What is a first article inspection?
A first article inspection, or FAI, is a planned and documented check of one representative item from the first production run of a part. Every requirement on the drawing and in the documents it calls up is verified and recorded: dimensions, notes, material, special processes and functional tests. The aim is to show that the methods, tooling and sub-tier sources used for production give a part that meets the design. The record is the first article inspection report, often shortened to FAIR.
AS9102 is the SAE aerospace standard for this. It belongs to the same family as AS9100, and the same document is published in Europe as EN 9102. Revision C is dated June 2023. It followed Revision B of 2014. A purchase order or quality clause normally names the standard and may name a revision. Use the one your contract names.
An FAI is not a prototype check, and it is not the routine inspection that every delivered part receives. It is done on a part made by the production process, and its result stands for later parts made the same way, until something changes.
What are the three AS9102 forms?
The standard gives three forms. Customers accept the supplier's own layout or the output of inspection software if it holds the same information. The table describes each form in our own words. It does not reproduce the fields. Buy the standard for those.
| Form | Name | What it accounts for | Evidence it points to |
|---|---|---|---|
| Form 1 | Part number accountability | Which part was inspected: part number and revision, the drawing it was checked to, the manufacturing source, and the parts that make up an assembly | Reports for the detail parts and sub-assemblies in an assembly, and the signatures that close the report |
| Form 2 | Product accountability | The raw materials, special processes and functional tests the design calls for, with the specification and the source for each | Material certificates, special process certificates and functional test reports |
| Form 3 | Characteristic accountability | Every design characteristic, one line each, with the requirement, the measured or observed result and any non-conformance | The numbered drawing, measurement records and the identity of gauges or tooling where recorded |
Public summaries of Revision C say it made the reason for a full or partial inspection a mandatory entry, changed how sign-off works across the forms, and put more weight on planning the inspection before parts are made. Those are vendors' descriptions and not the standard's text. Check the revision itself before you change a procedure.
What is a ballooned drawing?
A ballooned drawing, also called a bubbled drawing, is a copy of the engineering drawing on which every design characteristic has been given a number in a small circle. Dimensions with their tolerances, geometric tolerances, surface finish callouts, general notes and parts list entries each get a number. Those numbers become the lines of the characteristic accountability form, so a reader can go from any line of the report to the exact place on the drawing.
- Each characteristic has one number, and each number appears once.
- Notes count. A note that calls up a material or process specification is a characteristic to account for.
- A dimension that applies in several places needs a way to show each place was checked.
- The ballooned copy carries the same drawing revision as the report.
The word ballooned is shop practice. What the standard asks for is that each characteristic can be identified and traced to its result. Where the design is a 3D model with no full drawing, the same accounting is done against the model's annotations.
When is a full or partial FAI repeated?
A full FAI covers every characteristic. A partial FAI covers only the characteristics affected by a change, and it refers back to the earlier report for the rest. The standard sets out the events that call for one or the other. Customers' public supplier documents describe them in broadly the same way.
| Event | What to consider |
|---|---|
| A new part number | The first production run of a part you have not made before needs a full inspection |
| A design change | A drawing or specification revision that affects fit, form or function. Usually a partial inspection of the changed characteristics |
| A change of manufacturing process or method | A different machine type, sequence, programme or inspection method that could affect the result |
| A change of source or location | A new sub-tier supplier or special processor, or a move of the work to another site |
| A change of tooling or material | New or reworked tooling, or a different material source, where it could affect conformance |
| A lapse in production | Public customer documents cite a gap of two years. Some customers set a shorter period in their own clauses |
| Correcting an earlier report | Characteristics that were non-conforming or not complete on the first report are inspected again once corrected |
The customer's clause decides
A customer may ask for a full inspection where the standard would allow a partial one, set a shorter lapse period, require its own representative to attend, or require approval of the report before parts ship. Read the quality clause on the order and record on the report why the inspection is full or partial.
What to check on an FAI report before it goes to the customer
Most rejected reports fail on paperwork, not on the part. This checklist is our own summary of the points a customer's receiving inspector tends to look at. It is not a substitute for the standard or for the customer's clause.
| Check | What to look for |
|---|---|
| Part identity | The part number, revision and name on the report match the purchase order and the drawing used |
| Drawing and specification revisions | The revisions inspected to are the ones the order names, and the ballooned drawing is at the same revision |
| Full or partial | The report says which it is and why. A partial report names the earlier report it relies on |
| Every characteristic accounted for | Each balloon number has a line, and each line has a result. No gaps in the number sequence without an explanation |
| Results, not ticks | Measured values are recorded for dimensions with tolerances, in the same units as the drawing |
| Drawing notes | Each note is accounted for, and a note that calls up a specification points to the certificate that shows it was met |
| Materials | Each material on the product accountability form has a certificate, and the heat or lot number links the certificate to the part |
| Special processes | Each process has a certificate naming the processor, the specification and revision, and the processor is one the customer accepts |
| Functional tests | Each test the design calls for has a report with a result and the procedure used |
| Assemblies | Each detail part and sub-assembly that needs its own first article has one, and the top report refers to it |
| Non-conformances | Any characteristic out of tolerance is marked, with the non-conformance record and the customer's disposition attached |
| Measuring equipment | Gauges and special tooling are identified where the customer asks for it, and were in calibration when used |
| Sign-off | The report is signed and dated by the people the standard and your procedure require, and they are not the same person where independence is asked for |
| Customer extras | Anything the quality clause adds: the customer's format or portal, approval before shipment, or attendance by its representative |
A version of this list you can adapt is on the first article inspection report checklist template page. OdysseyGPT can help with the document side of it. Document Review checks the customer's first article clause against your own procedure and quotes both. Material Certificate Review (beta) checks the material certificates behind the product accountability form against the purchase requirements. Calibration Validity Check (beta) matches instruments named in a report to certificates valid on the date of use.
What OdysseyGPT does not do here
It does not read engineering drawings or 3D models, balloon a drawing, measure a part or fill in first article forms. It is not FAI software and does not judge whether a characteristic conforms. It reads text documents and reports differences with a quote on each side. An engineer decides.