Glossary term
Construction Submittal
A package of documents, drawings or samples that a contractor sends to the design team for review before work is made or installed, to show that what will be supplied matches the contract documents.
Last reviewed by the OdysseyGPT team
What it is
A construction submittal is a package of documents, drawings or samples that a contractor sends to the engineer or architect for review before an item is made or installed. It shows that what will be supplied matches the contract documents. For equipment, the manufacturer prepares most of it and the contractor reviews and forwards it.
Key Takeaways
- The specification section lists the submittals wanted. A general section sets the procedure.
- The supplier writes the content, and the contractor reviews, stamps and forwards it.
- Review actions vary by contract. Approved as noted still carries obligations.
- A variation from the contract documents has to be pointed out in the submittal.
Why it matters
A construction submittal is how a contractor shows the engineer or architect what it intends to supply before the item is fabricated, shipped or installed. The contract documents list the submittals wanted, section by section, and a general section near the front of the project manual sets the procedure. For equipment, the supplier writes most of the content and the contractor passes it on. The contractor is expected to review each submittal first and stamp it, because the contract is between the owner and the contractor, not the supplier. A submittal for process equipment usually holds marked-up product data, shop drawings made for the project, design data, certificates, test procedures or reports, manufacturer's instructions and, later, operation and maintenance data and closeout documents. The US federal guide specification for submittal procedures sorts submittals into eleven numbered types on these lines, from preconstruction submittals to closeout submittals. Private and municipal contracts use similar groups under their own names. The reviewer returns the submittal with an action. Typical actions are approved, approved as noted, revise and resubmit, and rejected, and some firms use wording such as "no exceptions taken". Review is for general conformance with the design. It does not normally relieve the contractor or the supplier of meeting the contract documents, and contracts usually say that a variation is accepted only if it was pointed out in the submittal. A submittal is not a substitution request and it is not a request for information. Those have their own procedures.
How OdysseyGPT uses it
Document Review takes the specification section as the base and checks your product data, certificates, test procedures and draft manual against it before the package goes to the contractor. Each finding quotes both documents, and the review also lists items the section asks for that the package does not contain. OdysseyGPT does not read drawings, and it does not number, route or stamp submittals. Your engineers decide every status.
Evaluation questions
What is in an equipment submittal?
Marked-up product data, project-specific shop drawings, design data or calculations, certificates and listings, factory test procedures and reports, installation instructions and operation and maintenance data. The section's submittal article gives the exact list.
Frequently asked questions
Who prepares a construction submittal?
The party that supplies the work prepares the content: a manufacturer, fabricator or subcontractor. The general contractor reviews it, stamps it and sends it to the engineer or architect, and is the one answerable for it under the contract.
What does approved as noted mean on a submittal?
The reviewer accepts the submittal provided the comments marked on it are followed. Work can usually proceed, but each note is an obligation. Some contracts ask for a corrected copy for the record, so read the submittal section.
Is a submittal the same as a substitution request?
No. A submittal shows how the specified item will be supplied. A substitution request asks to supply something other than what is specified, and most contracts set a separate form, deadline and approval for it.
References
UFGS 01 33 00 Submittal Procedures
US Department of Defense, Unified Facilities Guide Specifications, hosted by the Whole Building Design Guide
A public guide specification for US federal construction. Used for submittal types, the submittal register and review action wording. Your contract's own submittal section governs.