Structural steel ITP template: inspection and test plan for steel fabrication (Excel and CSV)

For steel fabricators: fifteen inspection steps from goods-in to the fabrication dossier, each with its governing document, extent, record and intervention points.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

A structural steel ITP sets out each inspection during fabrication, from material receipt through cutting, fit-up, welding, NDE, dimensional checks and coating to final documentation. This free Excel template gives every step a governing document, an acceptance criteria reference, an extent, the record produced and H, W, R or M codes for fabricator, customer and third party.

Key Takeaways

  • Find the fabrication standard and level in the specification first. Traceability, weld inspection and paperwork all follow from it.
  • Acceptance criteria cells say where the limits are written. The limits themselves stay in the specification and the approved procedure.
  • The Extent column takes its sampling rules from the specification, never from this template.
  • The example has 15 steps for an invented pipe rack order (PO-EX-8120).

Download the structural steel ITP

Both files are free under CC BY 4.0, with no form to fill in. The XLSX opens in Excel, Google Sheets, LibreOffice and Numbers. The CSV carries the table only; the header block is in the XLSX.

Who needs a steelwork ITP, and when

Customers who buy pipe racks, platforms, skid frames or building steel often ask for an inspection and test plan with the first drawing submission. Write it once the fabrication drawings and welding procedures are far enough on to be named in it, and get it approved before cutting starts. After that it doubles as the running inspection record for the job.

  • The fabricator's quality engineer or responsible welding coordinator, who drafts it.
  • The customer's engineer, who marks where they want to attend or review.
  • A third-party inspector, where the contract appoints one.

How much traceability, weld inspection and documentation a job needs depends on the standard and level the specification calls up, for example an execution class under EN 1090 or the rules of AWS D1.1. Check the governing standard or contract. For plant equipment rather than steelwork, start from the general ITP template. See also steel fabricators.

Header block

Header block fields, with the invented example values
FieldExample
ProjectExample Pipe Rack and Access Platform (fictional)
CustomerExample Engineering Contractor Ltd (fictional)
Purchase orderPO-EX-8120 (fictional)
Scope of supplyPipe rack frames PR-01 to PR-06 and platform PF-01 (fictional)
Fabrication standard and levelAs stated in the specification (for example EN 1090-2 with its execution class, or AWS D1.1)
Project specificationPS-STR-004 Rev 1 (fictional)
Third partyAs the contract requires (fictional)
ITP no.ITP-EX-8120
RevisionA
Date2027-01-12
Prepared byQuality engineer
Approved by (customer)

Example steps: pipe rack frames and a platform

Invented example steps for PO-EX-8120 (some columns omitted)
No.Inspection or testGoverning documentAcceptance criteria referenceExtentRecordFabricatorCustomerThird partyRemarks
1Fabrication drawings, welding procedures and this plan approved before steel is cutDocument register DR-EX-8120Per specification PS-STR-004Every documentApproved drawings and proceduresHRR
2Material receipt: plates, sections and fasteners checked against the order, with their inspection certificatesGoods-in procedure QP-04Per specification and the material standard on the orderEach deliveryGoods-in record; certificate review checklistHRR
3Material identification: grade and heat or batch marks checked against the certificatesQP-04; traceability procedure QP-06Per specification and approved procedureEach deliveryMaterial identification recordH-M
4Cutting and marking: piece marks applied, and traceability kept to the level the specification requiresQP-06; cutting lists CL-EX-8120Per specification and approved procedureAs specifiedCutting list with heat numbersH-MThe traceability level comes from the specification. Check it before cutting starts.
5Holes, edges and weld preparations checked against the drawingsFabrication drawings FD-EX-8120Per specification and approved drawingAs specifiedIn-process inspection recordH--
6Fit-up of each assembly before welding: alignment, gaps and tack weldsFabrication drawings; WPSPer specification and approved procedureEvery assemblyFit-up inspection recordHMW
7Welding: approved procedure, qualified welder and consumable control for each jointWPS list WL-EX-8120; QP-08Per specification and approved procedureEvery jointWelding record; welder listHMM
8Visual inspection of finished weldsVisual inspection procedure NDT-EX-01Per specification and approved procedureAs specifiedVisual inspection reportHRW
9NDE of welds, by the methods and to the extent specifiedNDE procedures NDT-EX-02 to -04Per specification and approved procedureAs specifiedNDE reportsHRRMethods, extent and any waiting time before examination come from the specification and the standard it names.
10Dimensional check of finished members: length, squareness, hole positions and camber where shownFabrication drawings FD-EX-8120Per specification and approved drawingAs specifiedDimensional reportHW-
11Trial assembly, where specifiedTrial assembly procedure TA-EX-01Per specification and approved procedureFrames named in the specificationTrial assembly report with photographsHHWDelete the step if the specification does not ask for it.
12Surface preparation before coating or galvanisingCoating procedure CP-EX-02Per coating specification and approved procedureAs specifiedSurface preparation recordHM-
13Coating or galvanising inspection: appearance and thicknessCoating procedure CP-EX-02Per coating specification and approved procedureAs specifiedCoating inspection report or galvaniser's certificateHW-Keep the row for paint, for galvanising, or one of each.
14Final inspection: piece marks, damage, loose items and packing for transportQP-12; packing listPer specification and approved procedureEvery pieceFinal inspection reportHW-
15Documentation: fabrication dossier checked and released for shipmentDossier index DI-EX-8120Per contract document requirementsEvery documentRelease note; declaration or certificate the contract requiresHHRNothing ships before the release note is signed.

The file also has columns for phase, record number and status. The H, W, R and M entries were made up for this example. Your contract, and the standard it names, decide who attends what. Every example value is invented: the project, customer, bidders, purchase order, prices and every document, certificate, serial and report number do not exist. Standards are named but not quoted.

Intervention codes

CodeCommon meaning
H (hold)Fabrication stops at this step until the party named has inspected it or signed a release.
W (witness)The party is told in advance and can come to see the step. Fabrication carries on if they choose not to.
R (review)The party checks the document the step produces. Nobody needs to be on the shop floor.
M (monitor)The party can look at this work whenever they are in the shop. No notice is sent.
-The party takes no part in this step.

Legends differ from one customer to the next. Where the contract prints its own, copy it into the How to use sheet and use its letters.

Columns and what to write

ColumnWhat to write
No.Step number, in fabrication order.
Inspection or testWhat is inspected or tested at this step.
PhaseBefore fabrication, Material, Preparation, Assembly, Welding, Examination, Coating, Final or Documentation.
Governing documentThe drawing, procedure or specification section the step is done to.
Acceptance criteria referenceWhere the pass/fail limits are written: the project specification, the approved procedure or the drawing. Name the place; leave the values there.
ExtentHow much is inspected: every piece, every joint, each delivery, or as specified. Percentages come from the specification and the fabrication standard; do not invent them.
Record producedThe report, certificate or checklist this step leaves behind.
FabricatorFabricator's intervention: H, W, R, M or - (drop-down).
CustomerCustomer's intervention: H, W, R, M or - (drop-down).
Third partyThird-party inspector's intervention: H, W, R, M or - (drop-down).
Record no.The record's number, filled in when the step is done.
StatusNot started, Notified, Done, Released or NCR raised (drop-down). NCR rows turn red.
RemarksWhether the step applies, the notice the customer needs, or what is still open.

How to fill in the plan

  1. Fill in the header block: the scope, the project specification, and the fabrication standard and level it names. That level drives traceability, weld inspection and documentation, so get it from the specification, not from habit.
  2. Go through the steps from material receipt to documentation. Delete what your contract does not ask for, such as trial assembly, and add anything it does.
  3. For each step, name the governing document and say where the acceptance criteria are written. The cell names the place; the limits stay in the specification and the approved procedure.
  4. Fill in the Extent column from the specification. Where it gives a percentage or a sampling rule, quote the clause number rather than the figure.
  5. Agree the intervention for fabricator, customer and third party: H, W, R, M or a dash. If the contract has its own legend, use that.
  6. Issue the plan for approval before any steel is cut. A hold point needs a written release before work goes past it.
  7. Enter each record number and update the status as fabrication goes on. A row with an NCR raised turns red.
  8. Before shipment, filter Status for rows that are not Done or Released, and close each one.

Comparing the plan with the steelwork specification

A steelwork specification scatters its inspection requirements across welding, NDE, tolerances and coating sections. In OdysseyGPT's Inspection & Testing module, ITP Validator (beta) reads the specification and your ITP together and lists the required inspections the plan does not yet cover. NDE Coverage Review (beta) does the same job for the NDE called for on the drawings. Findings carry a page citation, and the fabricator's own engineer decides what changes. Tools marked beta are open on request, and we onboard each team ourselves.

Want us to run the check for you?

Send your ITP and the customer's quality requirements. We send back what is covered, what is missing and what still needs evidence before the FAT.

Get the free ITP and FAT readiness check

New templates by email (optional)

Your download does not depend on this.

We use your email only for this. See our privacy policy.

Frequently asked questions

What is an ITP in steel fabrication?

It is the fabricator's table of inspections for a job, in fabrication order. Each line says what is inspected, to which document, how much, what record results and whether the customer or a third party attends.

What inspections does structural steel fabrication need?

It varies with the fabrication standard, the level or class the specification sets and the contract. The template offers fifteen common steps to start from. Remove the ones your contract does not require and add any it does.

How much weld NDE should the plan show?

Whatever the specification and the fabrication standard it names require for the job's level or class. Put the clause reference in the Extent column. The template deliberately gives no percentage.

Is trial assembly required?

Only where the specification asks for it, typically for complex or site-critical connections. The step is in the template as a reminder. Delete it when it does not apply.

How is this different from the pressure vessel ITP template?

The steps and columns differ. Steelwork has cutting and piece-marking, trial assembly and galvanising, and an Extent column for sampling. The vessel plan has forming, heat treatment, a pressure test and a data report.