What does ASME Section III cover?
Section III of the ASME Boiler and Pressure Vessel Code is titled Rules for Construction of Nuclear Facility Components. In the code, construction takes in materials, design, fabrication, examination, testing, inspection and certification. The rules apply to new components. Inspection of a plant in service is the subject of a different section of the code, Section XI.
In the United States the code has legal force. The regulation 10 CFR 50.55a incorporates named editions of Section III Division 1 by reference, with conditions, and ties the reactor coolant pressure boundary to the Class 1 rules. Elsewhere the code applies because the plant design and the contract call for it. In both cases the edition is fixed by the plant's licensing basis and the purchase order, not by the date of the enquiry.
Divisions and subsections
| Part | Subject |
|---|---|
| Subsection NCA | General requirements for Division 1 and Division 2: responsibilities, quality assurance, authorised inspection, certificates, marks and data reports |
| Division 1, Subsection NB | Class 1 components |
| Division 1, Subsection NCD | Class 2 and Class 3 components. Editions before 2021 held these in two subsections, NC and ND |
| Division 1, Subsection NE | Class MC components, which are metal containment |
| Division 1, Subsection NF | Supports |
| Division 1, Subsection NG | Core support structures |
| Appendices | Mandatory and nonmandatory appendices, including the data report forms |
| Division 2 | Code for concrete containments |
| Division 3 | Containment systems for transport and storage of spent nuclear fuel and high-level radioactive material |
| Division 4 | Fusion energy devices |
| Division 5 | High temperature reactors |
Section III calls up other sections: Section II for materials, Section V for examination methods and Section IX for welding qualifications. A purchase order that names Section III brings those with it. Most equipment makers work in Division 1.
Classes of components
Division 1 does not have one set of rules for all components. It has classes, and each class has a subsection. Class 1 carries the most demanding rules. Class 2 and Class 3 follow. Class MC is for metal containment and Class CS for core support structures. A support takes its rules from the class of the component it holds.
The code does not tell you which class an item belongs to. That decision belongs to the plant owner or its designee, and it is recorded in the design specification the owner provides. In the United States, Regulatory Guide 1.26 gives the regulator's view on sorting components into quality groups A to D, and 10 CFR 50.55a links groups B and C to Class 2 and Class 3. The manufacturer answers the design specification with a design report where the code calls for one.
Read the class on every line
One valve order can hold Class 1, Class 2 and non-code items. The class changes the material requirements, the examination, the documents and the price. If a line item has no class, ask before you quote.
N-type certificates of authorization
To build to Section III and apply the ASME Certification Mark, an organisation must hold an ASME certificate of authorization for the work. ASME issues it after a survey of the organisation's quality assurance programme and how it is put into practice. Each certificate names a scope and a location, and is issued for a limited term, so ask for the current one.
| Designator | Scope in outline |
|---|---|
| N | Components: vessels, pumps, valves, piping, storage tanks and core support structures, among others |
| NA | Field installation and shop assembly |
| NPT | Parts, appurtenances, welded tubular products and piping subassemblies |
| NS | Supports |
| NV | Pressure relief valves |
| N3 | Transport and storage containments under Division 3 |
| OWN | The owner's certificate, for the owner of a nuclear power plant |
Material comes through a parallel route. A material organisation can hold an ASME Quality System Certificate, which covers its quality system for making and supplying material under Section III. A certificate holder can also qualify a material supplier itself. Either way the material arrives with a certified material test report. The quality assurance programme behind all of these certificates draws on ASME NQA-1.
How does Section III differ from Section VIII?
| Point | Section III | Section VIII |
|---|---|---|
| Subject | Components of nuclear facilities: vessels, pumps, valves, piping, supports, containment | Pressure vessels in general industry |
| How it is divided | By class of component, set by the owner | By division: general rules, alternative rules and high-pressure vessels |
| Quality system | A quality assurance programme drawing on NQA-1 | A quality control system described in the code |
| Certificates | N-type certificates, such as N, NPT, NS and NV | U, U2 and U3 |
| Inspector | Authorized Nuclear Inspector, with a nuclear endorsement | Authorized Inspector |
| Material | From a qualified material organisation, with certified material test reports | To the material specification, with the reports the code and the order require |
| Design documents | Owner's design specification, and a design report from the manufacturer where required | User's requirements or design specification, depending on the division |
| Regulatory tie in the US | Incorporated by reference in federal nuclear regulation | Adopted by states and other jurisdictions |
A shop that holds a U certificate cannot build Section III items on the strength of it. The certificates, the inspector's endorsement and the quality programme are all separate. For the general industry code, see ASME Section VIII.
What to check in a tender against ASME Section III
| Check | Why it matters |
|---|---|
| Division, subsection and class for each line item | The class decides the rules, and one order can mix classes |
| Edition and addenda, and any code cases the purchaser allows or requires | The licensing basis may fix an edition older than the one your procedures use |
| Whether the Certification Mark is required, and whether your certificate covers the designator, scope and location | Some purchasers buy to the technical rules of the code without the mark; the order must say which |
| Who provides the design specification, and whether you must produce a design report | Design responsibility changes the price and the people you need |
| The quality assurance requirements, including the NQA-1 edition | The code and the purchaser may each name one |
| Material: source, qualification of the material organisation, and the content of each CMTR | Material from an unqualified source needs qualification or dedication before use |
| Welding and NDE requirements beyond the code, and personnel qualification | Existing procedure qualifications may not cover the additions |
| Purchaser hold and witness points in addition to the ANI's | Two sets of notice periods set the schedule |
| Seismic and environmental qualification, if the specification asks for it | It is usually governed by other standards and can mean a separate test programme |
| Data report form, and any registration the purchaser requires | It decides the final certification paperwork |
| Sub-suppliers: who needs a certificate, and who you qualify yourself | Castings, forgings, bolting and weld filler each need a qualified source |
| Records to deliver and records to keep, with the retention period | Record requirements reach every sub-supplier |
OdysseyGPT's Document Review compares the purchaser's specification package with your own standard specification and drafts a compliance matrix and a list of exceptions, each row quoting its source. After award, Material Certificate Review (beta) checks material test reports against the material purchase requirements, and Welding Qualification Review (beta) checks whether your welding records cover the welds on your weld list.
What OdysseyGPT does not do
It does no design or stress analysis and does not decide whether an item meets the code. That is for your engineers, your quality assurance programme and the Authorized Nuclear Inspector. It does not hold the text of the code and does not read drawings. It is not software qualified under a nuclear quality programme, so qualified people must verify what it reports.
Try it on your own documents
Free sample: a certificate check report
Send up to 20 material certificates and the PO. Get a certificate check report.