What is ASME B31.3?
ASME B31.3, Process Piping, is one section of the ASME B31 Code for Pressure Piping. ASME describes it as covering piping typically found in petroleum refineries, chemical, pharmaceutical, textile, paper, semiconductor and cryogenic plants, and in related processing plants and terminals. It applies to piping for many kinds of fluid, including chemicals, petroleum products, gas, steam, air, water, refrigerants and cryogenic fluids.
The code sets requirements for materials and components, design, fabrication, assembly, erection, examination, inspection and testing. It is written for new piping. A fabricator meets it mainly through the fabrication, examination and testing rules, but the design choices behind a piping class, such as material and wall thickness, come from it too.
B31.3 is a paid document and it is revised regularly. ASME's page listed the 2024 edition when we checked in November 2026. Use the edition your contract names, which may be older.
Fluid service categories in outline
B31.3 does not treat every line the same way. It groups piping by fluid service, and some of its rules, including how much examination is required and which leak tests are allowed, change with the category. The owner is responsible for assigning the category. A fabricator should find it on the line list, the piping class or the isometric, and should ask if it is missing.
| Fluid service | In plain terms | What it means for a fabricator |
|---|---|---|
| Normal | The default. Most process piping that is not placed in another category | The base rules of the code apply |
| Category D | Low-hazard fluids, such as non-flammable and non-toxic utilities, within limits on pressure and temperature that the code defines | Reduced examination and testing rules may be used, if the owner has assigned this category |
| Category M | Highly toxic fluids, where exposure to a very small leak could cause serious irreversible harm | Stricter rules for design, fabrication, examination and leak testing |
| High Pressure | Piping the owner designates for the code's high pressure chapter | A separate chapter with its own design, fabrication and examination rules |
| Elevated Temperature | Piping that operates hot enough for time-dependent material behaviour to matter | Additional rules, mainly for design and for welds in that service |
| High Purity | Piping where cleanliness matters, such as semiconductor and hygienic bioprocessing systems | A separate chapter with its own joining, examination and cleanliness rules |
This page does not reproduce the code's examination percentages or acceptance criteria. For your spools, the fluid service category and the customer's specification set them. Many customers ask for more examination than the code's minimum, so the specification is often the governing document in practice.
How B31.3 ties to ASME Section IX welding
B31.3 does not contain its own full system for qualifying welding. It sends the user to ASME Section IX, which covers the qualification of welding procedures and of welders and welding operators. A fabricator therefore needs a welding procedure specification (WPS) supported by a procedure qualification record (PQR), and welders with current performance qualifications, for every production weld. See WPS, PQR and WPQ.
B31.3 then adds its own requirements on top of Section IX. These include rules for preheat and post-weld heat treatment by material and thickness, and conditions under which extra qualification tests, such as impact testing, are needed. The customer's welding specification usually adds more: permitted processes, consumable controls, hardness limits and repair rules. A WPS that is valid under Section IX can still fall short of the code or the specification.
Examination, inspection and testing under B31.3
B31.3 separates two activities that are often confused. Examination is the quality control work done by the manufacturer, fabricator or erector, such as visual examination, radiography, ultrasonic, magnetic particle and liquid penetrant examination. Inspection is done for the owner, by the owner's inspector, to verify that the required examination and testing have been carried out.
The extent of examination depends on the fluid service and on certain design conditions. Where the code asks for a sample of welds to be examined and a sampled weld is rejected, further welds have to be examined. That is why a weld log needs to show which welds belong to which lot and welder.
The code also requires piping to be leak tested before it goes into service. A hydrostatic test is the usual method. The code provides for pneumatic and other tests in set circumstances, and for Category D service an initial service leak test may be used if the owner agrees. Spools are often tested after erection as part of a complete system, so check whether the enquiry asks for a shop test as well.
ASME B31.3 vs ASME B31.1
| Point | ASME B31.3 Process Piping | ASME B31.1 Power Piping |
|---|---|---|
| Typical plants | Refineries, chemical, pharmaceutical and related processing plants and terminals | Electric power generating stations, industrial and institutional plants, and district heating and cooling systems |
| Boiler external piping | Not its subject | Covered, for power boilers within the limits the code sets |
| How requirements are graded | By fluid service category, assigned by the owner | Does not use the B31.3 fluid service categories |
| Welding qualification | ASME Section IX, with B31.3 additions | ASME Section IX, with B31.1 additions |
| Life cycle | New piping: design through testing | The scope description also names operation and maintenance |
The two codes can sit side by side on one site, for example in a process plant with its own steam generation. The rules for examination, heat treatment and testing differ, so the same weld can have different requirements under each. Confirm which code governs each line before you price it.
What to check in a piping fabrication enquiry against ASME B31.3
| Check | Why it matters |
|---|---|
| Code and edition named in the piping specification, the piping classes and the purchase order | Documents in one package often name different editions, or name B31.1 for some lines |
| Fluid service category for every line class in your scope | It changes the examination and testing rules, and it is the owner's decision, not yours |
| Examination method and extent in the customer's specification, by line class | Customers often ask for more than the code's minimum. Price what the specification says |
| Acceptance criteria and who interprets the results | A named standard, a required personnel qualification level or third-party review all add cost |
| Welding processes and consumables permitted | Your qualified procedures may use a process the specification excludes |
| Extra procedure qualification tests, such as impact or hardness testing | Existing PQRs may not include them, and a new qualification takes time |
| Preheat and PWHT requirements, and the method allowed | Heat treatment beyond the code, or furnace-only rules, change cost and schedule |
| Sour service, low temperature or other special service notes | They bring material, hardness and certificate requirements, for example under NACE MR0175 / ISO 15156 |
| Material certificate type and positive material identification | An EN 10204 type 3.1 or 3.2 requirement and PMI extent affect purchasing |
| Leak test scope: shop test, test after erection, or both | Shop testing needs blinds, test water of the right quality, calibrated gauges and time |
| Owner's inspector: hold and witness points and notice periods | They set when fabrication can move on and when spools can ship |
| Records required per weld, per spool and per isometric | The weld log, NDE reports and certificates become the data book |
OdysseyGPT's Document Review checks a customer's specification package against your own procedures and drafts the compliance matrix and deviation list, each row quoting its source. After the order, the Welding Qualification Review (beta) checks WPS, PQR and welder records against each weld in the weld log, and the NDE Coverage Review (beta) matches NDE reports to the welds that need them. OdysseyGPT does not read isometrics, does not do stress analysis and does not decide which fluid service applies. See how this fits a fabricator's work on the pipe spool fabricators page.
Try it on your own documents
Free sample: a certificate check report
Send up to 20 material certificates and the PO. Get a certificate check report.