Water and wastewater equipment manufacturers: check your bid and your submittal against the specification section

For bid engineers, applications engineers and submittals coordinators at makers of pumps, valves, screens, clarifiers, filters, membrane systems and dosing packages for treatment plants.

By Ademola Afolabi, Founder, New Odyssey Ltd ยท Last reviewed:

The short answer

Water and wastewater equipment makers answer a project specification section by section, first with a scope letter and list of exceptions at bid, then with a submittal package after award. OdysseyGPT checks the section against your product data, certificates and manuals and quotes both documents for every finding. Your engineers decide each status.

Key Takeaways

  • The maker rarely contracts with the plant owner. The offer goes to bidding contractors, and the engineer judges the product later through the submittal.
  • The equipment section, the general submittal section and each addendum all carry requirements. Reading only Part 2 of the equipment section misses most of the paperwork.
  • Exceptions belong in the scope letter at bid. A deviation that first appears in a submittal is usually returned.
  • OdysseyGPT reads documents and quotes its sources. It does not read drawings, size equipment or run the submittal workflow.

See how OdysseyGPT reviews a tender. Tell us how your team reviews tenders today. We can walk through an example together. Book a call

How do water and wastewater equipment makers answer a bid?

A municipal treatment plant project is normally designed by a consulting engineer and built by a general contractor. The engineer writes a project manual: general and procedural sections at the front, then one technical section for each kind of equipment. The equipment maker quotes to the contractors who are bidding, often through a local representative, and usually has no contract with the owner at all.

In North America the manual follows the MasterFormat numbering published by the Construction Specifications Institute, which has a division for water and wastewater equipment and others for process piping and process equipment. Most equipment sections are written in three parts: general, products and execution. Requirements for the maker sit in all three.

Where a treatment plant bid package puts requirements for the equipment maker (own summary)
Part of the packageWhat it holdsWhat the maker has to do with it
The equipment section, Part 1Scope, referenced standards, the submittals wanted, quality assurance, experience clauses, warranty and spare partsList every submittal item and every qualification clause. These are the ones a product datasheet does not answer
The equipment section, Part 2Named manufacturers, performance and design conditions, materials, coatings, motors, controls and factory testsCompare line by line with the standard product and note each difference
The equipment section, Part 3Installation, the manufacturer's field services, field tests, training and start-upPrice the days on site and the trips, and check what the field test must prove
The equipment scheduleTag numbers, quantities, duty points, sizes and motor ratings for each unit, on a drawing sheet or at the back of the sectionCheck each tag against the section text. The schedule and the text do not always agree
The general submittal sectionHow submittals are numbered, packaged, certified, reviewed and resubmittedBuild the package to it. The rules apply to every section in the manual
AddendaChanges and answers to bidders' questions issued before bid dayRe-read the section after each one. An addendum can change a duty point or add a named manufacturer

Many sections name one or more manufacturers and add "or equal" or "or approved equal". The clause decides how an unnamed maker gets in. Some specifications want a substitution request approved before bid day, with a deadline. Others leave it to the submittal after award, which puts the risk on the contractor who carried the price. Read the substitution article in the front-end sections as well as the equipment section, because the two are meant to be read together.

The maker's answer at bid is short: a scope letter that names the section and the addenda received, states what is included and excluded, and lists the exceptions. The full answer comes after award, in the submittal.

Which standards and approvals come up in water equipment specifications?

A water equipment section usually cites a product standard, a drinking water contact standard where the equipment touches potable water, and a funding or procurement clause. The table gives the ones that appear most often, at name level. It is our own summary. Use the edition and the wording your contract gives.

Standards, approvals and clauses named in water and wastewater equipment specifications (own summary)
ReferenceWhat it isWhat the section usually asks the maker for
AWWA standards, pipe and accessories groupAmerican Water Works Association standards for pipe, linings and coatings, valves, hydrants, actuators and slide gates, numbered with a C. C504 covers rubber-seated butterfly valves and C509 and C515 cover resilient-seated gate valvesA statement that the product conforms to the named standard, the purchaser options chosen, and the test records the standard calls for
AWWA pump and plant equipment groupsE102 and E103 cover submersible vertical turbine pumps and horizontal centrifugal and vertical line shaft pumps. The F group covers items such as ultraviolet disinfection and ozone systemsConfirmation of conformance and the factory test evidence set by the section
AWWA treatment groupStandards numbered with a B for filter media, membrane systems and treatment chemicalsNamed for media and membrane packages. Check which parts apply to supplied equipment and which to the plant operator
NSF/ANSI/CAN 61A health effects standard for products and materials that touch drinking water. A product is tested and listed by an accredited certification bodyThe listing for the exact model, size and material offered, from the certifier's directory
NSF/ANSI/CAN 372A standard for evaluating the lead content of drinking water productsEvidence of compliance for wetted parts where the lead free rules apply
Regulation 31 and WRAS approval (United Kingdom)Regulation 31 governs products that water companies use in public supply in England, with matching rules in the other nations. WRAS approval is a certification scheme for fittings installed in premises under the Water Fittings RegulationsWhich regime the buyer means. They cover different parts of the system and are not interchangeable
Domestic preference clauses (United States)The Build America, Buy America Act covers iron, steel, manufactured products and construction materials on federally funded infrastructure. The older American Iron and Steel requirement covers iron and steel products on State Revolving Fund projectsA signed statement of where the product is made, in the form the funding agency or the contractor asks for

A domestic preference clause is a bid decision

Whether a product meets a domestic preference clause depends on where it and its components are made and on the agency's current rules and waivers. Treat the clause as a question for your own compliance or legal function before bid day. If the answer is no or not yet known, say so in the scope letter.

AWWA does not test, certify or approve products, so "AWWA approved" in a specification has no formal meaning. What the engineer can ask for is the maker's statement of conformance and the records the standard requires. An NSF/ANSI/CAN 61 listing is different: it is issued by a third party and can be looked up.

What goes in the list of exceptions?

The list of exceptions names each paragraph of the section the offer does not meet as written, says what is offered in its place and gives the reason. Engineers and contractors in this sector also call it a list of deviations or clarifications. The same areas come up on most water and wastewater equipment offers.

Where water and wastewater equipment offers most often differ from the section (own summary)
AreaWhat to check before the scope letter goes out
Materials of constructionWetted part materials, shaft and fastener grades and elastomers against your standard build, especially where the section copies another maker's material list
Coatings and liningsThe paint system, surface preparation, film thickness and holiday testing the section names, against your shop standard, and whether the lining must be listed for drinking water contact
Drinking water contact evidenceWhether a listing exists for the exact model, size and material offered. A listing for a different size range or lining is not evidence for this one
Performance and duty pointsEach tag in the equipment schedule against your selection, including conditions stated only in a note
Motors, drives and controlsEnclosure, efficiency class, voltage, variable speed drive compatibility, named makes for control components and the panel standard
Experience and reference clausesRequired years in production, numbers of similar installations and reference lists. These are yes or no questions and cannot be engineered around
Factory tests and witnessingWhich tests are on every unit, which are witnessed, and who pays for the witness to attend
Field servicesDays and trips for installation checks, start-up, field testing and operator training, compared with what the price allows
Warranty and sparesWarranty period and start date, extended or special warranties, and the spare parts and special tools listed
Domestic preferenceWhether the product as built for this order meets the clause, and what statement can be signed

Declare at bid, not in the submittal

Many general submittal sections require the contractor to flag every variation from the contract documents when the submittal is made, and some state that review does not approve a variation that was not flagged. An exception left out of the scope letter tends to surface at exactly that point, after the price is fixed.

For the format of a deviation line, see the technical deviation list guide. A clause-by-clause table that covers the whole section is a compliance matrix.

How does the submittal process work after award?

After award the contractor issues a purchase order and asks for the submittal. A construction submittal is the package that shows the engineer what will be supplied before it is made or shipped. The maker prepares it, the contractor reviews and stamps it, and the engineer reviews it against the section.

What an equipment submittal usually contains (own summary; your section's submittal article governs)
ItemWhat it isWhat the reviewer checks
Product dataCatalogue pages, datasheets, performance curves, materials lists and motor data, marked to show the model and options offeredThat the marked-up data matches each paragraph of Part 2 and each tag in the schedule
Shop drawingsDrawings prepared for this project: dimensions, weights, anchor locations, connections, wiring and control diagrams. See shop drawing submittalFit with the structure, piping and electrical design
Design data and calculationsSelections, sizing and, where the section asks, anchorage or seismic calculationsThat the basis matches the stated design conditions
CertificatesStatements of conformance to named standards, drinking water contact listings, domestic preference statements and welder or coating applicator qualificationsThat each certificate names this project and this product
Test reportsFactory test procedures before the test, and results afterwardsThat the test and its acceptance basis are the ones the section sets
Manufacturer's instructionsStorage, handling and installation instructionsThat they exist before the equipment arrives on site
Operation and maintenance dataThe O&M manual, often in a draft before shipment and a final after start-upContent and format against the O&M article, which is often in a separate section
Closeout itemsWarranty certificates, field service reports, training records and spare parts listsThat everything the section promised has been handed over

The engineer returns each submittal with a review action. The wording is set by the contract and varies. Common actions are approved, approved as noted, revise and resubmit, and rejected, and some engineers avoid the word "approved" and write "no exceptions taken" or "make corrections noted". The public US federal guide specification for submittal procedures uses approved as submitted, approved as noted, and disapproved with a resubmission. An approved as noted return still carries obligations: each note has to be answered or built in.

The contractor tracks every item on a submittal log, also called a submittal register. A maker with more than one section on a project needs its own copy, with each resubmission and each review comment against it. A free submittal log template is available. The maker's side of the same job, where the order carries a document list, is the vendor data requirements list.

Which factory tests and certificates are asked for?

Test and certificate requirements sit in three places: the named standard, the equipment section and the general quality sections. The section can add to the standard, and it often does.

Test records and certificates a water or wastewater equipment order may call for (own summary)
RecordTypical source of the requirementWhat to confirm at bid
Pump performance test reportThe pump section, which names a test standard and an acceptance gradeWhether the test is on every pump or one per size, certified or witnessed, and with the job motor or a shop motor
Valve and gate test recordsThe AWWA standard named for the valve or gate type, plus any extra tests in the sectionWhich tests the section adds or makes witnessed, and whether actuators are tested mounted
Coating and lining recordsThe coating section or the coating standard named in the equipment sectionSurface preparation, thickness and holiday test records, and who signs them
Material certificatesThe section's materials articleWhether certified mill test reports are required for castings, shafts or pressure parts, or a certificate of conformance is enough
Drinking water contact listingThe section's reference to NSF/ANSI/CAN 61 or to a national approvalThat the listing covers the model, size, material and lining on this order
Certificate of conformanceThe submittal articleThe exact wording wanted. See certificate of conformance
Calibration evidenceThe test article or the general quality sectionWhether certificates for test instruments must be included with the test report
Factory acceptance test for packaged systemsSections for skid-mounted, membrane, dosing and control panel packagesThe procedure approval step, the notice period and what counts as a pass. See FAT vs SAT

Field tests are separate. Part 3 of the section normally sets a functional test and sometimes a performance test on site, with the manufacturer's representative present and a signed certificate of proper installation. Those days belong in the price and in the scope letter.

How does OdysseyGPT help?

OdysseyGPT reads the documents you upload and checks them against the written requirements. Every finding shows the passage it rests on in both documents. Document Review takes one document as the base, such as the equipment section with its addenda, and checks the documents you select against it: your product data, scope letter, certificates and draft O&M manual. It works in both directions, so it also lists commitments in your documents that the section does not ask for. The other tools each take a narrower set of documents.

Water and wastewater equipment documents and the tool that reads each
Your documentToolWhat it reports
The equipment section, the general submittal section and your offer or submittal packageDocument ReviewA status and a pair of quotes for each paragraph of the section, and an editable matrix with a list of exceptions and clarifications
The project manual sections and addenda that apply to your equipmentCustomer Specification Review (beta)A requirements register: one line each for technical, quality, test and document obligations, with the paragraph it came from
The engineer's equipment schedule or datasheet as a spreadsheet, and your filled datasheetDatasheet Comparison (beta)Matched fields and each material difference in value, with the cell it came from
Scope letter, clarification replies and returned review commentsDeviation Register (beta)One running record of each exception, declared or not, through to the engineer's decision
The contractor's list of required documents for your orderVDRL/MDR Tracker (beta)A register of each document with its due date, revision and review status, and overdue resubmissions flagged
Mill test reports for castings, shafts and pressure partsMaterial Certificate Review (beta)Each certificate checked against the purchase requirements and the material specification
Your inspection and test plan and the section's quality and test articlesITP Validator (beta)Tests the section asks for that the plan leaves out, and witness points that do not match
Factory test reports and instrument calibration certificatesCalibration Validity Check (beta)Each instrument named in a report matched to a certificate and checked for validity on the test date
Factory acceptance test procedure, ITP, calibration evidence and open items for a packaged systemFAT Readiness Check (beta)A readiness verdict, with blockers listed apart from review items
The closeout folder and the contract's required indexMRB Readiness Check (beta) and MRB Compiler (beta)Documents that are missing, unapproved or at the wrong revision, and a manifest in index order

The tools are grouped by stage: tender, order, inspection and handover. Makers of rotating equipment and valves for other industries have their own pages: pump manufacturers and valve manufacturers.

What does a result look like?

This table is an invented example. The project, the section and paragraph numbers, the pump, the maker's documents and every figure are made up to show how a result is laid out. None of it comes from a real specification, a real manufacturer or a standard.

Invented example: a specification section for vertical turbine high-service pumps, checked against a maker's submittal documents
Specification requirement (quoted)Maker's document (quoted)StatusNote
"Each pump shall deliver 2,100 gpm at 185 ft total dynamic head." (Section 43 21 39, 2.02.A)"Rated condition: 2,100 USgpm at 185 ft TDH." (Pump datasheet PD-114, line 6)CompliesSame duty point in both documents.
"All materials in contact with potable water shall be certified to NSF/ANSI/CAN 61." (2.03.A)"Bowl assembly listed to NSF/ANSI/CAN 61. Column pipe lining: shop epoxy, two coats." (Product data, p. 4)ClarificationThe bowl assembly is stated as listed. Nothing is said about a listing for the column pipe lining.
"Line shaft shall be Type 416 stainless steel." (2.04.C)"Line shaft: AISI 1045 carbon steel with stainless steel sleeves at bearings." (Bill of materials, item 12)DeviatesA different shaft material is offered. It is not in the scope letter's list of exceptions.
"Each pump shall be factory performance tested with the job motor. The test shall be witnessed by the Engineer." (2.07.B)"Certified non-witnessed performance test with calibrated shop motor." (Scope letter, item 7)DeviatesA shop motor and a non-witnessed test are offered in place of the section's test.
"Furnish an anchor bolt design calculation sealed by a professional engineer registered in the State." (1.04.D)No matching statement found in the documents supplied.Not addressedNot in the submittal contents list. Add it or declare it.
"Manufacturer shall have not less than ten installations of similar size in municipal service for five years." (1.05.A)"Reference list: eight municipal installations, 2014 to 2023." (Reference list, p. 1)ClarificationEight are listed and the list does not say which are of similar size.
"Furnish the services of a factory representative for not less than three days in two trips for start-up and training." (3.04.A)"Includes one trip, two days on site, for start-up assistance." (Scope letter, item 11)DeviatesFewer days and trips are offered, and training is not mentioned.
"Provide a certification that iron and steel products comply with the domestic preference requirements of the funding agency." (1.04.G)"Castings poured and machined at our works. Certification letter available on request." (Scope letter, item 14)ClarificationA letter is offered on request and is not in the package.

A bid engineer or submittals coordinator opens the two quotes on each row and confirms or changes the status. Rows left as deviates go to the list of exceptions. Rows left as clarification become questions to the contractor or additions to the package before it is sent.

Where OdysseyGPT falls short

  • It is not submittal workflow software. It does not number, route, stamp or distribute submittals, and it does not replace the contractor's or the engineer's project platform.
  • It does not read drawings. Layouts, sections, piping and instrumentation diagrams and an equipment schedule that exists only as a drawing sheet are not checked. A schedule supplied as a spreadsheet or as text in the section can be.
  • It does no hydraulic or process design. It does not select a pump, check a system curve, size a clarifier or filter, or tell you whether a duty point can be met.
  • It certifies nothing. It cannot confirm that a product is listed to NSF/ANSI/CAN 61 or approved under a national regime. It can show what your certificate says next to what the section asks for.
  • It does not decide whether a product meets a domestic preference clause. That turns on where things are made and on the agency's rules.
  • It holds no standards. A requirement that sits only inside an AWWA standard is checked only if you upload the edition and the text is readable.
  • It can match a paragraph to the wrong passage or miss one, most often where several tags share one section. The quotes are there so a person can catch it.
  • Tools that carry a beta marker on this page are available on request, and we set each team up ourselves.

Talk through your tender review

See how OdysseyGPT reviews a tender

Tell us how your team reviews tenders today. We can walk through an example together.

Book a call

Buyer questions

20 questions bid engineers, proposal engineers and buyers ask. Last reviewed:

What is an equipment submittal?

It is the package a manufacturer prepares after award to show the engineer what will be supplied before it is built. It normally holds marked-up product data, project shop drawings, certificates, test procedures and installation instructions. The contractor reviews it, stamps it and forwards it. See the glossary entry for construction submittal for the review steps.

Where are the equipment submittal requirements written?

In two places. The submittal article in Part 1 of the equipment section lists what to send for that equipment. A general section near the front of the project manual, often titled submittal procedures, sets numbering, format, certification and review rules for every section. Operation and maintenance data and closeout documents often have further sections of their own. Read all of them.

What is in a water treatment equipment specification section?

Most sections have three parts. Part 1 covers scope, referenced standards, submittals, quality assurance, warranty and spares. Part 2 covers manufacturers, performance, materials, coatings, motors, controls and factory tests. Part 3 covers installation, field services, field testing and training. An equipment schedule gives the duty for each tag. Requirements for the maker appear in all three parts.

What does "or equal" mean in an equipment specification?

It means a product from a maker that is not named may be accepted if the engineer judges it equal to the one specified. The contract decides how and when. Some require a substitution request approved before bid day. Others decide at submittal review, which leaves the contractor carrying the risk. Read the substitution article in the front-end sections.

When should a manufacturer take exceptions to a specification?

At bid, in the scope letter, before the contractor fixes its price. Name each paragraph, say what is offered and why. Many contracts require variations to be flagged in the submittal and state that review does not accept one that was not flagged. An exception first seen in a submittal is commonly returned for resubmission.

What goes in a manufacturer's scope letter?

The section number and title, the addenda received, the equipment and quantities offered by tag, what is included and excluded, the factory tests and field service days in the price, the warranty offered, and a numbered list of exceptions and clarifications. Contractors compare scope letters from several makers, so state plainly what is not included.

How do addenda affect an equipment bid?

An addendum changes the bid documents before bid day. It can revise a duty point, change a material, add a named manufacturer or answer a bidder's question in a way that alters scope. Re-read the affected section after each one and list the addenda you have received in your scope letter, so the contractor can see your price is current.

Which AWWA standards apply to valves for water service?

It depends on the valve type. C504 covers rubber-seated butterfly valves, C509 and C515 resilient-seated gate valves, C500 metal-seated gate valves, C507 ball valves, C508 swing-check valves and C517 eccentric plug valves. Actuators and slide gates have their own numbers. The AWWA standards page lists them at title level. Use the edition your contract names.

Can a product be AWWA approved?

Not formally. AWWA writes standards and does not test, certify or approve products. When a specification says AWWA approved, it can only mean the product conforms to the named standard. The evidence is the manufacturer's statement of conformance, sometimes as a signed affidavit, and the test records the standard and the section require.

When does equipment need an NSF/ANSI/CAN 61 listing?

When it touches drinking water or drinking water treatment chemicals and the specification or the local regulations call for it. The listing must cover the model, size and wetted materials on the order. Equipment for wastewater or raw water service may not need one. The NSF/ANSI/CAN 61 page explains what a listing shows.

Does a listed coating make a valve or pump NSF 61 compliant?

Not by itself. A coating listing covers the coating as a product, usually with conditions on how it is applied and cured. The finished valve or pump has other wetted parts, such as seats, seals and shafts. Check whether the section asks for a listed finished product or for listed materials, and answer in those terms.

Is Regulation 31 the same as WRAS approval?

No. Regulation 31 covers products that water companies in England use in public supply, from the source to the consumer's building, with matching regulations in Wales, Scotland and Northern Ireland. WRAS approval is a certification scheme for fittings installed in premises under the Water Fittings Regulations. A UK buyer's specification should say which one it means. Ask if it does not.

What is a Buy America clause in a water project specification?

It is a domestic preference requirement tied to the project's funding. In the United States, the Build America, Buy America Act covers iron, steel, manufactured products and construction materials on federally funded infrastructure, and the American Iron and Steel requirement applies to State Revolving Fund projects. The supplier is normally asked for a signed statement. Waivers exist, and the rules change, so check current agency guidance.

What do the review stamps on a returned submittal mean?

The wording is set by the contract. Approved, or no exceptions taken, means the item may proceed. Approved as noted means it may proceed if the marked comments are followed. Revise and resubmit means it must be corrected and sent again before work proceeds. Rejected means it does not meet the documents. Each note on an approved as noted return is still an obligation.

Why would an equipment supplier keep its own submittal log?

Because one equipment package produces many submittals over months: product data, drawings, calculations, test procedures, manuals and closeout items. A supplier's log shows what is due, what is with the engineer and which comments are open, and which approvals are holding up manufacture. See submittal log, or start from the free submittal log template.

What is the difference between shop drawings and product data in a submittal?

Product data is standard published material, such as catalogue pages, curves and datasheets, marked to show the model and options offered. Shop drawings are made for the project and show dimensions, anchorage, connections and wiring for the equipment as it will be supplied. Sections usually ask for both. See shop drawing submittal.

Which factory tests does a water equipment specification ask for?

It varies by equipment. Pump sections usually ask for a performance test to a named test standard. Valve and gate sections rely on the tests in the named AWWA standard and may add to them. Packaged systems and control panels often need a factory acceptance test. Check which tests are witnessed, on how many units, and what records must be submitted.

Can OdysseyGPT check our submittal against the specification before we send it?

Yes, for the text documents. Document Review takes the specification section as the base and checks your product data, certificates, scope letter and manuals against it. Each row gets a status and a quote from both documents, and items the section asks for that are missing from the package are listed. It does not read drawings. Your engineers decide each status.

Does OdysseyGPT replace the contractor's submittal software?

No. Workflow platforms number, route, stamp and track submittals between the contractor and the design team. OdysseyGPT does a different job for the supplier: checking the content of its own package against the section. For tracking your own document list there is the VDRL/MDR Tracker (beta). See the submittal software comparison.

What does OdysseyGPT not do for a water equipment maker?

It does not read drawings or piping and instrumentation diagrams. It does no hydraulic or process design, so it cannot select a pump or size a filter. It does not certify a product, confirm a drinking water listing or decide whether a domestic preference clause is met. It reads documents and quotes them, and an engineer makes each decision.

Frequently asked questions

Who prepares an equipment submittal at a water equipment manufacturer?

Usually an applications or project engineer with a submittals coordinator, drawing on engineering for drawings and calculations and on quality for certificates and test procedures. A local representative often passes it to the contractor.

Does OdysseyGPT manage the submittal workflow?

No. It checks the content of your package against the specification section before you send it. Numbering, routing, stamping and tracking stay in the contractor's and the engineer's own systems.

Can OdysseyGPT read a specification section from a project manual?

Yes. It reads PDF, Word, Excel and CSV files and cites the page, sheet or cell for each quote. It does not read drawings, so an equipment schedule on a drawing sheet is outside what it checks.

What if the equipment section and the general submittal section disagree?

Ask the contractor to raise a question with the engineer before you build the package. The front-end sections usually state which document governs, and the answer should be on record.

References

AWWA standards list

American Water Works Association

Used for standard numbers, titles and groupings. The standards themselves are paid documents. Read 15 Nov 2026.

Visit source

AWWA standards programme

American Water Works Association

How the standards are developed and what they are for.

Visit source

UFGS 01 33 00 Submittal Procedures

US Department of Defense, Unified Facilities Guide Specifications, hosted by the Whole Building Design Guide

A public guide specification. Used for submittal types, the submittal register and review action wording. Private and municipal contracts use their own wording.

Visit source

NSF/ANSI/CAN 61: Drinking Water System Components, Health Effects

NSF

Scope of the standard. The standard is a paid document.

Visit source

Build America, Buy America (BABA) overview

US Environmental Protection Agency

The categories covered and the grounds for a waiver. Read 15 Nov 2026.

Visit source

State Revolving Fund American Iron and Steel (AIS) requirement

US Environmental Protection Agency

The programmes the requirement applies to.

Visit source

What is Regulation 31?

Drinking Water Inspectorate

The regulation in England and the matching regulations in Wales, Scotland and Northern Ireland.

Visit source

Approvals directory

Water Regulations Approval Scheme Ltd

The public list of WRAS approved products and materials.

Visit source

Related Pages

Module

Tender & Quotation

The tools for checking a tender package and what they produce.

Standards

AWWA standards

How the standards are grouped, the valve, pump and coating ones makers meet most, and a specification checklist.

Standards

NSF/ANSI/CAN 61

What the drinking water contact standard covers, how listings work and what a supplier submits.

Glossary

Construction submittal

What a submittal is, what goes in one and how it is reviewed.

Glossary

Submittal log

The register that tracks each submittal from due date to final action.

Glossary

Shop drawing submittal

Project-specific drawings from the maker, and how they differ from product data.

Comparison

Submittal software

Submittal workflow tools compared, and where a supplier-side check fits.

Template

Submittal log template

A free register for tracking submittals and resubmissions.

Product

Document Review

Check a specification section against your submittal documents, in both directions.

Product

VDRL/MDR Tracker (beta)

Turn the contractor's document list into a register with due dates and review status.

Industry

Pump manufacturers

How pump makers answer customer specifications and datasheets.

Industry

Valve manufacturers

How valve makers check tender packages against their documents.

Template

Compliance matrix template

A paragraph-by-paragraph matrix you can adapt to an equipment section.

Pillar guide

Technical deviation list guide

The deviations you agree at bid stage are the ones you verify and record later.