Download the load test certificate checklist
XLSX
Load test certificate checklist (Excel)
Header block, 7 columns, a result drop-down, Fail rows in red and Query rows in amber, frozen header row, filters and a How to use sheet.
CSV
Load test certificate checklist (CSV)
The example rows as plain CSV (UTF-8), for Google Sheets or any other tool.
Both files are free under CC BY 4.0, with no form to fill in. The XLSX opens in Excel, Google Sheets, LibreOffice and Numbers. The CSV carries the table only; the header block is in the XLSX.
The last document before a crane goes into service
A load test certificate records that a crane, hoist or lifting accessory carried a stated test load in a stated arrangement and was examined afterwards. The customer's insurer, safety department and inspection body all read it, often years later. It is written on site at the end of commissioning, when everyone wants to leave, and that is when entries go missing: one motion not recorded, an edition left off, a load cell certificate nobody looked at. Run this checklist in the office within a few days of the test, while the site notes still exist.
- Commissioning and service engineers at crane and hoist manufacturers, before the handover file is issued.
- Quality engineers, who release the certificate.
- Owners' engineers and inspection bodies, as a quick review of a certificate they have been handed.
How large the test loads are, whether a dynamic test is needed and who counts as a competent person all depend on the product standard, the regulations where the equipment is installed and the contract. They differ between countries and equipment types, so the template states none of them. Check the governing standard or contract. See also lifting equipment manufacturers.
Header block
| Field | Example |
|---|---|
| Project | Example Workshop Extension (fictional) |
| Customer | Example Fabrication Works Ltd (fictional) |
| Purchase order | PO-EX-1475 (fictional) |
| Equipment | Double-girder overhead travelling crane, crane no. CR-02 (fictional) |
| Serial no. | EX-OTC-2231 (fictional) |
| Test standard or specification named in the contract | As stated in the PO, with its edition |
| Load test procedure | LTP-EX-02 Rev A (invented) |
| Load test certificate | LTC-EX-1475-01 Rev 0 |
| Test date | 2027-05-14 |
| Checklist no. | LTK-EX-1475 |
| Date | 2027-05-17 |
| Prepared by | Commissioning engineer |
| Checked by | Quality engineer |
Example points: an overhead travelling crane
| Item | Subject | Point to check | What the contract specifies | What the certificate records | Result | Action before handover |
|---|---|---|---|---|---|---|
| 1 | Identification | Equipment description, crane number and serial number are those of the order and the nameplate | PO-EX-1475 line 1; nameplate drawing NP-EX-1475 | Crane CR-02; serial EX-OTC-2231 | OK | |
| 2 | Identification | The certificate says where the equipment is installed and what was included in the test, such as the hoist and any attachment below the hook | Bay 2; main hoist with bottom block; no lifting attachment in the scope | Bay 2; main hoist | OK | |
| 3 | Rated capacity | The rated capacity on the certificate is the capacity marked on the equipment and stated in the order | Rated capacity as PO line 1, marked on both girders | Capacity agrees with the girder marking. The hoist unit's own nameplate shows a different figure | Query | The certificate should state the crane's rated capacity and say which marking governs. |
| 4 | Standard | The test standard or specification is named with its edition, and is the one the contract names | PO clause 9.1; LTP-EX-02 Rev A | LTP-EX-02 named; the standard is named with no edition | Query | Add the edition the PO names. |
| 5 | Test loads | The static test load applied is the one the contract specifies | Static test load as LTP-EX-02 4.2 (contract value, invented order) | Load recorded in tonnes; equal to the value in LTP-EX-02 4.2 | OK | |
| 6 | Test loads | The dynamic test load and the motions tested under it are as the contract specifies | Dynamic test as LTP-EX-02 4.3: hoisting, cross travel and long travel | Hoisting and cross travel recorded. No entry for long travel | Fail | Find the site record for long travel, or repeat that part of the test. |
| 7 | Configuration | The load positions tested are recorded, and are those the procedure asks for | Positions as LTP-EX-02 4.4 | Mid-span only | Query | The procedure also asks for the end positions. Confirm from the site record. |
| 8 | Measurements | Deflection, where the contract asks for it, is recorded as a measured value with the limit it was judged against and where that limit comes from | Girder deflection at mid-span as LTP-EX-02 4.5; limit as design specification DS-EX-1475 | A measured value in millimetres; no limit and no source | Query | State the limit and the document it comes from. |
| 9 | Measurements | Checks of brakes, limit switches and the overload device are recorded where the contract asks for them | LTP-EX-02 5.1 to 5.3 | Brakes held the test load; upper limit switch operated; overload device setting recorded | OK | |
| 10 | Test weights | The test weights or the load cell used are identified | Certified test weights or a calibrated load cell, as LTP-EX-02 3.1 | Load cell LC-EX-07; weights list TW-EX-11 | OK | |
| 11 | Test weights | The load cell's calibration, or the weights' certification, was valid on the test date | Valid on 2027-05-14 | LC-EX-07 calibration ran out on 2027-04-30 | Fail | The load was measured with an instrument out of calibration. Raise a nonconformance; prove the load from the certified weights or retest. |
| 12 | Examination | The examination made after the test is recorded, with what was looked at and what was found | LTP-EX-02 6.1: structure, welds, bolted joints, ropes and hook | Examined after the test; no defect recorded | OK | |
| 13 | Sign-off | The competent person is named, with employer and signature | As the contract and the regulations that apply at the site require | Signed, with the name printed; no employer given | Query | Add the employer. Check the governing regulations for what a competent person's report must state. |
| 14 | Sign-off | The certificate carries the date of the test and its own date of issue, and the customer's witness has signed where the contract asks | PO clause 9.3: customer witness | Test date 2027-05-14; issued 2027-05-15; witness signed | OK | |
| 15 | Deviations | Any departure from the procedure, and any agreed concession, is stated on the certificate | None agreed | None stated | OK |
The test loads appear only as references to an invented procedure, LTP-EX-02, and never as a figure or a percentage. The crane, its capacity marking, the load cell and the design specification are made up. Every example value is invented: the project, customer, bidders, purchase order, prices and every document, certificate, serial and report number do not exist. Standards are named but not quoted.
Columns and what to write
| Column | What to write |
|---|---|
| Item | Running number. |
| Subject | Identification, Rated capacity, Standard, Test loads, Configuration, Measurements, Test weights, Examination, Sign-off or Deviations. |
| Point to check | What to confirm on the load test certificate before the equipment is handed over. |
| What the contract specifies | The clause of the purchase order, specification or agreed test procedure. Write test loads as the contract and the procedure state them; do not work one out from a percentage you remember. |
| What the certificate records | What the certificate says, as written, including what it leaves out. |
| Result | OK, Query, Fail or Not applicable (drop-down). Fail rows turn red; Query rows amber. |
| Action before handover | What has to be corrected, added or repeated before the equipment goes into service. |
How to go through a certificate
- Fill in the header block: the equipment and its serial number, the certificate number, the test date, and the standard or specification and the test procedure the contract names.
- Check identification against the nameplate, then the rated capacity against the marking on the equipment and the order.
- Find the test loads in the contract and the agreed procedure, and write them in the contract column in the contract's own words. Which loads apply depends on the standard, the regulations at the site and the contract. Check the governing standard or contract.
- Compare what was applied and in which positions and motions with what the procedure asks for.
- Where the contract asks for deflection or other measurements, look for a measured value, the limit and the document the limit comes from.
- Check that the test weights or the load cell are identified, and that their certificates were valid on the test date.
- Read the examination after the test and the sign-off: who signed, for whom, and when.
- Set the result for each row. Fail rows turn red and Query rows amber. Close each one before the equipment is handed over.
Checking the certificate against the contract and the calibration records
Two comparisons take the time. One is the certificate against the test clauses of the contract and the agreed procedure. OdysseyGPT's Document Review reads those documents together and lists each point where the certificate says something different or says nothing, with page references. The other is dates: in the Inspection & Testing module, Calibration Validity Check (beta) sets the calibration certificates of the load cell and other instruments beside the test date. Whether a gap matters is for your engineer and the competent person to decide. Tools marked beta are open on request, and we onboard each team ourselves.
Want us to run the check for you?