What is EN 13001?
EN 13001, Cranes: General design, is a series written by the European committee for crane safety, CEN/TC 147. It sets out how to show by calculation that a crane's structure and mechanical parts are strong enough, stable enough and durable enough for the work intended. It is not about one kind of crane. Bridge cranes, tower cranes, mobile cranes and others each have a product standard that draws on it.
| Part | Subject | What a maker uses it for |
|---|---|---|
| EN 13001-1 | General principles and requirements | The overall method: how the proof is structured, and how the crane's duty is classified |
| EN 13001-2 | Load actions | Which loads to consider and how they are combined as the basis for the proof |
| EN 13001-3-1 | Limit states and proof of competence of steel structure | Girders, end carriages, portal legs and other structural members and their connections |
| EN 13001-3-2 | Limit states and proof of competence of wire ropes in reeving systems | The hoist rope and its arrangement |
| EN 13001-3-3 | Limit states and proof of competence of wheel/rail contacts | Travel wheels and the rails they run on |
| EN 13001-3-4 | Limit states and proof of competence of machinery: bearings | Bearings that are not inside bought-in standard components |
| EN 13001-3-5 | Limit states and proof of competence of forged and cast hooks | The hook |
| EN 13001-3-6 | Limit states and proof of competence of machinery: hydraulic cylinders | Cylinders in cranes that use them |
National standards bodies publish the series under their own prefix, such as BS EN 13001 in the UK. Each part has its own edition and amendment history, and when we checked catalogue listings in November 2026 several parts were being revised. Further parts were listed as in preparation and are not in the table. All parts are paid documents.
What does proof of competence mean?
Proof of competence is the phrase the series uses for the calculated demonstration that a crane, or one of its parts, can do its job. The designer takes the load actions from part 2, works out their effects on each member or component, and shows that those effects stay within the limits the relevant part 3 sets.
- The catalogue descriptions of the parts name the hazards the proof is there to prevent: exceeding the limits of strength, including fatigue, exceeding temperature limits, and loss of stability.
- The proof covers both a single extreme event and the build-up of damage over the many load cycles of the crane's life. The second is why the crane's duty matters.
- The series is built on the limit state method. Some parts say they deal with that method only.
- Proof by calculation is separate from proof by test. A load test after erection does not replace the calculation, and the calculation does not replace the test.
For a buyer, the visible result is usually a calculation summary: the classification used, the load combinations considered and a statement that each proof is satisfied. Whether the customer gets the summary or the full calculation is a contract matter, and a frequent row on the deviation list.
Why is the crane's duty classification an input?
Two cranes with the same capacity and span can need very different structures. A maintenance crane lifts near its capacity a few times a year. A process crane in a steel service centre lifts all day. The fatigue part of the proof depends on how many working cycles the crane will see and how heavy the typical load is compared with the rated capacity.
EN 13001-1 therefore asks for the crane's service to be classified before the design starts. The customer knows the process, so the customer's specification should give the class or the data behind it. Older specifications state the duty in other systems: an ISO 4301 class, a FEM group or, in North America, a CMAA service class. These are built on different definitions. If the enquiry gives one of them and the contract design standard is EN 13001, agree in writing how the stated duty turns into the design input. Do not rely on a conversion chart.
If the class is missing
An enquiry that calls up EN 13001 and gives only capacity and span has left out a design input. Raise a clarification, or state in the offer the working cycles and load spectrum you have assumed, so that the assumption becomes part of the contract.
How does EN 13001 relate to EN 15011 and the machinery rules?
EN 13001 gives the general design method. A product standard applies it to one type of crane and adds the rest: equipment, controls, safety devices, verification and the information for use. EN 15011 is the product standard for bridge and gantry cranes. Its published scope covers bridge and gantry cranes that travel by wheels on rails, runways or roadway surfaces, and gantry cranes fixed in one place. It says it does not cover runways and other supporting structures.
| Layer | Document | What it settles |
|---|---|---|
| Law | Machinery Directive, then the Machinery Regulation | The essential health and safety requirements, including extra ones for machinery that lifts loads, and the duty to issue a declaration of conformity |
| Product standard | EN 15011 for bridge and gantry cranes, or the standard for another crane type | How those requirements are met for that type of crane, and how each is verified |
| Design method | EN 13001 series | The calculations that the product standard calls for |
| Contract | The customer's crane specification | Everything the customer wants beyond the law and the standards |
A harmonised standard whose reference is published in the Official Journal gives a presumption of conformity with the legal requirements it covers. Which editions are listed changes over time, and the lists for the Directive and for the Regulation are separate. Check the current list before you name an edition on a declaration. The standards themselves are voluntary. The law is not.
What to check in a crane specification against EN 13001
| Check | Where to look | Why it matters |
|---|---|---|
| Which parts and editions are named | The list of applicable standards | Parts are revised separately. The contract edition governs your calculation |
| The product standard named with it | The same list | EN 13001 alone does not define a finished crane. A bridge crane also needs EN 15011 or the customer's equivalent |
| The classification of the crane's duty | Technical data sheet or process description | It is a design input. Missing means a clarification or a stated assumption |
| Classification of each mechanism | Hoist, cross travel and long travel data | Mechanisms can be classed differently from the structure |
| Duty stated in another system | References to ISO 4301, FEM or CMAA | Agree how it becomes the EN 13001 input |
| Loads beyond normal lifting | Environment and site sections | Wind for outdoor cranes, temperature, seismic requirements, tandem lifts or special attachments |
| What hangs below the hook | Scope of supply | A grab, magnet or lifting beam changes the load the crane sees and may be a separate product |
| The runway and building | Scope split and interface data | The product standard for bridge and gantry cranes leaves supporting structures out |
| Deflection, speed or positioning limits set by the customer | Performance clauses | Customer limits can be tighter than the standard and change the girder |
| Calculations to be submitted | Documentation requirements | Full calculations, a summary, or review by a third party each cost different hours |
| Tests after erection | Testing and handover clauses | Who supplies test loads and what the load test certificate must state |
| Declaration and marking | Commercial and quality sections | Which law the declaration is made under for the country of use |
Customer Specification Review (beta) lists the requirements in an enquiry package and flags ones that are missing or left open, such as a duty classification that is never given. Document Review sets the specification beside your standard technical specification and quotes both. Neither performs a proof of competence or checks one. The calculation remains the work of your design engineers.
Talk through your tender review
See how OdysseyGPT reviews a tender
Tell us how your team reviews tenders today. We can walk through an example together.