OdysseyGPT

Free template

Load test certificate checklist for cranes and lifting equipment (Excel and CSV)

For crane and lifting equipment makers: fifteen points to confirm on a load test certificate before handover, each set against what the contract and the agreed test procedure specify.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

A load test certificate checklist confirms that a crane or lifting equipment load test certificate records what the contract requires before handover. This free Excel template has one row per point: identification, rated capacity as marked, the named test standard, test loads and configuration, measurements, load cell calibration, examination after test, the competent person and deviations.

Key Takeaways

  • Take the test loads from the contract and the agreed procedure. The template gives no percentage of rated capacity.
  • A load measured with a load cell that was out of calibration is not proven.
  • A deflection figure means little without the limit and the document the limit comes from.
  • The example has 15 points on an invented overhead crane certificate (LTC-EX-1475-01), with two fails and five queries.

Download the load test certificate checklist

Both files are free under CC BY 4.0, with no form to fill in. The XLSX opens in Excel, Google Sheets, LibreOffice and Numbers. The CSV carries the table only; the header block is in the XLSX.

The last document before a crane goes into service

A load test certificate records that a crane, hoist or lifting accessory carried a stated test load in a stated arrangement and was examined afterwards. The customer's insurer, safety department and inspection body all read it, often years later. It is written on site at the end of commissioning, when everyone wants to leave, and that is when entries go missing: one motion not recorded, an edition left off, a load cell certificate nobody looked at. Run this checklist in the office within a few days of the test, while the site notes still exist.

  • Commissioning and service engineers at crane and hoist manufacturers, before the handover file is issued.
  • Quality engineers, who release the certificate.
  • Owners' engineers and inspection bodies, as a quick review of a certificate they have been handed.

How large the test loads are, whether a dynamic test is needed and who counts as a competent person all depend on the product standard, the regulations where the equipment is installed and the contract. They differ between countries and equipment types, so the template states none of them. Check the governing standard or contract. See also lifting equipment manufacturers.

Header block

Header block fields, with the invented example values
FieldExample
ProjectExample Workshop Extension (fictional)
CustomerExample Fabrication Works Ltd (fictional)
Purchase orderPO-EX-1475 (fictional)
EquipmentDouble-girder overhead travelling crane, crane no. CR-02 (fictional)
Serial no.EX-OTC-2231 (fictional)
Test standard or specification named in the contractAs stated in the PO, with its edition
Load test procedureLTP-EX-02 Rev A (invented)
Load test certificateLTC-EX-1475-01 Rev 0
Test date2027-05-14
Checklist no.LTK-EX-1475
Date2027-05-17
Prepared byCommissioning engineer
Checked byQuality engineer

Example points: an overhead travelling crane

Invented example points on certificate LTC-EX-1475-01
ItemSubjectPoint to checkWhat the contract specifiesWhat the certificate recordsResultAction before handover
1IdentificationEquipment description, crane number and serial number are those of the order and the nameplatePO-EX-1475 line 1; nameplate drawing NP-EX-1475Crane CR-02; serial EX-OTC-2231OK
2IdentificationThe certificate says where the equipment is installed and what was included in the test, such as the hoist and any attachment below the hookBay 2; main hoist with bottom block; no lifting attachment in the scopeBay 2; main hoistOK
3Rated capacityThe rated capacity on the certificate is the capacity marked on the equipment and stated in the orderRated capacity as PO line 1, marked on both girdersCapacity agrees with the girder marking. The hoist unit's own nameplate shows a different figureQueryThe certificate should state the crane's rated capacity and say which marking governs.
4StandardThe test standard or specification is named with its edition, and is the one the contract namesPO clause 9.1; LTP-EX-02 Rev ALTP-EX-02 named; the standard is named with no editionQueryAdd the edition the PO names.
5Test loadsThe static test load applied is the one the contract specifiesStatic test load as LTP-EX-02 4.2 (contract value, invented order)Load recorded in tonnes; equal to the value in LTP-EX-02 4.2OK
6Test loadsThe dynamic test load and the motions tested under it are as the contract specifiesDynamic test as LTP-EX-02 4.3: hoisting, cross travel and long travelHoisting and cross travel recorded. No entry for long travelFailFind the site record for long travel, or repeat that part of the test.
7ConfigurationThe load positions tested are recorded, and are those the procedure asks forPositions as LTP-EX-02 4.4Mid-span onlyQueryThe procedure also asks for the end positions. Confirm from the site record.
8MeasurementsDeflection, where the contract asks for it, is recorded as a measured value with the limit it was judged against and where that limit comes fromGirder deflection at mid-span as LTP-EX-02 4.5; limit as design specification DS-EX-1475A measured value in millimetres; no limit and no sourceQueryState the limit and the document it comes from.
9MeasurementsChecks of brakes, limit switches and the overload device are recorded where the contract asks for themLTP-EX-02 5.1 to 5.3Brakes held the test load; upper limit switch operated; overload device setting recordedOK
10Test weightsThe test weights or the load cell used are identifiedCertified test weights or a calibrated load cell, as LTP-EX-02 3.1Load cell LC-EX-07; weights list TW-EX-11OK
11Test weightsThe load cell's calibration, or the weights' certification, was valid on the test dateValid on 2027-05-14LC-EX-07 calibration ran out on 2027-04-30FailThe load was measured with an instrument out of calibration. Raise a nonconformance; prove the load from the certified weights or retest.
12ExaminationThe examination made after the test is recorded, with what was looked at and what was foundLTP-EX-02 6.1: structure, welds, bolted joints, ropes and hookExamined after the test; no defect recordedOK
13Sign-offThe competent person is named, with employer and signatureAs the contract and the regulations that apply at the site requireSigned, with the name printed; no employer givenQueryAdd the employer. Check the governing regulations for what a competent person's report must state.
14Sign-offThe certificate carries the date of the test and its own date of issue, and the customer's witness has signed where the contract asksPO clause 9.3: customer witnessTest date 2027-05-14; issued 2027-05-15; witness signedOK
15DeviationsAny departure from the procedure, and any agreed concession, is stated on the certificateNone agreedNone statedOK

The test loads appear only as references to an invented procedure, LTP-EX-02, and never as a figure or a percentage. The crane, its capacity marking, the load cell and the design specification are made up. Every example value is invented: the project, customer, bidders, purchase order, prices and every document, certificate, serial and report number do not exist. Standards are named but not quoted.

Columns and what to write

ColumnWhat to write
ItemRunning number.
SubjectIdentification, Rated capacity, Standard, Test loads, Configuration, Measurements, Test weights, Examination, Sign-off or Deviations.
Point to checkWhat to confirm on the load test certificate before the equipment is handed over.
What the contract specifiesThe clause of the purchase order, specification or agreed test procedure. Write test loads as the contract and the procedure state them; do not work one out from a percentage you remember.
What the certificate recordsWhat the certificate says, as written, including what it leaves out.
ResultOK, Query, Fail or Not applicable (drop-down). Fail rows turn red; Query rows amber.
Action before handoverWhat has to be corrected, added or repeated before the equipment goes into service.

How to go through a certificate

  1. Fill in the header block: the equipment and its serial number, the certificate number, the test date, and the standard or specification and the test procedure the contract names.
  2. Check identification against the nameplate, then the rated capacity against the marking on the equipment and the order.
  3. Find the test loads in the contract and the agreed procedure, and write them in the contract column in the contract's own words. Which loads apply depends on the standard, the regulations at the site and the contract. Check the governing standard or contract.
  4. Compare what was applied and in which positions and motions with what the procedure asks for.
  5. Where the contract asks for deflection or other measurements, look for a measured value, the limit and the document the limit comes from.
  6. Check that the test weights or the load cell are identified, and that their certificates were valid on the test date.
  7. Read the examination after the test and the sign-off: who signed, for whom, and when.
  8. Set the result for each row. Fail rows turn red and Query rows amber. Close each one before the equipment is handed over.

Checking the certificate against the contract and the calibration records

Two comparisons take the time. One is the certificate against the test clauses of the contract and the agreed procedure. OdysseyGPT's Document Review reads those documents together and lists each point where the certificate says something different or says nothing, with page references. The other is dates: in the Inspection & Testing module, Calibration Validity Check (beta) sets the calibration certificates of the load cell and other instruments beside the test date. Whether a gap matters is for your engineer and the competent person to decide. Tools marked beta are open on request, and we onboard each team ourselves.

Want us to run the check for you?

Send your ITP and the customer's quality requirements. We send back what is covered, what is missing and what still needs evidence before the FAT.

Get the free ITP and FAT readiness check

New templates by email (optional)

Your download does not depend on this.

We use your email only for this. See our privacy policy.

Frequently asked questions

What is a load test certificate?

A signed record that lifting equipment was tested under a stated load and examined afterwards. It identifies the equipment, its rated capacity, the test applied, the instruments or weights used, the result and the person who carried it out.

What should a crane load test certificate show?

The equipment and serial number, rated capacity, the standard or specification tested to, the loads and positions, any measurements the contract asks for, the test weights or load cell with calibration details, the examination after the test, and a named signatory with dates.

What test load should be applied?

The one your contract, the product standard it names and the local regulations require for that equipment. These differ, so the template asks you to copy the contract's wording. Check the governing standard or contract.

Is a load test report the same as a thorough examination report?

Not necessarily. In some countries the regulations ask for a report of examination by a competent person with defined contents, and a load test may be only one part of it. Read the regulations that apply at the site.

Can I use the checklist for lifting accessories and hoists?

Yes. Remove the rows that do not apply, such as travel motions, and add any the contract asks for. The columns stay as they are.

References

Creative Commons Attribution 4.0 International

Creative Commons

Visit source

Related Pages