What is GAMP 5?
GAMP stands for Good Automated Manufacturing Practice. GAMP 5 is a guide published by ISPE, the International Society for Pharmaceutical Engineering, with the full title "A Risk-Based Approach to Compliant GxP Computerized Systems". The second edition was published in July 2022. ISPE describes it as a framework of good practice to make sure computerised systems are effective and of high quality, written for regulated companies, suppliers and regulators.
It is not a regulation and no authority issues a GAMP certificate. The legal requirements sit elsewhere, for example in EU GMP Annex 11 on computerised systems and in the US rule on automatic, mechanical and electronic equipment, 21 CFR 211.68. Drug manufacturers use GAMP 5 as their method for meeting those requirements, and they pass parts of it to suppliers through the URS and the contract.
The supplier's role under GAMP 5
The drug manufacturer, the regulated company, stays responsible for showing that a system is fit for its intended use. GAMP 5 encourages that company to make full use of supplier knowledge, experience and documentation where it can, and ISPE says the second edition gives more weight to service providers. ISPE's description counts equipment makers among suppliers, alongside software, hardware, system integration and IT service providers.
The customer can only rely on your documents and tests if it can show they are trustworthy. EU GMP Annex 11 says the regulated user should take reasonable steps to confirm a system was developed under an appropriate quality management system, and that the supplier should be assessed appropriately. In practice that means a supplier questionnaire or an audit, and URS lines about your quality system, your software development procedures and your change control.
- What you do: design and build to the URS, write the specifications, test the system and record the results.
- What the customer does: assess you as a supplier, review and approve your documents, decide how much of your testing it can reuse, and carry out its own qualification.
- What the URS response must make clear: which documents and tests are in your standard scope and which are extra.
Software categories and what they mean for your equipment
GAMP 5 sorts software into categories by how much it is configured or custom-built. The category guides how much specification and testing is expected. Four categories are in use. Category 2, once used for firmware, is no longer used.
| Category | What it is | Often applied to on a process skid | What the customer tends to ask for |
|---|---|---|---|
| 1 | Infrastructure software | Operating systems, database engines and similar platform software | A record of what is installed and its version |
| 3 | Non-configured products | Standard devices and packages used as supplied, with only run-time parameters set | Version and parameter records, and tests against the user requirements |
| 4 | Configured products | Standard control or SCADA and HMI packages configured for the project without custom code | A configuration specification, and risk-based testing of the configuration |
| 5 | Custom applications | Control code written for the project, such as bespoke PLC logic and custom scripts | Functional and design specifications, code review and structured testing through the life cycle |
One control system often spans several categories: a standard operating system, a configured visualisation package and custom logic. A URS that states a single category for the whole system is worth a clarification. So is a URS that gives none, because the customer may later ask for category 5 documents on software you priced as a standard product.
Specifications the supplier is asked for
GAMP 5 is often drawn as a V. Specifications run down one side: user requirements, then functional specification, then design specifications. Verification runs up the other, with each level of testing checking one level of specification. ISPE says the approach is not inherently linear and also supports iterative and incremental development. For equipment, the customer writes the URS and the supplier usually writes the rest.
| Document | What it says | Who usually writes it |
|---|---|---|
| Quality and project plan | How the project will be run, documented and tested | Supplier |
| Functional specification | What the system does, in answer to each user requirement | Supplier, approved by the customer |
| Hardware and software design specifications | How the system is built: architecture, modules, interfaces, I/O | Supplier |
| Configuration specification | The settings chosen in configurable products | Supplier |
| Traceability matrix | Links each user requirement to the specification and the test that covers it | Supplier, customer or both |
| Test specifications and reports | Module, integration and acceptance tests, with results | Supplier, often witnessed at the FAT |
| Code review records | Evidence that custom code was reviewed against standards | Supplier |
| Version, backup and change control records | What was delivered, and how changes are controlled | Supplier |
Testing the supplier is asked for
Customers want to reuse supplier testing rather than repeat it. EU GMP Annex 15 allows documentation review and some tests done at the FAT to stand without being repeated at IQ or OQ, where that is appropriate and justified and transport and installation do not affect the function. That only works if your test records meet the customer's standard: approved protocols, expected results stated before the test, signed and dated entries, calibrated instruments and recorded deviations.
- Software module and integration testing before the FAT, with records.
- Factory acceptance testing of the hardware and software together, against an approved protocol. See FAT vs SAT.
- Site acceptance testing after installation.
- Tests of alarms, interlocks, access control, audit trail, data backup and recovery, where the URS asks for them.
- Support for the customer's IQ and OQ, sometimes by supplying draft protocols.
What to check in a tender or URS against GAMP 5
| Check | Why it matters |
|---|---|
| Which edition of GAMP 5 the URS names, and any ISPE good practice guides it adds | The second edition differs from the first, and each extra guide adds expectations |
| The software category the customer assigns to each part of the control system | The category sets the documents and tests, and so the engineering hours |
| The list of life cycle documents, and which need customer approval | Each approval round adds time before you can start building |
| Whether custom code is expected, or the customer's standard libraries must be used | Using customer libraries changes the category mix and the test effort |
| Code review, coding standards and the evidence required | Not every maker keeps formal code review records as standard |
| Traceability matrix: who owns it and in what format | Building it at the end from finished documents is slow and error-prone |
| Supplier assessment: questionnaire, remote audit or site audit, and when | An audit before award can decide the bid, and findings need closing |
| Test record standards for the FAT and SAT, including witness and review periods | Records that fall short cannot be reused in qualification |
| Audit trail, electronic records and signature requirements, and the regulation named | These can need a different HMI or SCADA package or licence |
| User access levels, password rules and time synchronisation | Often set by the customer's IT standards, which differ from your default |
| Backup, restore and disaster recovery tests | Extra test steps at the FAT or SAT |
| Change control after the FAT, and who approves changes | Late software changes can force a retest |
| Whether you supply IQ and OQ protocols, execute them, or only support | A large difference in scope that is easy to leave unpriced |
OdysseyGPT's Document Review checks the URS and the customer's automation and documentation specifications against your own functional specification, standard document list and quality plan. It drafts the compliance matrix and the deviations and clarifications list, with a quote from both sides on each row. The Customer Specification Review (beta) lists the documentation and test requirements in the package, each with its clause.
Where OdysseyGPT falls short
- It is not validated software under GAMP 5, and we do not offer it as a GxP system. Its output is a draft for your engineers to check.
- It does not perform computerised system validation, write test scripts or execute tests.
- It does not classify your software. It reports what the URS says about categories and what your documents say, with quotes.
- It does not hold a copy of GAMP 5 and does not judge your documents against the guide. It compares the documents you upload.
- It does not read source code, PLC programs, P&IDs or other drawings.
- It does not replace a validation lifecycle system or a quality management system. See equipment qualification software compared.