Download the certificate of conformance template
XLSX
Certificate of conformance template (Excel)
A blank certificate form, a filled-in example and a How to use sheet. Header block, an 11-column item table, a statement and a signature block, set up to print on one landscape page.
CSV
Certificate of conformance template (CSV)
The example rows as plain CSV (UTF-8), for Google Sheets or any other tool.
Both files are free under CC BY 4.0, with no form to fill in. The XLSX opens in Excel, Google Sheets, LibreOffice and Numbers. The CSV carries the table only; the header block is in the XLSX. The statement and signature block are also in the XLSX only.
What it is for and who uses it
Most purchase orders for engineered equipment ask for a certificate of conformance with each shipment, and it is usually one of the first pages of the manufacturing record book. It does not replace the records behind it. Where the order asks for material certificates or test reports, those are still needed.
- Quality managers and quality engineers, who sign it.
- Document controllers, who file it in the record book.
- Receiving inspectors on the customer's side, who check it against the delivery.
If the customer supplies its own certificate form, use that form. Check the purchase order for who must sign and what the certificate must state.
Header block
| Field | Example |
|---|---|
| Certificate no. | CoC-EX-3105-01 |
| Date of issue | 2027-02-05 |
| Supplier | Example Valve Manufacturer Ltd (fictional) |
| Supplier works / address | Example Works, Example Town (fictional) |
| Customer | Example EPC Contractor Ltd (fictional) |
| Project | Example Gas Compression Station, Phase 2 (fictional) |
| Purchase order / revision | PO-EX-3105 Rev 1 (fictional) |
| Supplier order no. | JOB-EX-0871 |
| Governing specification | PS-VAL-001 Rev 2 |
| Agreed deviations and concessions | TDL-EX-2291 Rev B |
| Inspection release note | IRN-EX-3105-01 |
| Delivery note / packing list | DN-EX-3105-01 |
Example: items certified on valve order PO-EX-3105
| PO item | Description | Quantity | Drawing / revision | Specification / standard | Serial / batch nos. | Supporting records | Deviation / concession |
|---|---|---|---|---|---|---|---|
| 1 | Ball valve, trunnion-mounted, 6 in, ASME Class 600, RF flanged, gear operated | 6 ea | GA-BV-0600 Rev B | PS-VAL-001 Rev 2; DS-VAL-0600 Rev B; API 6D | BV-0871-001 to BV-0871-006 | Pressure test reports PTR-EX-0871-01 to -06; material certificates in MRB-EX-3105 | EX-03 (RPTFE seat inserts); EX-08 (tests to API 6D) |
| 2 | Ball valve, floating, 2 in, ASME Class 600, RF flanged, lever operated | 4 ea | GA-BV-0200 Rev A | PS-VAL-001 Rev 2; DS-VAL-0200 Rev A; API 6D | BV-0872-001 to BV-0872-004 | Pressure test reports PTR-EX-0872-01 to -04; material certificates in MRB-EX-3105 | EX-08 (tests to API 6D) |
| 5 | Commissioning spares: seat and seal kits | 1 lot (10 kits) | Spare parts list SPL-BV-01 Rev A | MR-VAL-001 Rev 1 section 6 | Batch SB-2291 | Elastomer batch certificate EC-2291 | None |
The file also has Tag(s), Part / model no. and Remarks columns. Every example value is invented: the project, customer, bidders, purchase order, prices and every document, certificate, serial and report number do not exist. Standards are named but not quoted.
Statement and signature block
Example statement
We certify that the items listed above were manufactured, inspected and tested in accordance with the purchase order and the specifications and drawings listed, and that they conform to those requirements, except for the agreed deviations and concessions referenced. The supporting records are held on file and are available on request.
Example wording only. Use the statement your contract, customer or quality system prescribes, and check what the purchase order asks the certificate to state.
| Field | Example |
|---|---|
| Authorised signatory (name) | Quality manager (fictional) |
| Position | Quality manager |
| Signature | (signed by hand or electronically) |
| Date | 2027-02-05 |
Columns and what to write
| Column | What to write |
|---|---|
| PO item | The purchase order line the row certifies. |
| Description | What was supplied, as the purchase order describes it. |
| Tag(s) | Equipment tag numbers, where the order uses them. |
| Quantity | Quantity shipped under this certificate, with unit. Say so in Remarks if it is a part shipment. |
| Part / model no. | Your part, figure or model number. |
| Drawing / revision | The drawing or datasheet the item was made to, with the revision that applied. |
| Specification / standard | The specifications and standards the order names for the item, with revision or edition. Name them; do not quote them. |
| Serial / heat / batch nos. | Serial numbers, or heat, lot or batch numbers, so the certificate can be tied to the parts. |
| Supporting records | The test reports, material certificates or record book sections that back the statement. |
| Deviation / concession ref. | Agreed deviations and approved concessions that apply to the item, or None. |
| Remarks | Part shipments, shelf life, storage conditions or anything else the receiver needs. |
How to use the template
- Check what the purchase order asks for: who must sign, the statement wording, and whether the customer supplies its own certificate form. If it does, use that form.
- Fill in the header block: certificate number, supplier, customer, purchase order and revision, governing specification, and the agreed deviation list or concessions.
- Add one row per purchase order line shipped under this certificate, with quantity, drawing and revision, and the specifications the order names.
- Enter the serial, heat or batch numbers, so the certificate can be tied to the parts and to their records.
- List the supporting records and any agreed deviation or approved concession for each row. Write None where there is none; do not leave it blank.
- Replace the example statement with the wording your contract or quality system requires.
- Have the person your quality system authorises sign and date it, after the final inspection is released. Issue one certificate per shipment and file a copy in the record book.
Checking the record book behind the certificate
OdysseyGPT does not issue certificates of conformance. In its Handover & MRB module, MRB Readiness Check (beta) compares the record package with the customer's required index and reports missing documents, wrong revisions and unsigned records, and MRB Compiler (beta) assembles the book. Every finding cites the page it came from, and your engineers decide what to do with it. Tools marked beta are open on request, and we onboard each team ourselves.
Want us to run the check for you?
Send your MRB index and the customer's document requirements. We send back an MRB readiness report: what is in place, what is missing and what does not match.