Factory acceptance test (FAT): what it is, who attends and how it runs

A plain account of the factory acceptance test for engineered equipment: its purpose, the people in the room, what a FAT procedure contains, the steps on the day and the documents before and after.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

A factory acceptance test (FAT) is a test of finished equipment at the manufacturer's works, witnessed by the customer, to show it meets the purchase order before it ships. The manufacturer runs it to an approved FAT procedure. The result is a signed test record and a punch list of points to close.

Key Takeaways

  • A FAT shows the customer the equipment works to the order, at the factory, where faults are cheapest to fix.
  • It runs to a FAT procedure (also called a FAT protocol) that the customer approves beforehand.
  • Most failed FATs fail on readiness: an unapproved procedure, an expired gauge, an open NCR.
  • OdysseyGPT's FAT Readiness Check (beta) checks readiness before the customer travels.

What a factory acceptance test is

Factory acceptance testing is the last major step before engineered equipment leaves the works. The manufacturer sets up the finished pump, valve, skid, panel or package and runs the tests the order requires while the customer watches. The purpose is simple: find any fault while the equipment is still with the people and tools that built it.

What gets tested depends on the equipment. A pump has a performance test. A valve has pressure and leakage tests. A skid or control panel has functional, interlock and alarm checks. A FAT also covers checks that are not tests in the strict sense: dimensions, nameplate data, tagging, painting and a review of the documents.

This page explains the test itself. When you are ready to prepare for one, the factory acceptance test checklist lists what to have in place.

Find out if your next FAT is ready to run

Bring the FAT procedure for an upcoming test, with the drawings, calibration certificates, NCR register and punch list. We run the readiness check and show each blocker and where it was read.

Request a demo

Who attends a FAT

People at a factory acceptance test and what each does
RoleFromWhat they do at the FAT
Test engineerManufacturerRuns the test to the procedure and records the readings
Quality engineerManufacturerPresents the documents, records punch items and controls the test record
Project managerManufacturerHosts the visit and agrees actions and dates
Customer's engineerBuyer or EPC contractorWitnesses the test and accepts or comments on the results
Third-party inspectorInspection agencyWitnesses on behalf of the buyer or end user and signs the record
End user's representativePlant owner or operatorAttends where the order gives them the right, often for operability points
Sub-supplier specialistSupplier of a major item, such as a drive or control systemSupports the test of their own equipment

The FAT is normally a hold point for the customer on the ITP. See hold point vs witness point for what that means for notice and waivers.

What a FAT procedure or FAT protocol contains

The FAT procedure is the document the test is run to. Some industries, pharmaceutical equipment in particular, call it a FAT protocol. The manufacturer writes it from the customer's specification and datasheets, and the customer approves it before the test date.

Sections of a FAT procedure
SectionWhat it says
Scope and equipmentThe purchase order, tag numbers and exactly what is under test
Reference documentsSpecification, datasheets, drawings and standards with revisions
PrerequisitesWhat must be complete before the test: earlier inspections, documents, calibration, safety checks
Test set-upArrangement, utilities, test medium, instruments and their ranges
Test stepsEach test in order, with the method and the readings to take
Acceptance criteriaThe value or behaviour that counts as a pass for each step, with its source
Test record sheetsThe forms for readings, results and signatures
Punch listHow faults and open points are recorded, graded and closed
Roles and safetyWho does what, and the safety rules for the test area

The weakest part of most procedures is the acceptance criteria. Each one should point to a line in the datasheet or specification, so nobody argues on the day about what a pass looks like.

How to perform a factory acceptance test

  1. Write the FAT procedure and have the customer approve it.
  2. Run the tests yourself first, as a dry run or pre-FAT, and fix what you find.
  3. Check readiness: approved documents, instruments in calibration, open NCRs closed, safety prerequisites met.
  4. Send the witness notice with the lead time the order requires.
  5. Hold an opening meeting: scope, procedure revision, safety and the plan for the day.
  6. Review the documents: certificates, earlier inspection records and calibration.
  7. Carry out the visual and dimensional checks, then each test step, recording every reading.
  8. Record each fault or open point on the punch list as it is found.
  9. Hold a closing meeting, agree the punch list and its dates, and sign the test record.
  10. Close the punch items and issue the FAT report.

A worked example. A dosing skid is due for FAT on a Tuesday. The procedure is approved and the customer's engineer has flown in. During the document review, the inspector sees that the pressure transmitter used for the leak test has a calibration certificate that expired the week before. The leak test cannot be accepted. The team loses a day finding a calibrated instrument, and the customer extends the visit at the manufacturer's cost. A readiness check a week earlier would have found the date.

Factory acceptance test documents, before and after

  • Before: the approved FAT procedure, approved drawings and datasheets, the ITP, calibration certificates for every test instrument, the NCR register, material and inspection records, and the witness notice.
  • During: the completed test record sheets, the punch list and the attendance sheet.
  • After: the FAT report, the signed punch list with closure evidence, and the release for shipment.

The punch list deserves its own care. See the FAT punch list guide for how to grade and close items, and the FAT readiness checklist template for a form to prepare with. Once the FAT is signed, the customer's inspector can issue the inspection release note.

FAT and SAT

The site acceptance test (SAT) repeats the proof after the equipment is installed, connected to the real utilities and process. The FAT shows the equipment was built right. The SAT shows it still works after transport and installation, in its real setting. The full comparison is in FAT vs SAT.

How OdysseyGPT checks a factory acceptance test is ready

FAT Readiness Check (beta) reviews whether a factory acceptance test is ready to go ahead. You upload the FAT procedure. You can add the drawings, datasheets, the ITP, calibration evidence, the NCR register and the punch list.

  • It checks the customer's witness requirements.
  • It blocks on outstanding NCRs.
  • It checks instrumentation readiness.
  • It checks safety prerequisites.
  • You get a readiness verdict, with hard blockers listed separately from review items.
  • Each finding quotes the procedure, register or certificate behind it, and exports to CSV or JSON for your FAT preparation tracker.

Your test and quality engineers review each finding and decide whether the date holds.

See the blockers a week before the customer flies in

Send one FAT procedure and its supporting documents before the call. You will see the verdict, the hard blockers and the quoted source for each, in time to fix them.

Request a demo

See it on your own documents

Run the FAT once

Choose a FAT on your schedule. Bring its procedure, calibration evidence and NCR register to a demo and leave with a readiness verdict and the list of what to close.

Request a demo

Frequently asked questions

What is the difference between FAT and SAT?

A factory acceptance test is done at the manufacturer's works before shipment. A site acceptance test is done after the equipment is installed at the customer's site. The FAT proves the equipment was built to the order. The SAT proves it works in place, connected to the real utilities and process.

How to perform a factory acceptance test?

Write a FAT procedure and have the customer approve it. Run the tests yourself first. Confirm documents, calibration and open NCRs are in order, then send the witness notice. On the day, review documents, run each test step, record readings and punch items, and sign the record. Close the punch list and issue the report.

What is a FAT procedure?

A FAT procedure is the approved document a factory acceptance test is run to. It lists the equipment under test, reference documents, prerequisites, test set-up, each test step, the acceptance criteria and the record sheets. Some industries call it a FAT protocol. The customer approves it before the test date.

Who attends a factory acceptance test?

The manufacturer's test engineer, quality engineer and project manager attend, with the customer's engineer as witness. A third-party inspector often attends for the buyer or the end user. The end user's own representative and specialists from major sub-suppliers attend where the order or the equipment calls for it.

Is a FAT the same as UAT?

No. User acceptance testing (UAT) is a software term: the users check that a system does what they need before it goes live. A factory acceptance test is for physical equipment at the manufacturer's works. They share an idea, acceptance by the customer, and equipment with control software may need both.

Is there a standard for factory acceptance tests?

There is no single standard for all equipment. The purchase order and specification set the tests. IEC 62381 covers FAT, SAT and site integration tests for automation systems in the process industry, and product standards such as those for pumps and valves define their own tests. Always start from the order.

References

IEC 62381, Automation systems in the process industry: Factory acceptance test (FAT), site acceptance test (SAT) and site integration test (SIT)

International Electrotechnical Commission

ISO 9001, Quality management systems: Requirements

International Organization for Standardization