What it is

An execution class is one of four levels, EXC1 to EXC4, defined in EN 1090-2 for steel structures. The designer assigns it to a structure or component. The higher the class, the stricter the requirements for welding control, inspection, traceability and records. A fabricator's certificate states the highest class it may supply.

Key Takeaways

  • There are four classes, EXC1 to EXC4, and requirements rise with the number.
  • The designer specifies the class. The fabricator's certificate must cover it.
  • Different parts of one structure can carry different classes.
  • A missing class in an enquiry is a clarification, not an assumption.

Why it matters

An execution class is a label the designer puts on a steel structure, or on part of one, to say how much control its fabrication needs. EN 1090-2 defines four classes, EXC1, EXC2, EXC3 and EXC4, and its requirements get stricter as the number rises. The class is chosen from the consequences of a failure and from how the structure is loaded and made. It is the designer's or structural engineer's decision, not the fabricator's. One class can cover the whole structure, and a higher class can be given to particular components or connection details. For the fabricator the class has practical effects. It changes how much non-destructive testing the welds receive, how far materials must be traced to their inspection documents, which level of welding quality system applies, and how much has to be recorded. It also limits which work a shop may take. A fabricator's factory production control certificate and welding certificate state the highest class they cover, and the shop can declare performance only up to that class. UK industry guidance says EXC2 is right for most buildings and advises specifiers not to add higher-class requirements without a reason. Bridges and structures where failure would have severe consequences are commonly placed higher. An enquiry that calls up EN 1090-2 should state the class. If it does not, ask before pricing, because the class changes the inspection and documentation cost of every tonne.

How OdysseyGPT uses it

OdysseyGPT does not select or assess an execution class. It reads the customer's specification package and reports what it says. Customer Specification Review (beta) lists the stated requirements and marks ones that are missing or unclear, such as a specification that calls up EN 1090-2 and never gives a class. Document Review compares the package with your own procedures and quotes both sides. An engineer decides what each finding means.

Evaluation questions

What does the execution class change in the shop?

The level of welding quality system, the knowledge required of the welding coordinator, how much weld testing is done, how far materials are traced and how much is documented. The detail is in EN 1090-2.

Is the execution class the same as the consequence class?

No. The consequence class describes how serious a failure would be. It is one input the designer uses to select the execution class.

Can OdysseyGPT tell me which execution class applies?

No. It reports what the customer's documents say and flags a class that is missing or stated inconsistently. Selecting the class is the designer's job.

Frequently asked questions

What is an execution class?

A level, from EXC1 to EXC4, that EN 1090-2 uses to scale its requirements for fabricating and inspecting a steel structure. A higher number means stricter requirements.

Who decides the execution class?

The designer or structural engineer, based on the consequences of failure and the type of structure. The fabricator's task is to hold certification that covers the class specified.

Which execution class applies to ordinary buildings?

UK industry guidance says EXC2 suits most buildings. The project's designer still has to state the class, and some components may be given a higher one.

Can a fabricator certified for EXC2 take EXC3 work?

No. A certificate covers the stated class and the classes below it. A shop certified for EXC3 can take EXC1 to EXC3 work. A shop certified for EXC2 cannot take EXC3.

References

UKCA marking of fabricated structural steelwork

SteelConstruction.info (BCSA and SCI)

Who specifies the execution class, what a certified class allows, and guidance on EXC2 for buildings.

Visit source

UKCA marking for structural steel

BM TRADA

Examples of structures in each class.

Visit source

EN 1090-2: Execution of steel structures and aluminium structures. Technical requirements for steel structures