How to review a material test report (MTR) against the purchase order

A field-by-field check of a mill test report or material certificate for quality engineers and buyers at equipment makers, from grade and heat number to EN 10204 type and traceability.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

To review a material test report (MTR), check it against the purchase requirement, not just the material standard. Confirm grade and edition, heat number, chemistry, mechanical and impact results, heat treatment, supplementary tests and the EN 10204 certificate type. Then tie the heat number to the bill of materials and the part it went into.

Key Takeaways

  • An MTR can meet the ASTM or EN grade and still fail your order, because the PO or specification adds requirements.
  • Read the certificate against three things: the material standard, the purchase requirement and the bill of materials.
  • The heat number is the key: it must match the part, the heat list and the certificate.
  • Check the certificate type and who signed it. A 3.1 is not a 3.2.

What an MTR is

A material test report, or mill test report (MTR), is the document a mill or foundry issues with a heat or lot of material. It states the grade, the heat number, the chemical analysis and the test results. In Europe it is often called a mill test certificate (MTC) or inspection certificate. EN 10204 sets the certificate types, such as 2.2, 3.1 and 3.2, which say who checked the results and how independent they are.

What to check, field by field

MTR review checklist (own summary)
FieldWhat to check
Issuer and certificate typeMill or foundry named; EN 10204 type as the PO asks; signed by the right party. A 3.2 also needs the purchaser's or third-party inspector's sign-off.
Material standard and gradeStandard, grade and, where the PO gives one, edition. Dual-certified grades should list both.
Product form and sizePlate, bar, forging, casting or pipe, and the size range, match the part.
Heat number (and lot)Matches the marking on the material and your heat list.
Chemical analysisEvery element the standard and the PO limit is reported and within range, including any extra limits in your specification.
Mechanical testsTensile, yield, elongation and reduction of area meet the grade and any PO minimums.
Impact testsCharpy tests at the temperature the order asks for, with the right specimen size and acceptance values.
HardnessReported where required, for example for sour service under NACE MR0175 / ISO 15156.
Heat treatmentCondition and treatment, such as normalised or quenched and tempered, as the grade and PO require.
Supplementary testsAny extra test the PO calls for, such as ultrasonic testing, intergranular corrosion or positive material identification.

Check against the order, not just the standard

Most MTR tools and distributor guides check a certificate against the grade. That is necessary but not enough for engineered equipment. The customer's specification often tightens the grade: lower carbon equivalent, impact tests at a colder temperature, a hardness cap, a 3.2 certificate or extra tests. Read the requisition, the specification and your agreed deviation list before you accept a certificate.

Common MTR problems

  • Certificate type lower than the PO asks for, such as 3.1 when 3.2 was ordered.
  • Impact tests at the wrong temperature, or missing.
  • Heat number that does not match the part marking or heat list.
  • Grade correct but standard edition older than the specification requires.
  • A distributor's certificate of conformity with no copy of the mill's certificate behind it.
  • Values reported but one element outside a tighter project limit.

What to do when a certificate fails

Quarantine the material and raise a nonconformance. Ask the supplier for a corrected or supplementary certificate if the issue is paperwork. If the material itself fails, the options are retest where the standard allows it, use under an approved concession from the customer, or reject. Never edit or annotate a mill certificate yourself.

Where the MTR ends up

Accepted certificates go into the materials section of the manufacturing record book, usually with a material traceability list. They are also a common item on supplier submissions that the customer reviews during the order.

Doing it with OdysseyGPT

The Material Certificate Review (beta) reads each certificate and checks it against the purchase requirements, the material specification and the bill of materials. It checks grade, heat number, chemistry, mechanical tests, heat treatment, supplementary tests and EN 10204 type, and cites every conflict. The Material Traceability Check (beta) follows the chain from tag to certificate. A quality engineer accepts or rejects each certificate. For tools aimed at mills and stockists, see MTR review software.

These tools are in beta

The Material Certificate Review and Material Traceability Check are in beta. You can request access, and we onboard each team ourselves. Every finding cites the page, sheet or cell it came from, and your engineers decide what to do with it.

Buyer questions

7 questions bid engineers, proposal engineers and buyers ask. Last reviewed:

How do I read a mill test report (MTR)?

Start at the top: who issued it, the certificate type and the material standard and grade. Find the heat number and check it matches the material. Then read the chemical analysis and the mechanical results against the grade limits, and check impact tests, hardness and heat treatment where required. Finally, check the signature and date.

What should I check on a material certificate?

Check the grade, standard and edition, product form and size, heat number, chemistry, tensile and yield results, impact tests, hardness, heat treatment and any supplementary tests. Check the EN 10204 type and signatures. Then compare every value with the purchase order and specification, which often set tighter limits than the material standard.

Is an MTR the same as an MTC or an inspection certificate?

Mostly, yes. Mill test report (MTR) is the common US term. Mill test certificate (MTC) and material test certificate are common in Europe and Asia. EN 10204 calls the documents with test results inspection certificates, types 3.1 and 3.2. A type 2.2 test report gives results from non-specific inspection, so check which type the order needs.

What is the difference between EN 10204 3.1 and 3.2 on an MTR?

Both report specific test results for the material supplied. A 3.1 is confirmed by the manufacturer's own inspection representative, independent of production. A 3.2 is confirmed by both the manufacturer's representative and the purchaser's representative or a named third-party inspector. Orders for critical service often ask for 3.2. See EN 10204 3.1 vs 3.2.

Can an MTR meet the material grade but still fail the order?

Yes. The customer's specification often adds limits beyond the grade, such as impact tests at a colder temperature, a hardness cap, a lower carbon equivalent, extra tests or a 3.2 certificate. A certificate that meets ASTM or EN still fails if it misses one of those. That is why you check against the purchase requirement, not only the standard.

Is a distributor's certificate enough?

Often not. Many specifications ask for the original mill certificate, or a copy that traces to it, not only a distributor's certificate of conformity. If material was cut or processed by a stockist, check the heat number was carried across and the stockist's paperwork links back to the mill's certificate.

What software reviews MTRs automatically?

Several tools read MTRs and check values against a material standard, mainly for mills, stockists and fabricators. OdysseyGPT's Material Certificate Review (beta) checks each certificate against the purchase order, specification and bill of materials of an engineered-equipment order, with citations. See MTR review software for a sourced comparison.

Frequently asked questions

Is an MTR the same as a certificate of conformity?

No. An MTR reports the actual test results for a heat. A certificate of conformity states that a product meets an order, often without results. Many specifications ask for the MTR, so check which one the PO needs.

Can I accept a 3.1 certificate when the PO asks for 3.2?

Only with the customer's written agreement. A 3.2 needs independent confirmation of the results by the purchaser's or a third-party inspector, so a 3.1 does not meet the requirement on its own.