What is a hold point?
Most pages on this subject are about construction sites. This one is about hold and witness points in the manufacture of engineered equipment, where they are set on the inspection and test plan (ITP) for a valve, pump, vessel or skid.
An inspection hold point is a stage in the plan that the manufacturer must not pass until a named party has inspected and signed. That party is usually the customer's inspector or a third-party agency. If the inspector cannot attend, the only way forward is a written waiver for that stage. A hold point inspection is used where a later stage would hide the work or make a fault costly to fix: before a pressure test, before painting, before a vessel is closed.
Passing a hold point without the signature or the waiver is a nonconformance. The customer can ask for the work to be opened up, or the test to be run again in front of them.
Check your ITP carries every hold point the customer asked for
Bring the customer's quality specification and your draft ITP. We compare them stage by stage and show each missing or downgraded hold point with the clause it comes from.
What is a witness point?
A witness point is a stage the named party has the right to watch. The manufacturer must give notice, in the form and with the notice period the order sets. If the inspector attends, they sign the record. If they do not attend after proper notice, the manufacturer goes ahead, records the result and sends the record to the customer.
The proof of notice is part of the record. Keep the notification, the date it was sent and any reply. Without it, a witness point passed alone looks the same as a witness point that was skipped.
The difference between a hold point and a witness point
Hold and witness points sit in a small family of intervention codes. The letters vary between customers, so always read the legend on the customer's own document.
| Code | Name | What the manufacturer must do | If the inspector does not attend |
|---|---|---|---|
| H | Hold point | Give notice and stop at the stage | Work waits until attendance or a written waiver |
| W | Witness point | Give notice of the stage | Work continues after the notice period; the record is sent on |
| R | Review | Submit the record or certificate for review | No attendance is expected; the document is reviewed later |
| M or S | Monitor or surveillance | Allow access during normal work | No notice for a set stage; the inspector may visit at any time |
One stage can carry different codes for different parties. A hydrostatic test may be a hold for the manufacturer's own quality department, a hold for the customer and a witness point for the end user.
A worked example: hold and witness points on a valve ITP
| Stage | Acceptance reference | Record | Manufacturer | Customer |
|---|---|---|---|---|
| Review of material certificates | Purchase order and material specification | Certificate review sheet | H | R |
| Radiography of body casting | Customer NDE specification | RT report | H | R |
| Dimensional check after machining | Approved drawing | Dimensional report | H | W |
| Hydrostatic shell test | Approved test procedure | Pressure test certificate | H | H |
| Seat leakage test | Approved test procedure | Pressure test certificate | H | H |
| Painting inspection | Paint specification | Paint report | H | W |
| Final inspection and document review | Purchase order | Release note | H | H |
In this extract the customer has three hold points and two witness points. Every one of them needs a notification, and the three holds need a signature or a waiver before the valve moves on.
Where hold and witness points come from, and how they get lost
The manufacturer writes the ITP, but the customer sets the hold and witness points. They are spread across the quality specification, the purchase-order quality clauses, an inspection agency's own requirements and sometimes the datasheet notes. The usual mistakes are simple:
- A hold point in the specification is written as a witness point on the ITP.
- A stage the customer wants to attend is missing from the plan, often painting, PMI or the final document review.
- The plan was copied from the last order and still carries the last customer's codes.
- The acceptance reference for a hold stage is blank, so the inspector has nothing to sign against.
- The notice period on the plan is shorter than the one in the order.
For how to build the whole plan, see the inspection and test plan guide and the ITP template.
Hold points in construction
In construction the idea is the same and the stages differ. A hold point in construction is a stop before work is covered up or made permanent: before concrete is poured over reinforcement, before a trench is backfilled, before a wall is closed over services. The site ITP names the party who must release each one. If you make equipment that is installed on such a site, your factory ITP and the site ITP are two separate plans.
How OdysseyGPT checks hold and witness points on your ITP
ITP Validator (beta) reads the customer's quality specification and your proposed ITP. You can add the purchase-order quality clauses, the standards the specification names and the inspection agency's requirements. It checks every stage for the right intervention level, acceptance criteria, procedure reference and record.
- One finding per ITP stage or missing stage, with the requirement it was checked against.
- Gaps sorted by type: missing stage, wrong intervention level, weak or missing acceptance criteria, missing record.
- A quote from the quality specification, PO clause or ITP for each finding.
- A CSV or JSON export for your ITP revision log.
Your quality engineer reviews each finding and decides what changes on the plan before it goes to the customer for approval.
See a downgraded hold point caught before the ITP is submitted
Send one order's quality specification and ITP ahead of the call. You will see the stages where the plan and the customer disagree, with both documents quoted side by side.
See it on your own documents
Submit an ITP the customer approves first time
Choose an ITP you are about to send for approval. Bring it and the customer's quality requirements to a demo, and leave with a stage-by-stage list of what to fix.