How do nuclear equipment makers answer a procurement specification?
A nuclear enquiry is less about the hardware than about proof. The purchaser, who may be a plant owner, a reactor vendor or a contractor acting for one, sends a set of procurement documents. Under the US rules those documents must carry the regulatory, design and quality requirements that apply to the item. The supplier reads all of them, decides which it can meet under its own quality programme, and returns a list of exceptions with its offer.
| Part of the package | What it sets | Question to settle before you price |
|---|---|---|
| Equipment specification | Function, service conditions, materials, qualification testing and the code of construction for the item | Does it ask for environmental or seismic qualification, and who does the testing and analysis? |
| Purchaser's quality requirements | The quality assurance programme the supplier must work to, such as ASME NQA-1, 10 CFR 50 Appendix B or ISO 19443, and the purchaser's additions | Which edition, which parts, and has the purchaser already audited and approved your programme? |
| Safety classification | Whether the item is safety-related, its code class and, on many projects, its seismic category | Is every line item classified, or only the assembly? Spares and soft parts are often left unclear. |
| Code of construction | The design and fabrication rules, for example ASME Section III or RCC-M, with the class and edition | Does your certificate or qualification cover that code, class, scope and shop? |
| Reporting clause | On US orders, a statement that 10 CFR Part 21 applies | Do your procedures cover evaluating and reporting defects, and do your own purchase orders pass the clause on? |
| Documentation and record requirements | The documents to submit for approval, the records to deliver, their format and how long the supplier keeps its own copies | Can you produce each record, in the form asked for, from every sub-supplier in the chain? |
Read the classification first. It decides how much of the rest applies. A safety-related valve and a non-safety valve of the same design can share a drawing and still need different material sources, different inspection points and a different record package.
Which codes and rules come up?
| Rule | What it is | Where it usually applies |
|---|---|---|
| 10 CFR 50 Appendix B | The US Nuclear Regulatory Commission's eighteen quality assurance criteria for safety-related structures, systems and components | US plants, and suppliers anywhere whose customer passes it down |
| 10 CFR Part 21 | The US rule on reporting defects and failures to comply in basic components. It also defines commercial grade dedication | US orders for basic components; procurement documents must say when it applies |
| ASME NQA-1 | The ASME standard of quality assurance requirements for nuclear facility applications, built around eighteen requirements | The usual way a supplier shows it meets Appendix B |
| ASME BPVC Section III | Rules for construction of nuclear facility components, with classes of component and N-type certificates of authorization | Pressure-retaining components and supports on US-design plants |
| RCC-M | AFCEN's design and construction rules for mechanical components of pressurised water reactor nuclear islands | French-design projects |
| ISO 19443 | Requirements for applying ISO 9001 in the nuclear supply chain, for products and services important to nuclear safety | Projects that name it, often alongside the purchaser's own requirements |
| IAEA GSR Part 2 | The International Atomic Energy Agency's safety requirements on leadership and management for safety | The basis many national regulators and owners build their management system rules on |
| ONR guide NS-TAST-GD-077 | The UK Office for Nuclear Regulation's guide to how it assesses supply chain management for nuclear safety related items and services | UK licensed sites. It is written for ONR inspectors and sets expectations for the purchaser, which reach suppliers through the contract |
Section III has its own certificates. ASME issues N-type certificates of authorization after a survey of the organisation's quality assurance programme. The designators include N for components, NPT for parts and piping subassemblies, NS for supports, NV for pressure relief valves and NA for installation and shop assembly. A material supplier can hold an ASME Quality System Certificate as a material organisation. Check what the specification asks for by name.
In the UK, the nuclear site licence makes the licensee responsible for safety, and Licence Condition 17 requires adequate quality management arrangements. ONR's guide expects purchasers to state codes, standards and quality requirements in the contract, to agree quality plans with the supplier, and to say which records the supplier must deliver. A UK supplier meets those expectations through the purchaser's specification, not through a rule addressed to the supplier.
What goes in the list of exceptions?
Nuclear purchasers usually call a deviation an exception, and many ask the supplier to state either "no exceptions" or a numbered list. Each row should give the clause, the requirement, what you offer instead and why. The rows below come up often, and they are about the quality programme as much as the product.
| Subject | What the purchaser may ask | Why a supplier takes exception or asks a question |
|---|---|---|
| Graded quality requirements | The full programme applied to every line item in the order | The supplier wants requirements graded by classification, so non-safety items and standard parts follow its commercial quality system |
| Edition of the quality standard | A named edition of NQA-1 or another standard | The supplier's programme is written and audited to a different edition |
| Record retention | The supplier keeps records for a stated period, or for the life of the plant, and gives notice before disposal | Storage, format and cost. Some suppliers offer to hand the records over instead of keeping them |
| Sub-supplier qualification | Every sub-supplier of safety-related items or services on an approved list, audited by the supplier, sometimes with purchaser approval of each one | Lead time for audits, and sub-suppliers who will not accept nuclear clauses |
| Material sourcing | Material from a qualified material organisation with a certified material test report, or stock material accepted by dedication | Small quantities, long mill lead times and the cost of dedicating commercial material |
| Purchaser access | Right of access to the supplier's works and its sub-suppliers' works for audit, surveillance and inspection | Sub-suppliers that restrict access, or processes the supplier treats as confidential |
| Nonconformance disposition | Purchaser approval before any "use as is" or "repair" disposition | The supplier asks which nonconformances it may close itself, and how quickly the purchaser will answer |
| Counterfeit and fraudulent items | Controls to keep counterfeit, fraudulent and suspect items out of the supply chain | The supplier asks what evidence the purchaser will accept from distributors |
An accepted exception changes the contract. Keep it with the order, because the same wording decides later whether a record is acceptable. The technical deviation list guide covers the format.
Which documents follow after award?
| Document | What it does | Who signs or accepts it |
|---|---|---|
| Quality plan | Sets out the sequence of manufacturing, inspection and test steps for this order, with the procedure and the record for each | Supplier quality; agreed with the purchaser before work starts |
| Inspection and test plan | Lists each inspection and test with its acceptance criteria and the hold and witness points for the purchaser and the inspector. Often combined with the quality plan | Purchaser, and the Authorized Nuclear Inspector on Section III work |
| Certified material test reports | Give the actual chemical analysis, test and examination results for each heat or lot, with the material organisation's certification | Supplier at receipt; reviewed again by the purchaser and inspector |
| Welding records | Procedure specifications, procedure qualification records, welder qualifications and the record of which welder made which weld | Supplier's welding engineer; inspector |
| NDE records | Reports for each examination, with the procedure, the examiner's qualification and the result | Level III examiner; purchaser and inspector |
| Nonconformance reports | Describe each departure from the requirements and its disposition: rework, repair, use as is or reject | Supplier's review; purchaser approval where the order requires it |
| Dedication records | Where a commercial grade item is used in a safety-related application: the critical characteristics chosen and the evidence that each was verified | The dedicating entity under its Appendix B programme |
| Data report | On Section III work, the certificate holder's certified statement on an ASME form, such as Form N-1 for vessels or NPV-1 for pumps and valves | Certificate holder and the Authorized Nuclear Inspector |
| Certificate of conformance | The supplier's statement that the item meets the purchase order, naming the documents and revisions it was built to | An authorised person in the supplier's quality organisation |
| Quality record package | The indexed set of the records above, to the purchaser's record index | Purchaser's quality and records staff, before release for shipment |
The package matters as much as the product. Under Appendix B, documentary evidence that purchased equipment conforms must be at the plant before the item is installed or used. A valve that arrives without its records cannot go into the plant. A free nuclear quality record index template gives a starting list.
How does OdysseyGPT help?
OdysseyGPT reads the files you upload and compares them with the purchaser's written requirements. Each finding quotes the page, sheet or cell it rests on. A qualified person on your side accepts, edits or rejects each one under your own procedures.
| When | What you upload | Tool | What comes back |
|---|---|---|---|
| Enquiry | The equipment specification and quality requirements, and your own standard specification or quality manual extract | Document Review | A compliance matrix and a draft list of exceptions and clarifications, with both sides quoted |
| Enquiry | The procurement specification and the documents it calls up | Customer Specification Review (beta) | A register of requirements, including record, retention and flow-down clauses, with unclear or missing items marked |
| Order | The requirements, your offer and the purchaser's replies | Deviation Register (beta) | One register of exceptions with status and consequence |
| Order | The purchaser's list of documents to submit | VDRL/MDR Tracker (beta) | Each contractual document with its due date, revision and status |
| Manufacture | Your quality plan or ITP and the purchaser's quality requirements | ITP Validator (beta) | Required steps that are missing, hold points shown at a lower level, steps with no acceptance criteria or record |
| Manufacture | Certified material test reports, the material purchase requirements and the bill of materials | Material Certificate Review (beta) | Conflicts and omissions per certificate: grade, heat, chemistry, mechanical results, heat treatment, required tests and statements |
| Manufacture | Bill of materials, certificates and heat list | Material Traceability Check (beta) | Heats with no certificate, certificates with no part, conflicting grades |
| Manufacture | Welding procedures, qualification records, welder qualifications and a weld list | Welding Qualification Review (beta) | Welds the records you hold do not cover |
| Inspection | Weld list, ITP and NDE reports | NDE Coverage Review (beta) | Welds with no report, a different method from the one required, repairs with no re-examination |
| Inspection | Test records and calibration certificates | Calibration Validity Check (beta) | Instruments whose calibration was not valid on the day of use |
| Release | The purchaser's record index and your record folder | MRB Readiness Check (beta) | Records that are missing, at an earlier revision, incomplete or awaiting approval |
| Release | The assembled record package | MRB Traceability Verification (beta) | Breaks in the chain from tag to heat, certificate, weld, welder, test and instrument |
The tools read PDF, Word, Excel and CSV files. They check the documents against the requirements in the files you provide. They do not hold the text of NQA-1, Section III or RCC-M, so a code rule is checked only where your specification, quality plan or procedure states it.
Example result (invented)
| ID | Finding | Why it was raised | Category | Severity | Confidence |
|---|---|---|---|---|---|
| F-MTR-01 | CMTR for body forging heat 5H2217 does not identify the quality programme it was supplied under | Purchase requirement 6.2 asks each certified material test report to name the material organisation's quality programme and its revision. The report for heat 5H2217 carries no such statement. | Missing statement | High | High |
| F-MTR-02 | CMTR for stem bar lot B-3391 reports no heat treatment condition | The material purchase requirement asks for the heat treatment condition on the report. The report gives chemistry and tensile results only. | Missing property | High | Medium |
| F-ITP-01 | Purchaser hold point for the hydrostatic shell test is not in the ITP | Quality requirement 8.4 makes the shell test a purchaser hold point. ITP step 14 shows it as a review of records. | Downgraded intervention | Critical | High |
| F-ITP-02 | No ITP step for liquid penetrant examination of the seat hardfacing | The equipment specification requires the examination after final machining. No step in the ITP names it. | Missing stage | High | Medium |
| F-TRC-01 | Bonnet stud heat 88104 has no certificate in the folder | The heat list assigns heat 88104 to the bonnet studs. No certificate in the folder carries that heat number. | Heat without certificate | Critical | High |
| F-NDE-01 | Body-to-bonnet seal weld W-03 has no examination report | The ITP requires liquid penetrant examination of W-03. No report references that weld number. | Missing report | Critical | High |
| F-CAL-01 | Torque wrench TW-22 was out of calibration at final assembly | The calibration certificate expired on 2026-03-31. The assembly record is dated 2026-04-09. | Expired at use | High | High |
| F-QRP-01 | Record index item 14, welder qualification records, is not in the package | The purchaser's record index lists welder qualification records as item 14. No document in the folder matches it. | Missing document | High | High |
| F-QRP-02 | NCR-014 is filed without the purchaser's disposition | The order requires purchaser approval of each "use as is" disposition. The copy of NCR-014 in the folder shows the supplier's proposal and an empty purchaser approval block. | Incomplete document | Critical | Medium |
| F-QRP-03 | Quality plan in the package is revision 2 | The document register shows revision 4 as the approved quality plan. The package holds revision 2. | Wrong revision | Medium | High |
Each row also carries the source document, the page and the quoted words. None of these findings is an acceptance decision. Under a nuclear quality programme, a qualified person verifies each one against the original records.
Where OdysseyGPT falls short
- It is not software qualified under a nuclear quality programme. Treat its output as a draft. People qualified under your own programme must verify every finding, and every absence of a finding, before a record is accepted.
- It does not replace your quality assurance programme, the Authorized Nuclear Inspector, the purchaser's surveillance or any audit.
- It does no design, stress, seismic or safety analysis, and it does not classify items.
- It does not perform commercial grade dedication. It cannot choose critical characteristics or verify them. It can only read the dedication records you give it as documents.
- It does not read drawings. A weld list or bill of materials must be a table or a list, not only a drawing.
- It cannot tell whether a certificate is genuine, so it is no control against counterfeit or fraudulent items.
- It checks only what is written in the files you upload. A requirement in a document you left out is not checked.
- Check your contract before uploading. Nuclear procurement documents can carry export control or security markings that restrict where they may be stored and processed.
- Only Document Review is generally available. The other tools named on this page are in beta, and we onboard each team ourselves.
Try it on your own documents
Free sample: an MRB readiness report
Send the customer's MRB or data book index and what you have compiled. Get an MRB readiness report.