Aerospace and defence component suppliers: check every quality clause and flow-down before you accept the order

For quality engineers, contract reviewers and programme managers at machine shops, fabricators and special-process houses that build to a customer's drawing, purchase order quality clauses and supplier quality manual.

By Ademola Afolabi, Founder, New Odyssey Ltd ยท Last reviewed:

The short answer

Aerospace and defence component suppliers review each purchase order against the drawing revision, the customer's supplier quality requirements and the quality clauses the order calls up, then pass the relevant ones to sub-tier suppliers. OdysseyGPT reads those documents and your own, lists each obligation and reports gaps with a quote for every finding. Your engineers decide.

Key Takeaways

  • The order is more than the purchase order: quality clause codes, a supplier quality manual, drawing notes and referenced specifications all carry obligations.
  • Flow-down is where orders go wrong. A clause you accepted and did not pass to a processor is still your obligation.
  • The customer expects a data package: first article inspection report, certificate of conformance, material and special process certificates, and test reports.
  • OdysseyGPT reads text documents. It does not read drawings or models, measure parts or produce first article forms, and engineers decide every finding.

Free sample: a quotation-vs-PO check. Send your quotation and the customer's purchase order. Get a list of what changed between them. Get the free result

How do aerospace and defence suppliers review an order?

A build-to-print supplier does not write a technical offer against a tender specification. It receives a purchase order for a part number at a drawing revision, and the purchase order points to everything else. The work at contract review is to find every document the order calls up, confirm the revision of each, and decide whether the shop can meet it.

Where the obligations in an aerospace purchase order sit (own summary)
DocumentWhat it usually carriesWhat goes wrong
Purchase order lines and notesPart number, drawing revision, quantity, delivery dates and a list of quality clause codesThe order names a newer drawing revision than the one quoted
Quality clausesShort coded requirements held on the customer's supplier portal, such as first article inspection, source inspection, certificate content or record retentionA code is accepted without anyone opening its text, or the clause has been revised since the last order
Supplier quality requirements manualGeneral rules for every order: quality system certification, control of sub-tier suppliers, non-conformance reporting, change notificationThe manual is treated as boilerplate and read once, years ago
Drawing notes and parts listMaterial and process specifications, marking, and any approved-source restrictionsA note calls up a process specification the shop's usual processor is not approved for
Material and process specificationsThe detailed requirement for the stock, heat treatment, plating, coating, welding or non-destructive testingThe revision in force at order date differs from the one the route card was written to
Terms and conditionsGovernment flow-down clauses, export control statements and audit rightsA material sourcing clause is noticed only when the certificate is being written

Most shops record this on a contract review form. A careful review ends with three lists: requirements the shop meets as it stands, requirements that must be passed to a sub-tier supplier, and points it cannot meet and must raise with the buyer before accepting the order.

  1. Collect the purchase order, each quality clause by code and revision, the supplier quality manual and the terms and conditions.
  2. Confirm the drawing, parts list and specification revisions against the order, and note any change since the quotation.
  3. List each obligation once, with the document and paragraph it comes from.
  4. Mark who must act on it: your own planning, inspection, purchasing, or a named sub-tier supplier.
  5. Write the sub-tier purchase orders so that each clause the customer says must be flowed down appears in them.
  6. Send exceptions to the buyer in writing and hold acceptance until they are answered.

Flow-down is your obligation, not the processor's

Customers commonly require a supplier to pass applicable requirements down to its own suppliers, including the customer's rights of access and any restriction to approved sources. If your order to a heat treater or plater leaves a clause out, the gap is found at the customer's audit or at receiving inspection, and it is found against you.

Which standards and rules come up?

The same handful of standards and regulations appear in most aerospace and defence purchase orders. The table names them and says what each is for. It is our own summary at title level. Read the revision your contract names, and take regulatory questions to a qualified adviser.

Standards and rules named in aerospace and defence purchase orders (own summary, name level)
NameWhat it isWhere an order usually pins it down
AS9100The quality management system standard for aviation, space and defence organisations. It builds on ISO 9001Whether third-party certification is required, for which site, and whether sub-tier suppliers need it too
AS9102The first article inspection requirement: what is verified on a representative part from the first production run and how it is recordedWhich parts need a first article inspection, who approves the report and when it must be repeated
NadcapAn industry-managed accreditation programme for special processes such as heat treating, non-destructive testing, welding and chemical processingWhich processes must be done by an accredited processor, and whether the customer's own approval is needed as well
DFARS specialty metalsA US defence acquisition clause that restricts where certain steels, nickel and cobalt alloys, titanium and zirconium may be melted or producedWhether the clause is in the order, and what the material certificate or certificate of conformance must state
AS5553 and AS6174SAE standards on counterfeit parts. AS5553 covers electrical, electronic and electromechanical parts. AS6174 covers materiel in generalPurchasing from the original maker or an authorised source, and the traceability records to keep
ITAR and EARUS export control regulations. ITAR covers defence articles and related technical data. EAR covers commercial and dual-use itemsA statement on the drawing or order that the data is export controlled, and who may receive it

This page does not explain how to comply with export control law or with any DFARS clause. It names them so a contract reviewer knows to look for them. For a quality system specification from another sector, compare API Q1.

What goes in the contract review exceptions list?

A build-to-print supplier cannot deviate from the drawing on its own authority. What it can do is tell the buyer, before acceptance, which requirements of the order it cannot meet or needs clarified. Some companies call this an exceptions list. In other sectors the same record is a technical deviation list. After acceptance, a departure goes through the customer's own request process for a deviation or concession.

Points that most often reach an aerospace supplier's exceptions list (own summary)
AreaWhat to check before you accept the order
RevisionsDrawing, parts list and specification revisions on the order against those quoted, and whether stock or work in progress is to the older revision
Quality clauses added since the quotationClause codes on the order that were not on the request for quotation, especially source inspection, first article and data submission clauses
Approved sourcesWhether each special process must go to a processor on the customer's approved list, and whether your usual processor is on it for that specification
First article inspectionWhether a full or partial inspection is needed, whether an earlier report can be used, and whether the customer must approve the report before shipment
Material sourcingCountry of melt restrictions, the certificate statements asked for, and whether stock on the shelf can meet them
Certificate contentThe statements the certificate of conformance must carry, who signs it and whether the customer's format is mandatory
Records and accessThe retention period, and rights of entry for the customer, its customer and regulators at your site and at sub-tier suppliers
Change and non-conformanceWhich changes need notice or approval first, and how fast a non-conformance found after delivery must be reported

Keep the list short and exact. Each line needs the document, the paragraph, what you can do instead and what you want the buyer to confirm. A general statement that the order is accepted subject to your quotation does not protect you against a clause you did not name.

Which documents are delivered with the parts?

The paperwork that ships with the parts, or is uploaded to the customer's portal before they ship, is often called a data package. For a finished deliverable it may be called an end item data package. The order and its quality clauses set the contents. These are the usual ones.

Documents an aerospace or defence component supplier delivers (own summary)
DocumentWhat the customer looks for
First article inspection reportThe part number and revision ordered, every design characteristic accounted for with a result, and the materials, special processes and functional tests listed with their evidence
Certificate of conformancePurchase order and line, part number, revision, quantity, serial or lot numbers, the statements the quality clauses require, and an authorised signature
Material certificatesThe specification and revision, the heat or lot number, results that meet the specification, and an unbroken link from the mill to the part. See heat number traceability
Special process certificatesThe processor's name and site, the process specification and revision, the parts and quantity covered, the date, and a statement of conformance
Test and inspection reportsFunctional, pressure or electrical test results, non-destructive testing reports and dimensional records where the order asks for them
Sub-tier certificates of conformanceA certificate from each sub-tier supplier whose work is in the part, tied to your purchase order to them
Deviation or concession approvalsThe customer's signed approval for any accepted departure, referenced on the certificate of conformance
Index or packing listA list of what is in the package, so receiving inspection can see at a glance that nothing is missing

A checklist for the first document is on the first article inspection report checklist template page. For the certificate, see the certificate of conformance template. The guide on how to review a material test report covers the material certificates.

How does OdysseyGPT help?

OdysseyGPT is document review software. You upload the customer's documents and your own, and it reports where they differ, quoting the passage on each side. Document Review takes the customer's quality clauses or supplier quality manual as the base and checks your contract review record, quality plan or sub-tier purchase order against it, forward and in reverse. The other tools each read a narrower set of documents.

Aerospace supplier documents and the tool that reads each
Your documentToolWhat it reports
Supplier quality requirements manual, quality clause texts and termsCustomer Specification Review (beta)A requirements register: one line per obligation, with the paragraph it comes from and its type
Customer's quality clauses and your purchase order to a sub-tier supplierDocument ReviewEach customer requirement with a status and a quote from your order, so a clause that was not flowed down shows as not addressed
Your quotation and the purchase order receivedQuotation-to-PO Review (beta)New obligations, changed revisions and exceptions the order does not carry, each with a quote
Exceptions raised and the buyer's repliesDeviation Register (beta)One running record of each exception, its status and the buyer's decision
Material certificates and the purchase requirementsMaterial Certificate Review (beta)Grade, heat number, chemistry and mechanical results checked against the requirement, with the value quoted from the certificate
Parts list, heat or lot records and material certificatesMaterial Traceability Check (beta)Heat numbers with no certificate, certificates that cover no part and conflicting grades
Test or inspection reports and calibration certificatesCalibration Validity Check (beta)Each instrument named in a report matched to a certificate that was valid on the date of use
The customer's data package requirements and your document folderMRB Readiness Check (beta)Each required document shown as present, missing, awaiting approval or at the wrong revision
Approved records and the customer's package indexMRB Compiler (beta)The records mapped to the index, with entries that have no document listed

The record book tools were written around a manufacturing record book. An end item data package is the same kind of thing: an index set by the customer and a folder of evidence to check against it. The tools are grouped by stage under order, manufacturing and handover.

What does a result look like?

This table is an invented example. The customer, the bracket, the clause codes, the certificate numbers and the company names are made up to show how findings are laid out. Nothing in it comes from a real order, a real supplier or a standard. The rows are of the kind produced by Quotation-to-PO Review, Document Review, Material Certificate Review and MRB Readiness Check.

Invented example: a purchase order for a machined and anodised titanium bracket, and the supplier's data package, checked against the customer's quality clauses
IDFindingWhy it was raisedCategorySeverityConfidence
F-01Quality clause Q-14 is not in the purchase order to the anodiserQ-14 states "Supplier shall flow this clause to all sub-tier sources performing special processes." Sub-tier order SP-3391 lists clauses Q-02 and Q-07 only.Flow-downCriticalHigh
F-02Material certificate does not state the country of meltClause Q-21 states "Certificates for titanium shall state the country in which the material was melted." Certificate MC-88014, heat T4471, gives the mill's address and no melt statement.Missing statementHighHigh
F-03Anodising certificate is from a processor not on the approved list suppliedClause Q-09 limits special processes to sources on approved processor list APL rev 12. Certificate AN-2207 names Northgate Finishing. That name does not appear on the list uploaded.Approved sourceCriticalMedium
F-04Purchase order calls up drawing revision D; the quotation was to revision CPurchase order line 1 states "BRK-5520 Rev D". Quotation Q-1182 states "BRK-5520 Rev C".Revision changeHighHigh
F-05First article inspection report is listed as required and is not in the folderClause Q-05 requires a first article inspection report with the first shipment. No document in the folder matches that index entry.CompletenessCriticalHigh
F-06Certificate of conformance omits the concession numberClause Q-03 states "Approved concessions shall be referenced on the certificate." Concession CN-0412 is in the folder. Certificate CC-7730 does not mention it.Certificate contentMediumMedium
F-07New obligation: record retention of 15 yearsPurchase order terms, section 9, state 15 years. The quotation referred to the supplier's standard period of 10 years.New obligationMediumHigh

A quality engineer opens the quotes behind each row and confirms it, changes it or dismisses it. F-03 is a good example of why. The software can say that a name is not on the list it was given. Only a person can say whether the list was current, or whether the processor trades under another name.

Where OdysseyGPT falls short

  • Export-controlled technical data needs your customer's and your own decision about where it may be processed and who may see it. OdysseyGPT is hosted in the United States. This page makes no claim of ITAR compliance, and you should not upload controlled data until that decision has been made.
  • It makes no claim of CMMC or AS9100 certification or compliance, and it is not a quality management system. It does not hold your procedures, training records, audits or corrective actions.
  • It does not read engineering drawings or 3D models. A requirement that exists only as a drawing note, a dimension or a model annotation is not checked unless you supply it as text.
  • It is not first article inspection software. It does not balloon a drawing, measure a part, fill in first article forms or connect to a measuring machine.
  • It does not confirm that a processor holds an accreditation or a customer approval. It can show what a certificate states and what a list you upload contains. Checking the live status is your job.
  • It gives no legal or regulatory opinion. Whether material meets a DFARS clause, or whether an item is export controlled, is a question for your compliance function.
  • It can miss a requirement or pair it with the wrong passage, most often where clause codes are listed without their text. The quotes are there so a person can catch this.
  • Tools carrying a beta marker on this page are available on request, and we set each team up ourselves.

Try it on your own documents

Free sample: a quotation-vs-PO check

Send your quotation and the customer's purchase order. Get a list of what changed between them.

Get the free result

Buyer questions

20 questions bid engineers, proposal engineers and buyers ask. Last reviewed:

What are aerospace supplier quality requirements?

They are the rules a customer sets for every supplier, usually in a supplier quality requirements manual with coded quality clauses added per order. They cover quality system certification, first article inspection, special process sources, certificates, non-conformance reporting, change notification, record retention and access rights. They apply on top of the drawing, and most must be passed to sub-tier suppliers.

What is a purchase order quality clause?

A quality clause is a short requirement identified by a code on the purchase order, with its full text held in a separate document or on the customer's supplier portal. One order may list a dozen codes. Each has its own revision, so open the current text every time. Do not rely on what the code meant on the last order.

What does flow-down mean in a purchase order?

Flow-down means passing the customer's requirements into your own purchase orders to sub-tier suppliers, so that a heat treater, plater or machining subcontractor is bound by the same clause you accepted. Customers usually state which clauses must be flowed down. If you leave one out, the obligation stays with you and the gap is yours to explain at audit.

Which purchase order quality clauses must be flowed down?

The customer's documents say. Clauses that commonly carry a flow-down instruction cover special process sources, material sourcing rules, counterfeit part prevention, record retention, rights of access and notification of change. Read each clause for words such as sub-tier or lower-tier. Then check your own order to the processor lists it by code and revision, not by a general reference to customer requirements.

What does contract review cover at an aerospace supplier?

It covers the purchase order, the drawing and specification revisions it names, each quality clause, the supplier quality manual and the terms. The reviewer confirms the shop can meet every requirement, identifies what must go to sub-tier suppliers, and lists exceptions for the buyer before the order is accepted. Most quality systems require a record of that review.

What if the purchase order names a newer drawing revision than we quoted?

Stop and compare the two revisions before accepting. A revision change can alter a dimension, a material, a process specification or a note, and each may affect price, lead time and first article status. Tell the buyer in writing what changed and what it costs. The guide to purchase order vs quotation review sets out the comparison.

What goes in a contract review exceptions list?

Each requirement of the order you cannot meet or need clarified, with the document, the paragraph, what you propose and the answer you need. Typical entries are a revision mismatch, a processor not on the customer's approved list, a certificate statement you cannot give for stock material, and a retention period longer than your own. Send it before you acknowledge the order.

What is AS9100 and do we need it?

AS9100 is the quality management system standard for aviation, space and defence organisations. It contains ISO 9001 and adds sector requirements. Whether you need certification depends on your customers. Many require it of any supplier that makes parts, and some accept ISO 9001 for limited work. The supplier quality manual states the rule. See the glossary entry on AS9100.

What is a first article inspection?

It is a full, documented check of one representative part from the first production run against every design requirement, including drawing notes, material, special processes and functional tests. It shows the production process can make a conforming part. In aerospace it follows AS9102 and is recorded on three forms. See the page on AS9102 first article inspection.

When must a first article inspection be repeated?

When something that could affect the part changes: the design, the manufacturing process, the tooling, the source or the location. A long gap in production also calls for one. Public customer documents cite two years, and some customers set less. Often only the affected characteristics are inspected again, as a partial first article. The customer's quality clause decides.

What is Nadcap and when is it required?

Nadcap is an industry-managed accreditation programme for special processes such as heat treating, non-destructive testing, welding and chemical processing, administered by the Performance Review Institute. It is required when the customer's quality clause says a process must be done by an accredited source. Many customers also require the processor to be on their own approved list. See Nadcap.

What should a special process certificate state?

At least the processor's name and site, your purchase order, the part number and quantity, the process specification with its revision, the date and a signed statement that the work conforms. Customers may add more, such as a lot or batch reference. Check the processor named is the one you ordered from and one the customer accepts for that specification.

What is an end item data package?

It is the set of records delivered with a finished item: typically a certificate of conformance, a first article inspection report where due, material and special process certificates, test reports and any concession approvals. The contract sets the contents, the order and the format. The glossary entry on the end item data package lists what assemblies add.

What must an aerospace certificate of conformance state?

The customer's quality clause sets the content. It usually asks for the purchase order and line, part number and revision, quantity, serial or lot numbers, a statement that the parts meet the order, any concession reference and an authorised signature. Some customers require extra statements on material source. See certificate of conformance for the general form.

What does the DFARS specialty metals clause mean for a machine shop?

If clause 252.225-7009 is in your purchase order, specialty metals in the parts must have been melted or produced in the United States, its outlying areas or a qualifying country, unless an exception applies. In practice you need mill certificates that state the country of melt. This is not legal advice. See DFARS specialty metals.

What do counterfeit parts prevention clauses ask for?

They ask a supplier to buy from the original manufacturer or an authorised source where it can, keep traceability records back to that source, and report suspect items. Customers often cite SAE AS5553 for electrical, electronic and electromechanical parts and AS6174 for other materiel. The purchase order clause sets the actual obligation. Read it, and pass it down to distributors.

Can we upload export-controlled technical data to OdysseyGPT?

That decision belongs to you and your customer. Export-controlled technical data may only be processed where the rules and your customer's instructions allow. OdysseyGPT is hosted in the United States and makes no claim of ITAR compliance. It also does not read engineering drawings. Decide what may be uploaded before you start, and leave controlled data out if in doubt.

Can OdysseyGPT check that quality clauses were flowed down?

It can compare the documents. Document Review takes the customer's quality clauses as the base and your purchase order to a sub-tier supplier as the document to check. A clause with no matching statement in your order is reported as not addressed, with the customer's text quoted. It cannot tell whether the processor read the order. An engineer confirms each finding.

Does OdysseyGPT create first article inspection reports or balloon drawings?

No. It does not read drawings or 3D models, measure parts, balloon a drawing or fill in first article forms. It reads text documents around the report. For example, Material Certificate Review (beta) checks material certificates against the purchase requirements and quotes the certificate for each finding. Dedicated first article software does the rest.

Can OdysseyGPT check a data package before shipment?

It can check what is in the folder against what the customer asks for. MRB Readiness Check (beta) reads the customer's package requirements or index and your documents, and marks each required record as present, missing, awaiting approval or at the wrong revision. It does not judge whether a part conforms. Your quality engineer releases the package.

Frequently asked questions

Who carries out contract review at an aerospace component supplier?

Usually a contracts or customer service person with quality, planning and purchasing. Quality reads the clauses and the supplier quality manual, planning checks the drawing and specification revisions, and purchasing takes the requirements that must go to sub-tier suppliers.

Does OdysseyGPT produce a first article inspection report?

No. It does not read drawings, measure parts or fill in first article forms. It reads text documents, such as quality clauses, certificates and reports, and checks them against the customer's written requirements with a quote for each finding.

Can we upload ITAR-controlled technical data to OdysseyGPT?

That is a decision for you and your customer, not for us. OdysseyGPT is hosted in the United States and makes no claim of ITAR compliance. Decide where controlled data may be processed before you upload any.

What is a purchase order quality clause?

A short, coded requirement a customer attaches to an order, with the full text held in a separate document or portal. Typical subjects are first article inspection, source inspection, certificate content, special process sources and record retention.

References

AS9100D: Quality Management Systems. Requirements for Aviation, Space, and Defense Organizations

SAE International

Paid standard. Publisher's page used for the title and scope. Use the revision your contract names.

Visit source

AS9102C: Aerospace Series. First Article Inspection Requirements

SAE International

Paid standard. Publisher's listing used for the title and revision. No form content is reproduced.

Visit source

Nadcap

Performance Review Institute

What Nadcap is, who governs it and the critical processes it accredits.

Visit source

DFARS 252.225-7009 Restriction on Acquisition of Certain Articles Containing Specialty Metals

acquisition.gov

The clause text: definition of specialty metal, the restriction, the exceptions and the subcontract paragraph.

Visit source

DFARS 252.246-7007 Contractor Counterfeit Electronic Part Detection and Avoidance System

acquisition.gov

The DFARS clause on counterfeit electronic parts. Named for context only.

Visit source

AS5553D: Counterfeit Electrical, Electronic, and Electromechanical (EEE) Parts; Avoidance, Detection, Mitigation, and Disposition

SAE International

Paid standard. Title only.

Visit source

AS6174: Counterfeit Materiel; Assuring Acquisition of Authentic and Conforming Materiel

SAE International

Paid standard. Title only.

Visit source

International Traffic in Arms Regulations, 22 CFR Parts 120 to 130

US Government (eCFR)

Named for context only. This page gives no export control advice.

Visit source

Export Administration Regulations, 15 CFR Parts 730 to 774

US Government (eCFR)

Named for context only.

Visit source

Related Pages

Module

Order & Document Control

The module hub: its tools, what they read and the free result.

Standards

AS9102 first article inspection

What a first article inspection is, the three forms at concept level and a pre-submission checklist.

Standards

DFARS specialty metals

What clause 252.225-7009 restricts and what to check when it is flowed down to you.

Glossary

AS9100

The aviation, space and defence quality system standard, and what customers ask suppliers to show.

Glossary

Nadcap

Special process accreditation and how it appears in a purchase order.

Glossary

End item data package

The set of records delivered with a finished aerospace or defence item.

Glossary

First article inspection report

What the report records and what it does not prove.

Glossary

Certificate of conformance

The supplier's signed statement that the delivery meets the order.

Template

First article inspection report checklist template

Points to check on a first article report before it goes to the customer.

Product

Document Review

Check the customer's quality clauses against your own documents, in both directions.

Product

Quotation-to-PO Review (beta)

Compare the purchase order received with what you quoted.

Product

Material Certificate Review (beta)

Check material certificates against the purchase requirements.

Guide

Purchase order vs quotation review

How to compare an order with your offer before you acknowledge it.

Pillar guide

Technical deviation list guide

The deviations you agree at bid stage are the ones you verify and record later.