OdysseyGPT

Standards explainer

AWS D1.1 structural welding code: scope, prequalified procedures and what to check in a fabrication enquiry

A plain-English overview of AWS D1.1 for bid and quality engineers at steel fabricators and skid builders, ending with a checklist for a fabrication enquiry.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

AWS D1.1 is the American Welding Society's Structural Welding Code for steel. It covers the design of welded connections, the qualification of welding procedures and welders, fabrication, and inspection of load-bearing steel structures. Some welding procedures can be prequalified without testing. All others must be qualified by test.

Key Takeaways

  • D1.1 is a complete structural welding code: design of connections, qualification, fabrication and inspection.
  • A prequalified WPS needs no qualification test, but it must stay inside every prequalification condition and be written down.
  • The contractor inspects its own work. The owner may add verification inspection.
  • ASME Section IX qualifications are a different system. Do not assume one covers the other.

Free sample: a certificate check report. Send up to 20 material certificates and the PO. Get a certificate check report. Get the free result

What is AWS D1.1?

AWS D1.1/D1.1M, Structural Welding Code - Steel, is published by the American Welding Society. AWS describes it as the code that sets the requirements for welding structural steel in load-bearing applications, and says it is used for buildings, bridges and infrastructure, and by equipment makers for skids, modules and equipment. It is not written for consumer products.

The code is broad. It deals with how welded connections are designed, how welding procedure specifications and welding personnel are qualified, how the work is fabricated, how it is inspected, and with stud welding and tubular structures. A fabricator working to D1.1 therefore finds procedure rules, workmanship rules and weld acceptance criteria in the same book.

D1.1 is one of a family. AWS publishes separate structural welding codes for other materials and uses, such as D1.2 for aluminium, D1.3 for sheet steel and D1.6 for stainless steel. If the take-off includes thin sheet or stainless steel, check which code the contract applies to those parts.

The code is a paid document and is revised every few years. When we checked in November 2026, AWS listed D1.1/D1.1M:2025 with a first amendment as the current edition. Clause numbers moved between recent editions, so an older specification may point to a clause that now has a different number. Work to the edition your contract names.

Prequalified and qualified-by-test procedures

Every production weld under D1.1 is made to a written welding procedure specification (WPS). The code offers two ways to arrive at one.

Two routes to a WPS under AWS D1.1 (concept only; the conditions are in the code)
RouteHow it worksWhat the fabricator holds
Prequalified WPSThe code lists conditions for the welding process, the steel, the filler metal, the joint detail, preheat and other variables. A procedure that stays inside all of them is exempt from qualification testingA written WPS. There is no test record behind it, so the WPS itself must show that each condition is met
WPS qualified by testAnything outside the prequalified conditions is proved by welding a test piece and testing itThe WPS and a procedure qualification record with the test results

Prequalification saves the cost of testing, which is why structural shops rely on it. It is also where audits find problems. A single variable outside the conditions, such as a joint detail, a process mode or a steel that is not on the code's list, means the procedure is not prequalified and needs a test. Not every welding process can be prequalified.

Customer specifications often narrow this. Some require every procedure to be qualified by test. Some add impact testing or hardness testing to the qualification. Either changes the price and the programme, so it belongs in the offer.

Welder qualification under D1.1

Welders, welding operators and tack welders are qualified by test. The test a welder passes sets what that welder may weld in production: the process, the positions, the thickness range and the type of joint. The contractor is responsible for qualifying its own welders and for keeping the records.

A qualification does not last by default. It stays valid only while the welder keeps using the process, which the contractor shows with a continuity record. If the record has a gap longer than the code allows, the welder has to requalify. The gap is the item an inspector asks to see first, so keep the log current. Our welder continuity log template gives a layout.

Customers sometimes ask for welder tests to be witnessed by their inspector or by a third party, or will not accept qualifications from a previous employer. Look for those sentences in the welding specification.

Who inspects what?

D1.1 separates two kinds of inspection. Understanding the split tells you which inspections you must price and which the customer may add.

Inspection roles under AWS D1.1 in outline
RoleWho it isWhat it does
Contractor's inspectionThe fabricator's or erector's own inspectorInspects and tests the work during fabrication and erection. This is the contractor's responsibility unless the contract says otherwise
Verification inspectionAn inspector acting for the owner or the EngineerChecks the contractor's work and records. It is the owner's choice whether to use it
The EngineerThe owner's designated engineerApproves matters the code leaves to engineering judgement, and specifies any NDT beyond visual inspection in the contract documents

Inspectors must be qualified on a basis the code accepts. In practice many specifications ask for an AWS Certified Welding Inspector. NDT technicians need their own certification, and the specification usually names the scheme. Which welds get ultrasonic, magnetic particle or radiographic testing, and how many, is a contract matter. Find it in the drawings and the NDE specification, not only in the code.

AWS D1.1 vs ASME Section IX

AWS D1.1 and ASME Section IX compared in outline (own summary)
QuestionAWS D1.1ASME Section IX
What is it?A structural welding code for steel: design of welded connections, qualification, fabrication and inspectionA qualification standard for welding, brazing and fusing procedures and personnel
Where is it used?Buildings, bridges, structural frames, and the steelwork of skids and modulesPressure vessels, boilers and piping, when a construction code such as ASME B31.3 calls it up
Can a WPS be used without a qualification test?Yes, if it meets every prequalification conditionNormally no. Each WPS rests on a PQR. Certain published standard procedures may be adopted under conditions the code sets
Where are production weld acceptance criteria?In D1.1 itselfIn the construction code that references Section IX
Do qualifications transfer?Not automatically. Ask the Engineer before offering Section IX recordsNot automatically. The construction code decides what it accepts

A skid often carries both. The base frame is welded to D1.1 and the pipework on it to a piping code with Section IX qualifications. Keep the two sets of procedures and welder records separate in the dossier and say in the ITP which applies to which weld. For the piping side, see pipe spool fabricators.

What to check in a fabrication enquiry against AWS D1.1

Enquiry checklist for work specified to AWS D1.1
CheckWhere to lookWhy it matters
Edition of D1.1Fabrication specification, list of codesClause numbers and some rules differ between editions
Loading type: static or cyclicDesign drawings and general notesThe code treats cyclically loaded structures more strictly
Steel grades and thicknessesMaterial take-off and drawingsThey decide whether your procedures can be prequalified
Whether prequalified procedures are acceptedWelding specificationA requirement to qualify by test adds weeks and cost
Extra qualification testsWelding specificationImpact or hardness tests may not be in your existing records
Welder qualification rulesWelding specificationWitnessed tests or project-specific tests need planning
NDT method, extent and personnelNDE specification and drawing notesThe contract, not the code alone, sets how much testing is done
Verification inspection and hold pointsQuality specificationThe owner's inspector may hold fit-up, welding or coating
Other codes on the same jobScope of workStainless, sheet steel, seismic or piping work may bring a second code
Records to submitDocumentation requirementsWPSs for approval before welding can hold the start of fabrication

Our Document Review compares the customer's welding and fabrication specifications with your own procedures and quotes both sides for each difference. After award, the Welding Qualification Review (beta) checks the procedures, qualification records and welder records you upload against each weld in the weld log. It does not decide whether a WPS is prequalified and it does not write procedures. A welding engineer does that.

Try it on your own documents

Free sample: a certificate check report

Send up to 20 material certificates and the PO. Get a certificate check report.

Get the free result

Frequently asked questions

What is AWS D1.1?

The American Welding Society's Structural Welding Code for steel. It sets requirements for the design of welded connections, the qualification of procedures and welders, fabrication and inspection of load-bearing steel structures.

What is a prequalified WPS in AWS D1.1?

A welding procedure specification that meets every prequalification condition in the code and is therefore exempt from qualification testing. It must still be written down, and a procedure outside any one condition has to be qualified by test.

Is AWS D1.1 the same as ASME Section IX?

No. D1.1 is a full structural welding code with its own qualification, fabrication and inspection rules. Section IX only covers qualification and is used with pressure equipment and piping codes. Qualifications do not transfer automatically.

Does AWS D1.1 apply to skids?

Often, for the structural frame. AWS says equipment makers use D1.1 for skids and modules. The contract decides, and piping or pressure parts on the skid usually follow a different code.

Who is responsible for inspection under AWS D1.1?

The contractor inspects its own fabrication and erection unless the contract says otherwise. The owner may also appoint a verification inspector to check the work and the records.

References

What is D1.1?

American Welding Society

Publisher's description of scope, users and the current edition. Read 15 Nov 2026. The code is a paid document.

Visit source

The Importance of Understanding AISC and AWS Codes

AWS Welding Digest

What D1.1 covers, contractor quality control and welder qualification.

Visit source

Understanding Prequalified WPSs and What QA/QCs Should Know

CEI

Secondary source on the prequalified route.

Visit source

UFC 3-320-01A Welding Structural (inspection and NDT sections)

US Department of Defense, Unified Facilities Criteria (hosted copy)

Secondary source on the contractor's inspection, the owner's verification inspection and specifying NDT in the contract documents.

Visit source

Standard Welding Procedure Specifications (SWPS)

American Welding Society

Background on standard procedures and their use with other codes.

Visit source

ASME BPVC Section IX: Welding, Brazing, and Fusing Qualifications

ASME

Visit source

Related Pages