The short answer

ASME B31.3 is the ASME code for process piping, the piping found in refineries, chemical, pharmaceutical and related plants. It sets requirements for materials, design, fabrication, assembly, erection, examination, inspection and testing. How strict the rules are for a line depends on its fluid service category, which the owner assigns.

Key Takeaways

  • B31.3 covers process piping. Power piping is covered by B31.1.
  • The owner assigns the fluid service category, and the category changes the examination and testing rules.
  • Welding procedures and welders are qualified to ASME Section IX, with extra rules in B31.3 itself.
  • The customer's specification usually adds to the code. Check both before you quote.

Free sample: a certificate check report. Send up to 20 material certificates and the PO. Get a certificate check report. Get the free result

What is ASME B31.3?

ASME B31.3, Process Piping, is one section of the ASME B31 Code for Pressure Piping. ASME describes it as covering piping typically found in petroleum refineries, chemical, pharmaceutical, textile, paper, semiconductor and cryogenic plants, and in related processing plants and terminals. It applies to piping for many kinds of fluid, including chemicals, petroleum products, gas, steam, air, water, refrigerants and cryogenic fluids.

The code sets requirements for materials and components, design, fabrication, assembly, erection, examination, inspection and testing. It is written for new piping. A fabricator meets it mainly through the fabrication, examination and testing rules, but the design choices behind a piping class, such as material and wall thickness, come from it too.

B31.3 is a paid document and it is revised regularly. ASME's page listed the 2024 edition when we checked in November 2026. Use the edition your contract names, which may be older.

Fluid service categories in outline

B31.3 does not treat every line the same way. It groups piping by fluid service, and some of its rules, including how much examination is required and which leak tests are allowed, change with the category. The owner is responsible for assigning the category. A fabricator should find it on the line list, the piping class or the isometric, and should ask if it is missing.

ASME B31.3 fluid services in outline (own summary; the code's definitions govern)
Fluid serviceIn plain termsWhat it means for a fabricator
NormalThe default. Most process piping that is not placed in another categoryThe base rules of the code apply
Category DLow-hazard fluids, such as non-flammable and non-toxic utilities, within limits on pressure and temperature that the code definesReduced examination and testing rules may be used, if the owner has assigned this category
Category MHighly toxic fluids, where exposure to a very small leak could cause serious irreversible harmStricter rules for design, fabrication, examination and leak testing
High PressurePiping the owner designates for the code's high pressure chapterA separate chapter with its own design, fabrication and examination rules
Elevated TemperaturePiping that operates hot enough for time-dependent material behaviour to matterAdditional rules, mainly for design and for welds in that service
High PurityPiping where cleanliness matters, such as semiconductor and hygienic bioprocessing systemsA separate chapter with its own joining, examination and cleanliness rules

This page does not reproduce the code's examination percentages or acceptance criteria. For your spools, the fluid service category and the customer's specification set them. Many customers ask for more examination than the code's minimum, so the specification is often the governing document in practice.

How B31.3 ties to ASME Section IX welding

B31.3 does not contain its own full system for qualifying welding. It sends the user to ASME Section IX, which covers the qualification of welding procedures and of welders and welding operators. A fabricator therefore needs a welding procedure specification (WPS) supported by a procedure qualification record (PQR), and welders with current performance qualifications, for every production weld. See WPS, PQR and WPQ.

B31.3 then adds its own requirements on top of Section IX. These include rules for preheat and post-weld heat treatment by material and thickness, and conditions under which extra qualification tests, such as impact testing, are needed. The customer's welding specification usually adds more: permitted processes, consumable controls, hardness limits and repair rules. A WPS that is valid under Section IX can still fall short of the code or the specification.

Examination, inspection and testing under B31.3

B31.3 separates two activities that are often confused. Examination is the quality control work done by the manufacturer, fabricator or erector, such as visual examination, radiography, ultrasonic, magnetic particle and liquid penetrant examination. Inspection is done for the owner, by the owner's inspector, to verify that the required examination and testing have been carried out.

The extent of examination depends on the fluid service and on certain design conditions. Where the code asks for a sample of welds to be examined and a sampled weld is rejected, further welds have to be examined. That is why a weld log needs to show which welds belong to which lot and welder.

The code also requires piping to be leak tested before it goes into service. A hydrostatic test is the usual method. The code provides for pneumatic and other tests in set circumstances, and for Category D service an initial service leak test may be used if the owner agrees. Spools are often tested after erection as part of a complete system, so check whether the enquiry asks for a shop test as well.

ASME B31.3 vs ASME B31.1

B31.3 and B31.1 compared (own summary of the publisher's scope descriptions)
PointASME B31.3 Process PipingASME B31.1 Power Piping
Typical plantsRefineries, chemical, pharmaceutical and related processing plants and terminalsElectric power generating stations, industrial and institutional plants, and district heating and cooling systems
Boiler external pipingNot its subjectCovered, for power boilers within the limits the code sets
How requirements are gradedBy fluid service category, assigned by the ownerDoes not use the B31.3 fluid service categories
Welding qualificationASME Section IX, with B31.3 additionsASME Section IX, with B31.1 additions
Life cycleNew piping: design through testingThe scope description also names operation and maintenance

The two codes can sit side by side on one site, for example in a process plant with its own steam generation. The rules for examination, heat treatment and testing differ, so the same weld can have different requirements under each. Confirm which code governs each line before you price it.

What to check in a piping fabrication enquiry against ASME B31.3

Checks to make before you quote
CheckWhy it matters
Code and edition named in the piping specification, the piping classes and the purchase orderDocuments in one package often name different editions, or name B31.1 for some lines
Fluid service category for every line class in your scopeIt changes the examination and testing rules, and it is the owner's decision, not yours
Examination method and extent in the customer's specification, by line classCustomers often ask for more than the code's minimum. Price what the specification says
Acceptance criteria and who interprets the resultsA named standard, a required personnel qualification level or third-party review all add cost
Welding processes and consumables permittedYour qualified procedures may use a process the specification excludes
Extra procedure qualification tests, such as impact or hardness testingExisting PQRs may not include them, and a new qualification takes time
Preheat and PWHT requirements, and the method allowedHeat treatment beyond the code, or furnace-only rules, change cost and schedule
Sour service, low temperature or other special service notesThey bring material, hardness and certificate requirements, for example under NACE MR0175 / ISO 15156
Material certificate type and positive material identificationAn EN 10204 type 3.1 or 3.2 requirement and PMI extent affect purchasing
Leak test scope: shop test, test after erection, or bothShop testing needs blinds, test water of the right quality, calibrated gauges and time
Owner's inspector: hold and witness points and notice periodsThey set when fabrication can move on and when spools can ship
Records required per weld, per spool and per isometricThe weld log, NDE reports and certificates become the data book

OdysseyGPT's Document Review checks a customer's specification package against your own procedures and drafts the compliance matrix and deviation list, each row quoting its source. After the order, the Welding Qualification Review (beta) checks WPS, PQR and welder records against each weld in the weld log, and the NDE Coverage Review (beta) matches NDE reports to the welds that need them. OdysseyGPT does not read isometrics, does not do stress analysis and does not decide which fluid service applies. See how this fits a fabricator's work on the pipe spool fabricators page.

Try it on your own documents

Free sample: a certificate check report

Send up to 20 material certificates and the PO. Get a certificate check report.

Get the free result

Frequently asked questions

What is ASME B31.3 used for?

It is the code for process piping: the piping in refineries, chemical, pharmaceutical and related plants. It sets requirements for materials, design, fabrication, assembly, erection, examination, inspection and testing of that piping.

What is the difference between ASME B31.1 and B31.3?

B31.1 covers power piping, such as piping in generating stations and heating systems, including boiler external piping. B31.3 covers process piping and grades its requirements by fluid service category. Their examination, heat treatment and testing rules differ.

What are the fluid service categories in ASME B31.3?

Normal fluid service is the default. The code also defines Category D for low-hazard fluids, Category M for highly toxic fluids, and High Pressure, Elevated Temperature and High Purity fluid services. The owner assigns the category.

Who decides the fluid service category?

The owner. A fabricator should find the category on the line list, piping class or isometric. If it is missing, ask before quoting, because it changes the examination and testing required.

Does ASME B31.3 require welders to be qualified to Section IX?

Yes. B31.3 refers to ASME Section IX for qualifying welding procedures and welders, and adds some requirements of its own. The customer's welding specification may add more.

How much radiography does ASME B31.3 require?

It depends on the fluid service category and on design conditions, and the customer's specification often asks for more than the code's minimum. Read the edition of the code your contract names and the specification's NDE table.

References

ASME B31.3 Process Piping

ASME

Paid code. The publisher's page gives the scope description used here.

Visit source

ASME B31.1 Power Piping

ASME

Paid code. The publisher's page gives the scope description used here.

Visit source

ASME BPVC Section IX: Welding, Brazing, and Fusing Qualifications

ASME

Visit source

When should Category M fluid service be selected for ASME B31.3 piping systems?

Becht

Explains that the owner decides the category and what Category M is for.

Visit source