit, and whether the customer's inspector holds, witnesses or only reviews it.

What is in a structural steel fabrication enquiry?

Usually a scope of work, design drawings, a material take-off or tonnage, and a fabrication specification that names the governing code. Welding, NDE, painting or galvanising and tolerance requirements may be separate documents or sections. There is normally a quality specification and a list of records to submit. Read the specifications before the drawings, because they decide how much each tonne costs to inspect and document.

Which welding code applies to structural steel?

The contract decides. American and many international projects name AWS D1.1, the structural welding code for steel. European projects name EN 1090-2, which sends procedure and welder qualification to ISO standards. Some owners add their own welding specification on top. If the enquiry names two systems, ask which governs procedures, welder qualification and NDE personnel before you price.

What is an execution class in a steel specification?

An execution class is one of four levels, EXC1 to EXC4, in EN 1090-2. The designer assigns it to the structure or to particular components. A higher class brings stricter welding control, more inspection, deeper traceability and more records. Your certificate must cover the class specified. If the enquiry calls up EN 1090-2 without stating a class, raise a clarification.

Can we use prequalified welding procedures on a D1.1 job?

Often, but check two things. First, the procedure must sit inside every prequalification condition in the edition of AWS D1.1 your contract names. One variable outside them means a qualification test. Second, read the customer's welding specification. Some customers require all procedures to be qualified by test, or add impact or hardness tests. Either requirement belongs in your price or your deviation list.

Can we use ASME Section IX welder qualifications on structural steel?

Do not assume so. AWS D1.1 has its own welder qualification rules, and Section IX is a separate system written for pressure equipment and piping. Acceptance of qualifications from another code is a matter for the customer's Engineer. If your welders hold only Section IX qualifications, say so in the offer and ask for written acceptance, or allow time and cost for new tests.

How much material traceability does structural steel need?

As much as the specification asks for. Some jobs need only evidence that the correct grade was supplied. Others need each member or plate tied to its heat number and mill certificate, sometimes down to individual pieces. The level changes how you cut, mark and store steel, so find the clause before pricing. See heat number traceability for the record chain.

Which mill certificate type does structural steel need?

The order states it. Structural plate and sections are commonly bought with an EN 10204 type 3.1 inspection certificate, which reports test results for the supplied batch. Types 2.1 and 2.2 do not report tests on the supplied batch itself and may be accepted for minor items. Type 3.2 adds an independent inspector. See EN 10204 3.1 vs 3.2.

Which welds on a steel structure need NDE?

Every weld gets a visual inspection. Testing beyond that, such as magnetic particle or ultrasonic examination, depends on the code, the execution class or loading type, the joint type and the customer's specification. Under AWS D1.1 the contract documents state it. Under EN 1090-2 the execution class drives it. Do not price NDE from the code alone. Read the drawing notes and the NDE specification too.

What goes in a steel fabricator's deviation list?

Any requirement you will not meet as written, with what you offer instead. Common rows cover the execution class your certificate allows, procedures qualified by test where you hold prequalified ones, NDE extent and personnel certification, mill certificate type, traceability level, tolerances at interfaces, and the coating system. The technical deviation list guide gives the format and a template.

What should a structural steel ITP contain?

A row for each inspection stage from material receipt to final release: the activity, the procedure, the acceptance reference, the record produced, and the inspection level for you, the customer and any third party. Coating and dimensional stages are the ones most often left thin. Start from the structural steel ITP template and match every hold and witness point in the customer's quality specification.

Does structural steel need a weld map?

Only if the specification asks for weld-by-weld traceability, which is common on offshore, lifting and higher execution class work. Then each weld needs an identity that ties it to a welder, a procedure and any NDE report. Building frames often record welding by member or assembly instead. The weld map and weld log template shows the columns to keep.

What coating records does a steel fabricator hand over?

Typically the surface preparation record, the environmental conditions during application, the paint batch numbers, the film thickness readings for each coat, and any repair record. Galvanised work has the galvaniser's certificate and thickness checks. The customer's coating specification, or ISO 12944 where it is called up, sets what is measured and how often. Check whether the customer's inspector must witness the readings.

Does fabricated structural steelwork need CE marking?

For structural components placed on the EU market under EN 1090-1, yes. The fabricator needs factory production control certified by a notified body, then issues a declaration of performance and applies the mark. Great Britain currently accepts UKCA or CE marking. Steel frames for skids and machinery may fall under other rules, so confirm the route for your product. See EN 1090.

What should a buyer check on a fabricator's EN 1090 certificates?

Ask for three documents: the factory production control certificate, the welding certificate and the declaration of performance. Check that they are in date, that the body's number is valid, that the execution class covers the project's, and that the steel grades and thicknesses on the drawings fall inside the scope. A certificate for a lower class does not cover the work.

What goes in the final dossier for a skid package?

Records from every discipline on the skid, under one index. Structural: welding, material, NDE and dimensional records for the frame and lifting points. Piping: weld logs, certificates, NDE and pressure test records. Mechanical: sub-supplier data books. Electrical and instrumentation: datasheets, calibration and equipment certificates and loop checks. Then coating records and the factory acceptance test report.

Why does a skid often need two sets of welding qualifications?

Because the base frame and the pipework follow different codes. The frame is structural steel, commonly welded to AWS D1.1 or EN 1090-2. The pipework follows a piping code such as ASME B31.3, which uses ASME Section IX qualifications. Keep the two sets of procedures and welder records apart, and state in the ITP which code applies to each group of welds.

What does OdysseyGPT check for a steel fabricator?

Documents. Document Review compares the customer's fabrication specification with your procedures before you quote. After award, ITP Validator (beta) checks your ITP, Material Certificate Review (beta) checks mill certificates, and Welding Qualification Review (beta) and NDE Coverage Review (beta) check welding and NDE records against the weld log. Each finding quotes its source, and your engineers decide what to do.

What does OdysseyGPT not do for steel fabrication?

It does not read fabrication drawings, erection drawings or 3D models. It does no structural or connection design, nesting, estimating or production tracking, and it does not write welding procedures. It does not certify anything. It reads the specifications, logs, certificates and reports you upload and checks them against the customer's requirements. Fabrication management and detailing software do the other jobs.

Frequently asked questions

What documents are needed for structural steel fabrication?

Before work: the fabrication specification, design drawings, and the welding, NDE, coating and tolerance requirements. During and after: an inspection and test plan, welding procedures and welder qualifications, a weld log, mill certificates, traceability records to the level specified, NDE, dimensional and coating reports, and a final dossier. EN 1090 work adds a declaration of performance.

What is quality control in steel fabrication?

The checks a fabricator makes at each stage, and the records that prove them: material receipt against certificates, fit-up, welding to a qualified procedure, visual and non-destructive examination, dimensional checks and coating inspection. The inspection and test plan lists the stages and who attends each one.

Does OdysseyGPT read steel fabrication drawings or Tekla models?

No. It reads text and tables in PDF, Word, Excel and CSV files. Give it the specifications, the weld log, certificates and reports, and it checks those against the customer's requirements.

Is OdysseyGPT steel fabrication management software?

No. It does not estimate, nest, schedule or track production. It checks the documents a job produces against what the customer specified and reports the gaps, each with a quote from the source.

References

What is D1.1?

American Welding Society

Publisher's description of the structural welding code, including its use for skids and modules. The code is a paid document.

Visit source

UKCA marking of fabricated structural steelwork

SteelConstruction.info (BCSA and SCI)

EN 1090-1 and -2, execution classes, factory production control and the declaration of performance.

Visit source

Welding

SteelConstruction.info (BCSA and SCI)

Welding quality management, procedure and welder qualification, and inspection under EN 1090-2.

Visit source

Fabrication

SteelConstruction.info (BCSA and SCI)

Visit source

Regulation (EU) No 305/2011 (Construction Products Regulation)

EUR-Lex

Declaration of performance and CE marking for construction products.

Visit source

ISO 3834, EN 10204 and ISO 12944

ISO and CEN

Paid standards, named here by title and subject only.

Related Pages

Module

Manufacturing QA

The module hub: its tools, what they read and the free result.

Standards

AWS D1.1 structural welding code

Scope, prequalified procedures, inspection roles and an enquiry checklist.

Standards

EN 1090 explained

Execution classes, factory production control and CE or UKCA marking.

Glossary

Execution class

EXC1 to EXC4 and what the class changes for a fabricator.

Glossary

Factory production control

The fabricator's own documented control of production.

Glossary

Skid package

Equipment, piping and instruments on one frame, with one dossier.

Template

Structural steel ITP template

An inspection and test plan layout for steelwork.

Product

ITP Validator (beta)

Your ITP checked against the customer's quality specification.

Product

Welding Qualification Review (beta)

Procedures and welder records checked against each weld in the log.

Product

Material Certificate Review (beta)

Mill certificates checked against the purchase requirements.

Product

Document Review

A fabrication specification checked against your own procedures.

Standards

EN 10204 3.1 vs 3.2

Which inspection certificate the order requires.

Comparison

Steel fabrication software compared

Fabrication management, detailing and document checking, sorted by job.

Industry

Pipe spool fabricators

The piping records that sit beside the steelwork on a skid.

Pillar guide

Technical deviation list guide

The deviations you agree at bid stage are the ones you verify and record later.