Why the check matters
A purchase order is the buyer's offer to buy. When you acknowledge it, or start work, you usually accept its terms. If the PO references a newer specification than the one you quoted, drops a deviation you declared, or adds documents and tests, you can end up bound to them at your quoted price. That is why this check belongs before the acknowledgement, not after.
What to put side by side
| Your side (what you sold) | Their side (what they ordered) |
|---|---|
| Quotation and price schedule | PO face: items, quantities, prices, delivery, Incoterms |
| Technical offer and datasheets | Attached specifications and datasheets, with revisions |
| Technical deviation list and clarifications | Statements about accepted or rejected deviations; the order of precedence clause |
| Answers to technical queries | Minutes of clarification meetings referenced in the PO |
| Your terms and validity | The buyer's general and special terms |
| Your document list | The vendor data requirements list (VDRL) |
Step by step
- List every document the PO names, with its revision. Check each one is the revision you quoted against.
- Compare each PO line with your quote: item, tag, size, rating, material, quantity, unit price and delivery.
- Read the order of precedence clause. Check whether your offer and deviation list are part of the order, and where they rank.
- Check each deviation and clarification from your offer. Mark it accepted in writing, listed in the PO, rejected, or silent.
- Read the attached specifications and terms for new obligations: extra tests, certificates, inspection, documents, spares, packing or warranty.
- Check commercial terms: price, payment milestones, retention, liquidated damages, Incoterms, warranty and validity.
- Write one list of every difference, with the PO clause and your quote reference, and agree it with the buyer.
- Acknowledge the order only with the differences settled, or with an acknowledgement that lists them.
Where the differences hide
- A specification attached at a later revision than the one you quoted.
- A general statement such as "vendor shall comply with all attached specifications" that cancels your deviations unless they are listed.
- Certificates upgraded, for example from EN 10204 3.1 to 3.2. See EN 10204 3.1 vs 3.2.
- Witness tests or third-party inspection you did not price.
- More documents on the VDRL, or earlier due dates.
- Delivery counted from PO date when you quoted from drawing approval.
- Payment tied to the final data book, or a retention you did not expect.
Silently rejected deviations
The hardest difference to see is the one that is not written down. If your offer declared a deviation, for example a cast body instead of forged, and the PO simply attaches the specification without listing the deviation, many buyers will treat the specification as governing. Ask for every agreed deviation to be listed in the PO or in a signed minute. Keep them in your deviation register (beta) through to the order. See also deviations and clarifications.
Handling scope change between quote and PO
If the PO asks for more than you quoted, you have three options: accept it at no cost, price it as a change, or ask the buyer to remove it. Do it in writing before acknowledgement, with the clause and your price or schedule impact. After acknowledgement, the same change usually needs a formal change order, which is slower and harder to win.
Doing it with OdysseyGPT
The Quotation-to-PO Review (beta) reads your quotation, clarifications and deviation register alongside the PO and its attachments. It reports obligations the PO added, deviations it rejected, and scope or commercial changes, each with a quote from both sides. Your sales, contracts or project team decides what to raise. It does not send anything to the buyer. After acceptance, the work moves into order engineering.
These tools are in beta
The Quotation-to-PO Review and the Deviation Register are in beta. You can request access, and we onboard each team ourselves. Every finding cites the page, sheet or cell it came from, and your engineers decide what to do with it.