Glossary term
ASME U Stamp
The everyday name for the ASME Certification Mark with the U designator, applied to a pressure vessel built to ASME Section VIII Division 1 by a certified manufacturer.
Last reviewed by the OdysseyGPT team
What it is
The ASME U stamp is the ASME Certification Mark with the U designator. A manufacturer certified by ASME applies it to a pressure vessel built to Section VIII Division 1 under the oversight of an Authorized Inspector. It shows the vessel meets the code, not that it meets the purchaser's specification.
Key Takeaways
- U is for Division 1, U2 for Division 2 and U3 for Division 3.
- The certificate names a scope and a shop location.
- An Authorized Inspector verifies the work and signs the data report.
- Meeting the code is not the same as meeting the customer's specification.
Why it matters
The U stamp is the ASME Certification Mark with the U designator. ASME certifies a manufacturer's quality control system and issues a certificate of authorization for a named scope and location. The manufacturer may then apply the mark to pressure vessels it builds to ASME Section VIII Division 1. The manufacturer must hold an agreement with an Authorized Inspection Agency, whose Authorized Inspector verifies the work and signs the data report for each vessel. Other designators cover other scopes: U2 for Division 2, U3 for Division 3 and UM for miniature vessels. ASME issues most of these certificates for three years. The mark on the nameplate says the vessel meets the code. It does not say the vessel meets the purchaser's specification, which usually asks for more than the code does.
How OdysseyGPT uses it
OdysseyGPT does not certify vessels and has no role in ASME certification. Document Review checks a customer's specification package against your own documents, so a requirement for a stamped vessel, a named division or National Board registration appears as a row in the compliance matrix with its source quoted. Your engineers confirm each row.
Evaluation questions
How do I check a fabricator holds a U stamp?
Ask for the current certificate of authorization and check its scope, location and expiry date. ASME also publishes a search of certificate holders on its website.
Does a U stamp cover CE marking?
No. CE marking under the Pressure Equipment Directive is a separate legal route with its own conformity assessment. A vessel can carry both, which means two inspection regimes.
Frequently asked questions
What does a U stamp mean on a pressure vessel?
That a manufacturer certified by ASME built the vessel to ASME Section VIII Division 1 under the oversight of an Authorized Inspector, and has certified this on a data report.
What is the difference between U, U2 and U3?
They are designators for the three divisions of Section VIII. U is for Division 1, U2 for Division 2 (alternative rules) and U3 for Division 3 (high-pressure vessels). A certificate for one does not cover the others.
Is a U stamp the same as an R stamp?
No. The U designator is issued by ASME for new construction. The R stamp is issued by the National Board for repairs and alterations to equipment already in service.
Is a U stamp always required?
No. It depends on the law where the vessel will be installed and on the purchase order. Many jurisdictions in North America and many owners require it. Check the requisition and datasheet.
References
Boiler and Pressure Vessel Certification
ASME
BPVC Section VIII, Division 1
ASME
Paid code.