What is ASME NQA-1?
NQA-1, Quality Assurance Requirements for Nuclear Facility Applications, is a standard published by ASME. It sets out what an organisation's quality assurance programme must control when its work affects a nuclear facility. ASME describes its scope as the structures, systems, components, activities and organisations that matter to the safe and reliable performance of a nuclear facility, over the whole life of the facility.
It is a programme standard. It does not say how thick a valve body must be or how a weld is examined. It says that design must be controlled, that purchase orders must carry the right requirements, that inspections must be planned and recorded, and that records must be kept. The technical rules come from the equipment specification and the code of construction, such as ASME Section III.
NQA-1 replaced the earlier N45.2 series of nuclear quality standards. A separate standard, NQA-2, was folded into it in the 1994 edition.
How is NQA-1 organised?
| Part | What it holds | How a purchase order uses it |
|---|---|---|
| Part I | The requirements for a quality assurance programme, arranged as Requirements 1 to 18 | Named in almost every order that invokes NQA-1. Some orders name only certain requirements for a limited scope of work. |
| Part II | Further requirements for particular kinds of work, set out in subparts. Software is one of the subjects with its own subpart. | Named subpart by subpart, where the work in the order matches |
| Part III | Nonmandatory guidance on applying Parts I and II | Not a requirement unless the order makes it one |
| Part IV | Nonmandatory guidance on using NQA-1, including comparisons with other quality requirements | Used as background, for example when comparing NQA-1 with a regulation or another standard |
Check which parts the order names. "NQA-1" alone is ambiguous. "NQA-1, Part I and Part II" with an edition is a clear requirement.
The eighteen requirements
Part I is built on eighteen requirement areas. Each has a number and a title, and each matches the criterion with the same number in 10 CFR 50 Appendix B. The table gives the titles, with a plain note on what each means for an equipment maker. The notes are ours, not the standard's wording.
| No. | Title | What it means on a supply order |
|---|---|---|
| 1 | Organization | Who is responsible for quality, and their freedom to stop work |
| 2 | Quality Assurance Program | The written programme, its scope, and training and qualification of people |
| 3 | Design Control | Design inputs, checks, changes and verification, where you hold design responsibility |
| 4 | Procurement Document Control | What your purchase orders to sub-suppliers must say |
| 5 | Instructions, Procedures and Drawings | Work done to written, approved documents |
| 6 | Document Control | Issue, revision and distribution of those documents |
| 7 | Control of Purchased Items and Services | Evaluating sub-suppliers and accepting what they deliver |
| 8 | Identification and Control of Items | Marking and traceability, so each part can be tied to its records |
| 9 | Control of Special Processes | Welding, heat treatment and NDE by qualified people to qualified procedures |
| 10 | Inspection | Planned inspections, hold points and independent inspectors |
| 11 | Test Control | Tests run to written procedures with stated acceptance limits |
| 12 | Control of Measuring and Test Equipment | Calibration, and what happens when an instrument is found out of tolerance |
| 13 | Handling, Storage and Shipping | Cleanliness, preservation and packing |
| 14 | Inspection, Test and Operating Status | Showing which items have passed which steps |
| 15 | Control of Nonconforming Items | Identifying, segregating and dispositioning items that do not meet requirements |
| 16 | Corrective Action | Finding the cause of significant problems and preventing a repeat |
| 17 | Quality Assurance Records | Which records exist, how they are kept and for how long |
| 18 | Audits | Planned internal and supplier audits by people independent of the work |
A purchaser's quality requirements often follow the same order. If you set your compliance matrix out under the same eighteen headings, the purchaser's reviewer can follow it without a cross-reference.
How does NQA-1 relate to 10 CFR 50 Appendix B?
| Point | 10 CFR 50 Appendix B | ASME NQA-1 |
|---|---|---|
| What it is | A US federal regulation | A consensus standard published by ASME |
| Who it binds | Applicants and licensees for US nuclear power plants and fuel reprocessing plants | Whoever a contract, a licence commitment or a code requires to follow it |
| Level of detail | Eighteen short criteria that state what must be controlled | Eighteen requirements with more detail on how, plus further parts |
| How a supplier meets it | Through the purchase order, which passes the criteria down | By writing and working to a programme that meets the named edition |
| Who checks | The licensee and its contractors, by audit and surveillance. The regulator inspects licensees and may inspect vendors | The purchaser's auditors. ASME also runs an NQA-1 certification programme for providers of nuclear safety products and services |
The link between the two is a regulatory guide. In Regulatory Guide 1.28 the US Nuclear Regulatory Commission says which NQA-1 editions it accepts as a way to meet Appendix B during design and construction, and on what conditions. Revision 6, issued in 2023, covers Parts I and II of the 2017, 2019 and 2022 editions, with exceptions and clarifications. Earlier revisions of the guide covered earlier editions.
So NQA-1 does not replace Appendix B. A US purchase order for a safety-related item often names both, and adds 10 CFR Part 21 on reporting defects.
Which edition applies?
ASME revises NQA-1 every few years. Editions in recent use include 2008 with its 2009 and 2011 addenda, 2012, 2015, 2017, 2019, 2022 and 2024. ASME's product page shows the edition now on sale.
The newest edition is not automatically the right one. A plant's licensing basis commits its owner to a particular edition, and the owner passes that edition down the supply chain. Two purchasers can therefore send the same supplier orders that name different editions. ASME's own NQA-1 certification lets an organisation either follow the current edition or hold its programme at a stated edition from 2008 onward.
- Use the edition and addenda the purchase order names.
- If your programme is written to another edition, compare the two and record the differences before you sign the order.
- If the order names no edition, ask. Do not assume the latest.
- Pass the same edition to your sub-suppliers, or state in your order which edition you accept from them.
What to check in a purchaser's NQA-1 quality requirements
| Check | Why it matters |
|---|---|
| The edition and addenda of NQA-1, and which parts and subparts are named | Your programme and your last audit are tied to an edition |
| Whether 10 CFR 50 Appendix B and 10 CFR Part 21 are also invoked | Part 21 brings evaluation and reporting duties, and the clause must go into your own orders |
| Which line items are safety-related and which are not | Applying the full programme to every item raises cost; applying it to too few is a nonconformance |
| Whether the purchaser must audit and approve your programme before award or before work starts | The audit date can set the schedule |
| Flow-down: what your sub-suppliers' orders must contain, and whether the purchaser approves sub-suppliers | Sub-suppliers that refuse nuclear clauses force a change of source or commercial grade dedication |
| Right of access for the purchaser, its customer and the regulator, at your works and your sub-suppliers' | You can only grant access you have secured in your own orders |
| Documents to submit for approval before use: quality plan, ITP, procedures, personnel qualifications | Work started on an unapproved procedure may need repeating |
| Hold and witness points, and the notice period | A missed hold point is a nonconformance even if the result is good |
| Material requirements: source, certified material test reports, traceability and marking | They must go into the material order on day one |
| Qualification of special process, inspection and test personnel | The standard the certificates must meet is set by the order |
| Calibration requirements, including traceability of standards and accreditation of laboratories | A calibration supplier may itself need qualifying |
| Nonconformance rules: which dispositions need purchaser approval | "Use as is" and "repair" usually need it in writing |
| Records: the list to deliver, the format, and how long you keep your copies | Retention periods can run for the life of the plant |
| Controls against counterfeit, fraudulent and suspect items | They affect how you buy from distributors |
| Software used for design, analysis or acceptance | Software that supports a safety-related decision may itself fall under the programme |
OdysseyGPT's Document Review compares a purchaser's quality requirements with your own quality manual extract or standard quality plan, and drafts a compliance matrix and a list of exceptions with both texts quoted. Customer Specification Review (beta) lists the requirements one by one. After award, the ITP Validator (beta) checks a quality plan or ITP against those requirements, and the MRB Readiness Check (beta) compares the record folder with the purchaser's index.
What OdysseyGPT does not do
It does not audit, approve or certify a quality assurance programme, and it does not decide whether your programme meets NQA-1. It is not software qualified under a nuclear quality programme. It reads the documents you give it and quotes the source of each finding. People qualified under your own programme must verify the output before relying on it.