Submittal Log
A register of every submittal a project requires, with the specification section, the item, who supplies it, the dates it is due, sent and returned, and the review action. Also called a submittal register.
Last reviewed by the OdysseyGPT team
What it is
A submittal log is a register of every submittal a construction project requires. Each row gives the specification section, the item, the party responsible, the dates it is due, sent and returned, and the review action. The contractor keeps it for the project, and an equipment supplier keeps one for its own package.
Key Takeaways
- The log is built from the submittal articles of the specification sections.
- Each resubmission is a new line or revision, so the history of an item stays visible.
- On US federal work it is called the submittal register.
- A supplier's own log shows which approvals are holding up manufacture.
Why it matters
A submittal log is the list that keeps track of every submittal on a project. The contractor usually builds it at the start by reading each specification section and listing each item the section's submittal article asks for. The log is then kept up through the job. A row normally carries the specification section and paragraph, a submittal number, a description, the type of submittal, the supplier or subcontractor responsible, the date the item is needed, the dates it was sent and returned, the review action and the revision number. Many contractors add the lead time of the equipment, so the log shows which approvals hold up an order. On US federal work the same document is called the submittal register. The guide specification for submittal procedures attaches a register form and expects the contractor to keep it current and the approving authority to record its action codes on it. An equipment maker has its own reasons to keep one. A package for a pump or a filter system is seldom a single submittal: product data, drawings, calculations, test procedures and manuals go in at different times and come back with different actions. A maker's log shows what the contractor still expects, which items are waiting on a resubmission and which review comments are still open. Where the purchase order carries a document list, that list plays the same part and goes by other names, such as a vendor data requirements list.
How OdysseyGPT uses it
Customer Specification Review (beta) lists the document and submittal obligations in a specification section, each with the paragraph it comes from, which is the raw material for a log. VDRL/MDR Tracker (beta) turns a customer's document list into a register with due dates, revisions and review status. Neither is submittal workflow software: they do not route or stamp submittals, and a person keeps the log.
Evaluation questions
How do you build a submittal log from a specification?
Read the submittal article of each section that applies to your scope, list each item as a row with its paragraph number, then add items the general submittal section and the closeout section require. Set a date for each from the delivery schedule.
Frequently asked questions
Is a submittal log the same as a submittal register?
Yes. Register is the term used on US federal projects and in some owner specifications. Log is the everyday term among contractors. Both mean the tracking list of required submittals and their status.
Who keeps the submittal log?
The general contractor keeps the project log, and the design team often keeps its own record of what it received and returned. Suppliers with several submittals on a project usually keep a log of their own items.
What columns does a submittal log need?
At least the specification section, submittal number, description, responsible supplier, required date, date sent, date returned, review action and revision. Add lead time and open comments if the log is used to manage an equipment order.
References
UFGS 01 33 00 Submittal Procedures
US Department of Defense, Unified Facilities Guide Specifications, hosted by the Whole Building Design Guide
A public guide specification for US federal construction. Used for submittal types, the submittal register and review action wording. Your contract's own submittal section governs.