What is LOLER and who does it apply to?
The Lifting Operations and Lifting Equipment Regulations 1998 came into force on 5 December 1998. The Health and Safety Executive (HSE) says they place duties on people and companies who own, operate or have control over lifting equipment. That includes a business whose employees use lifting equipment, whether or not the business owns it.
Lifting equipment is work equipment for lifting and lowering loads. The term includes the attachments used to anchor, fix or support it, and lifting accessories such as slings and shackles. A load can be a person. HSE lists some things LOLER does not cover, among them escalators and many conveyors. Passenger lifts have their own product regulations.
This is not legal advice
This page summarises public guidance for a manufacturer who wants to understand a buyer's requests. It does not tell a duty holder how to comply. HSE regulates health and safety in Great Britain. For Northern Ireland, check with the Health and Safety Executive for Northern Ireland. Read HSE's guidance and the Approved Code of Practice, or take professional advice, before you rely on any point here.
What does LOLER require of the duty holder?
| Subject | What the duty holder must ensure |
|---|---|
| The lifting operation | It is properly planned by a competent person, appropriately supervised and carried out in a safe manner |
| Strength and stability | The equipment is strong and stable enough for each use, and suitable for the task |
| Position and installation | It is placed or installed to reduce, as far as reasonably practicable, the risk of the equipment or load striking a person, or of the load drifting, falling or being released by accident |
| Marking | Equipment is marked with its safe working load. Where that depends on the configuration, the marking or information covers each configuration. Accessories are marked with what is needed for safe use |
| Lifting people | Equipment for lifting people is marked as such, with the number of people it can carry. Equipment that must not lift people is marked to say so |
| Thorough examination | The equipment is examined by a competent person at the times the regulations set, and a report is made |
| Records and defects | Reports are kept, and defects are reported and acted on |
HSE says the amount of planning should match the lift. A routine lift needs little. A complex one needs a written plan and closer supervision. The regulations are supported by an Approved Code of Practice, Safe use of lifting equipment (L113), which HSE publishes free.
What is a thorough examination, and when is one needed?
HSE describes a thorough examination as a systematic and detailed examination of the equipment and its safety-critical parts, carried out by a competent person who then completes a written report. The law does not define a competent person. The Approved Code of Practice says they need the practical and theoretical knowledge and experience to detect defects and judge how much they matter. They must be independent enough to be impartial, and should not be the person who routinely maintains the equipment.
| When | What the regulations say |
|---|---|
| Before first use | Required, unless the equipment is new, has a declaration of conformity made not more than 12 months earlier, and was not assembled on site |
| After installation | Required where safety depends on the installation conditions, and again after assembly at a new site or location |
| In service | At least every 6 months for equipment that lifts people and for lifting accessories, and at least every 12 months for other lifting equipment, or at the intervals in an examination scheme drawn up by a competent person |
| After exceptional circumstances | Required after events liable to affect safety, such as damage, a long period out of use or a major change |
The second row matters to crane makers. An overhead crane is erected on the user's runway, so its safety depends on the installation. The declaration that came with it does not remove the need for an examination before it goes into service.
- The written report must hold the information in Schedule 1 of the regulations. That includes the identity of the equipment, its safe working load, the date of the examination, the latest date for the next one, any defect and the details of any test.
- The examiner must tell the employer at once about a defect that is, or could become, a danger, and make the written report as soon as is practicable.
- Where a defect involves an existing or imminent risk of serious injury, a copy of the report goes to the enforcing authority.
- Testing is the competent person's decision. HSE says most equipment does not need routine testing as part of an examination, and that some overload tests can cause damage.
- The examination is separate from maintenance and from the user's routine inspections, both of which the user also has to arrange.
The regulations set how long each record is kept. The declaration of conformity is kept for as long as the equipment is operated. The report of an examination before first use is kept until the employer stops using the equipment, or for two years where the item is a lifting accessory. In-service reports are kept until the next report or for two years, whichever is later.
What do the manufacturer's documents contribute?
LOLER does not regulate the manufacturer. Supply is governed by product law: in Great Britain the Supply of Machinery (Safety) Regulations 2008, and in the EU the Machinery Directive and Regulation. HSE notes that most lifting equipment and lifting accessories fall under the machinery regulations, including equipment powered by human effort such as manual chain blocks. Your documents are still what the user's compliance starts from.
| Your document | What the user does with it |
|---|---|
| Declaration of conformity | Keeps it for as long as the equipment is used. Where it is recent enough and safety does not depend on installation, relies on it in place of an examination before first use |
| Load test certificate or test record | Gives the competent person the tests already done and the loads used, so they can decide whether any further test is needed |
| Instructions | Sets the limits of use and the maker's inspection and maintenance guidance that the user builds a regime on |
| Marking and rating information | Provides the safe working load, and the load for each configuration, that LOLER requires to be marked |
| Identity details | Supplies the serial number, description and date of manufacture that the examination report must record |
A buyer's purchasing clauses on documents often trace back to these duties. If a British customer asks for a declaration dated close to delivery, or a serial number on every certificate, that is usually why.
How does LOLER relate to PUWER?
PUWER is the Provision and Use of Work Equipment Regulations 1998. It applies to work equipment in general, and lifting equipment is work equipment, so both sets of regulations apply to it. PUWER covers suitability, maintenance, inspection, safeguards and the training of the people who use the equipment. LOLER adds the requirements that are specific to lifting.
PUWER also touches the manufacturer's documents. HSE's guidance tells a user who provides new work equipment to check that it has an appropriate conformity marking, comes with a declaration of conformity and has instructions in English. Equipment that LOLER leaves out, such as a pallet truck that raises a load just clear of the floor, is still covered by PUWER.
What documents a buyer in Great Britain will expect from the manufacturer
| Document | What to check before it leaves | Why the buyer wants it |
|---|---|---|
| Declaration of conformity | It names this model and serial number, the right legislation for the market and a recent date, and it is signed | The user must keep it, and may rely on it before first use |
| Conformity marking and data plate | The marking, maker's details, serial number, year and rated load match the declaration | PUWER guidance tells the user to check the marking and labelling |
| Safe working load marking | The load on the equipment matches the load in the documents, for every configuration | LOLER requires the marking |
| Test certificate or test record | It identifies the item by serial number and states the tests, loads, date and signatory | The competent person uses it when deciding what further testing is needed |
| Instructions in English | They cover the options supplied, the limits of use, and inspection and maintenance | PUWER guidance asks for them, and the examination regime is built on them |
| Certificates for hooks, ropes, chains and other accessories | Each one can be tied to the item fitted | Accessories are lifting equipment in their own right, with their own examination interval |
| Installation and commissioning records | Where you install, they show what was checked and tested on site | Safety that depends on installation triggers an examination before use |
| Any documents the order adds | Calculation summary, material certificates, welding and NDE records | These are contract requirements, not LOLER requirements |
The load test certificate checklist covers the fields on the test record. Document Review can set a buyer's documentation clauses beside your standard document list and show which ones your list does not answer. It reads documents only. It does not examine equipment, it is not a competent person, and it does not decide whether a user has met LOLER.