The short answer

DFARS clause 252.225-7009 restricts the source of specialty metals in items delivered under US defence contracts. Certain steels, nickel and cobalt alloys, titanium and zirconium must be melted or produced in the United States, its outlying areas or a qualifying country, unless an exception applies. Primes pass the clause down, so suppliers are asked to certify the melt source.

Key Takeaways

  • The clause is about where the metal was melted or produced, not where the part was machined.
  • It covers defined groups of steel, nickel, iron-nickel and cobalt alloys, and all titanium and zirconium and their alloys.
  • It has exceptions, and it reaches suppliers through the subcontract paragraph of the clause.
  • The clause sets the restriction. The statement your certificate must carry comes from the customer's purchase order.

Free sample: a certificate check report. Send up to 20 material certificates and the PO. Get a certificate check report. Get the free result

What does the DFARS specialty metals clause require?

This page is not legal advice

It is our own overview of a public regulation, written so a contract reviewer can recognise the clause and ask the right questions. The regulation changes. Read the current text on acquisition.gov and the wording of your own contract, and take compliance decisions to a qualified adviser.

DFARS is the Defense Federal Acquisition Regulation Supplement, the US Department of Defense's additions to the Federal Acquisition Regulation. Its contract clauses are numbered from 252. Clause 252.225-7009 is titled Restriction on Acquisition of Certain Articles Containing Specialty Metals. In the trade, material that meets it is often called DFARS compliant, though that phrase appears nowhere in the regulation.

The core rule is short. Specialty metals incorporated in items delivered under the contract must be melted or produced in the United States, its outlying areas or a qualifying country, unless one of the listed exceptions applies. The restriction follows the metal into the components and sub-assemblies that make up the delivered item. The country where a part was machined, forged or finished does not answer the question. The country of melt does.

The clause defines produce narrowly, for metal powders that are not derived from a melt. It does not define melted. The current clause is dated January 2023 on acquisition.gov. Check the date on the version your contract cites.

What counts as a specialty metal?

The clause defines the term itself. The table summarises the groups in our own words. The steel group is set by alloy content limits written into the clause, so check the certificate's chemistry against the clause text and not against this summary.

Groups of specialty metal in DFARS 252.225-7009 (own summary; confirm on acquisition.gov)
GroupHow the clause draws the lineEveryday examples
SteelSteel above stated limits for manganese, silicon or copper, or with more than a stated small content of any of a list of alloying elements that includes chromium, nickel, molybdenum, cobalt, titanium, tungsten and vanadiumStainless steels, and many alloy and tool steels. Check the heat chemistry against the limits in the clause
Nickel and iron-nickel alloysMore than 10 percent in total of alloying metals other than nickel and ironNickel-based high-temperature alloys
Cobalt alloysMore than 10 percent in total of alloying metals other than cobalt and ironCobalt-chromium wear and high-temperature alloys
TitaniumTitanium and titanium alloys, with no content thresholdCommercially pure grades and alloyed grades alike
ZirconiumZirconium and zirconium alloys, with no content thresholdZirconium alloy bar, sheet and tube

Aluminium alloys are not on the list. That is a common point of confusion, because aluminium parts sit in the same assemblies and their certificates are often asked for in the same clause of the purchase order.

What is a qualifying country?

The clause points to the DFARS definitions for this. A qualifying country is one that has a reciprocal defence procurement memorandum of understanding or international agreement with the United States. The definitions page on acquisition.gov lists them by name. When we checked it, the list had 28 countries, among them Australia, Canada, France, Germany, Italy, Japan, Sweden and the United Kingdom.

The list is amended from time to time. Do not rely on a list printed in a supplier manual, a mill's brochure or this page. Look at the current definitions page, and note the date of the version you checked on your record.

Which exceptions does the clause list?

The clause carries its own exceptions. Each has conditions, and several have exceptions of their own. The list below says only what each is about. Whether one applies to your part is a compliance decision, and in a subcontract the customer may also limit which ones you can use.

  • Electronic components, as the clause defines them.
  • Commercially available off-the-shelf items, with carve-outs. Mill products such as bar, plate and sheet, and forgings and castings, stay restricted unless they are already part of an off-the-shelf item.
  • Commercial fasteners, where the fastener maker gives a certification about its purchases of domestically melted metal.
  • Items manufactured in a qualifying country.
  • Cases where the US Government has determined that compliant metal cannot be obtained as and when needed.
  • Minimal content. Non-compliant specialty metal up to 2 percent of the total weight of specialty metal in the end item, on the contractor's good-faith estimate. This does not cover high performance magnets.

The minimal content exception is counted at the end item. A component supplier rarely knows the weight of specialty metal in the whole end item, which is why the clause lets the prime contractor adjust that paragraph when it flows the clause down.

What is a supplier's certificate asked to state?

The clause tells contractors to include its main paragraphs in subcontracts for items that contain specialty metals, including subcontracts for commercial products. That is how it reaches a machine shop three tiers down. The clause does not prescribe a certificate. The evidence asked for comes from the customer, through a quality clause or a note on the order.

Statements customers commonly ask for on material evidence (typical requests; your purchase order governs)
DocumentWhat is commonly asked for
Mill or material certificateThe country of melt for each heat, stated by the mill, alongside the usual specification, heat number, chemistry and mechanical results
Distributor's certificateA copy of the original mill certificate, and nothing that breaks the link between the heat number and the material shipped
Certificate of conformanceA statement that specialty metals in the delivery meet the clause, sometimes with the exception relied on named
Sub-tier certificatesThe same statement from each sub-tier supplier whose material is in the part
Traceability recordA record that ties each part or lot to the heat number on the certificate. See heat number traceability

A certificate that shows where the mill is located does not always show where the metal was melted. Some mills re-roll or finish material melted elsewhere. If the order asks for country of melt, look for those words or their equivalent.

Other DFARS clauses are separate

A buyer who asks whether you are DFARS compliant may mean something else entirely. The supplement has many clauses, and a purchase order lists the ones that apply by number. Two that suppliers meet often are 252.204-7012, Safeguarding Covered Defense Information and Cyber Incident Reporting, which deals with information security, and 252.246-7007, Contractor Counterfeit Electronic Part Detection and Avoidance System. Neither has anything to do with where metal was melted. Ask which clause numbers the question refers to.

This page covers specialty metals only. It says nothing about how to meet the cybersecurity clause or any certification scheme connected with it.

What to check in a purchase order that flows down DFARS material clauses

Points to check when a purchase order flows down DFARS material clauses (own summary; not legal advice)
PointWhat to check before you accept the order
Which clauses are listedThe clause numbers and dates in the order and its terms, and whether 252.225-7009 is among them
Whether the part contains a specialty metalThe material called up on the drawing against the clause's definition, including fasteners, inserts and other bought-out items in an assembly
Stock on the shelfWhether material you already hold has a certificate that states the country of melt, and what that country is
Your material purchase ordersWhether your orders to mills and distributors carry the clause and ask for the melt statement on the certificate
Distributor evidenceWhether the distributor will supply the original mill certificate and not only its own summary
ExceptionsWhether the customer allows you to rely on any exception in the clause, and how it wants that recorded
Certificate wordingThe exact statement the customer wants on the certificate of conformance, and who must sign it
Sub-tier suppliersWhether processors or machining subcontractors supply any material themselves, and whether the clause is in your order to them
Bought-out itemsHow you will get evidence for hardware and catalogue items, which often arrive without a mill certificate
RecordsHow long the certificates and traceability records must be kept, and whether the customer can ask for them later
Other clausesAny other material sourcing clause in the terms, which may have different rules and different exceptions

OdysseyGPT can help with the reading. Customer Specification Review (beta) lists the obligations in a customer's terms and quality clauses with the paragraph behind each, so a material sourcing clause is not missed. Document Review checks the customer's clauses against your purchase order to a mill or distributor and shows which were not flowed down. Material Certificate Review (beta) reads the certificates against the purchase requirements you supply and quotes the certificate for each finding.

What OdysseyGPT does not do here

It gives no legal opinion and does not decide whether material meets a DFARS clause or whether an exception applies. It does not hold a list of qualifying countries or verify a mill's statement. It reports what your documents say and where a required statement is absent, with a quote. A person decides what that means.

Try it on your own documents

Free sample: a certificate check report

Send up to 20 material certificates and the PO. Get a certificate check report.

Get the free result

Frequently asked questions

What does DFARS compliant mean for metal?

In trade use it usually means the metal meets the specialty metals clause, 252.225-7009: it was melted or produced in the United States, its outlying areas or a qualifying country. The phrase is shorthand and is not defined in the regulation.

Is aluminium a specialty metal under DFARS?

No. The definition in clause 252.225-7009 covers certain steels, nickel, iron-nickel and cobalt alloys, titanium and zirconium. Aluminium is not on the list. Check the current clause text on acquisition.gov.

Does DFARS specialty metals apply to subcontractors?

The clause tells contractors to include its main paragraphs in subcontracts for items containing specialty metals. A supplier is bound when the clause is in its own purchase order. Read the order to see whether it is.

Where is the list of DFARS qualifying countries?

In the DFARS definitions at 225.003 on acquisition.gov. The list is amended from time to time, so check the current page and record the date you checked it.

Is the specialty metals clause the same as the DFARS cybersecurity clause?

No. Cybersecurity sits in clause 252.204-7012, which deals with safeguarding covered defense information. It is a separate obligation with separate evidence.

References

DFARS 252.225-7009 Restriction on Acquisition of Certain Articles Containing Specialty Metals

acquisition.gov

The clause text: definitions, the restriction, the exceptions and the subcontract paragraph. Checked 15 Nov 2026.

Visit source

DFARS 225.003 Definitions

acquisition.gov

Definition of qualifying country and the current list. Checked 15 Nov 2026.

Visit source

DFARS 252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting

acquisition.gov

Named to show it is a separate clause. Not summarised on this page.

Visit source

DFARS 252.246-7007 Contractor Counterfeit Electronic Part Detection and Avoidance System

acquisition.gov

Named to show it is a separate clause. Not summarised on this page.

Visit source