Hold point vs witness point on an inspection and test plan

What a hold point and a witness point mean on a manufacturer's ITP, how notice and waivers work, a worked ITP extract, and how to check your plan carries every hold the customer asked for.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

A hold point is a step in manufacture where work must stop until the customer's inspector has attended, or has waived attendance in writing. A witness point is a step the inspector is invited to watch; if they do not attend after proper notice, work continues and the record is sent to them.

Key Takeaways

  • Hold point: work stops until the named party attends or waives in writing.
  • Witness point: the named party is notified and may attend; work goes on if they do not.
  • The customer's quality specification sets the hold and witness points. The manufacturer's ITP must carry every one of them.
  • OdysseyGPT's ITP Validator (beta) compares the ITP with the customer's requirements, stage by stage.

What is a hold point?

Most pages on this subject are about construction sites. This one is about hold and witness points in the manufacture of engineered equipment, where they are set on the inspection and test plan (ITP) for a valve, pump, vessel or skid.

An inspection hold point is a stage in the plan that the manufacturer must not pass until a named party has inspected and signed. That party is usually the customer's inspector or a third-party agency. If the inspector cannot attend, the only way forward is a written waiver for that stage. A hold point inspection is used where a later stage would hide the work or make a fault costly to fix: before a pressure test, before painting, before a vessel is closed.

Passing a hold point without the signature or the waiver is a nonconformance. The customer can ask for the work to be opened up, or the test to be run again in front of them.

Check your ITP carries every hold point the customer asked for

Bring the customer's quality specification and your draft ITP. We compare them stage by stage and show each missing or downgraded hold point with the clause it comes from.

Request a demo

What is a witness point?

A witness point is a stage the named party has the right to watch. The manufacturer must give notice, in the form and with the notice period the order sets. If the inspector attends, they sign the record. If they do not attend after proper notice, the manufacturer goes ahead, records the result and sends the record to the customer.

The proof of notice is part of the record. Keep the notification, the date it was sent and any reply. Without it, a witness point passed alone looks the same as a witness point that was skipped.

The difference between a hold point and a witness point

Hold and witness points sit in a small family of intervention codes. The letters vary between customers, so always read the legend on the customer's own document.

Common intervention codes on an ITP
CodeNameWhat the manufacturer must doIf the inspector does not attend
HHold pointGive notice and stop at the stageWork waits until attendance or a written waiver
WWitness pointGive notice of the stageWork continues after the notice period; the record is sent on
RReviewSubmit the record or certificate for reviewNo attendance is expected; the document is reviewed later
M or SMonitor or surveillanceAllow access during normal workNo notice for a set stage; the inspector may visit at any time

One stage can carry different codes for different parties. A hydrostatic test may be a hold for the manufacturer's own quality department, a hold for the customer and a witness point for the end user.

A worked example: hold and witness points on a valve ITP

Extract from an ITP for a cast steel valve (illustrative)
StageAcceptance referenceRecordManufacturerCustomer
Review of material certificatesPurchase order and material specificationCertificate review sheetHR
Radiography of body castingCustomer NDE specificationRT reportHR
Dimensional check after machiningApproved drawingDimensional reportHW
Hydrostatic shell testApproved test procedurePressure test certificateHH
Seat leakage testApproved test procedurePressure test certificateHH
Painting inspectionPaint specificationPaint reportHW
Final inspection and document reviewPurchase orderRelease noteHH

In this extract the customer has three hold points and two witness points. Every one of them needs a notification, and the three holds need a signature or a waiver before the valve moves on.

Where hold and witness points come from, and how they get lost

The manufacturer writes the ITP, but the customer sets the hold and witness points. They are spread across the quality specification, the purchase-order quality clauses, an inspection agency's own requirements and sometimes the datasheet notes. The usual mistakes are simple:

  • A hold point in the specification is written as a witness point on the ITP.
  • A stage the customer wants to attend is missing from the plan, often painting, PMI or the final document review.
  • The plan was copied from the last order and still carries the last customer's codes.
  • The acceptance reference for a hold stage is blank, so the inspector has nothing to sign against.
  • The notice period on the plan is shorter than the one in the order.

For how to build the whole plan, see the inspection and test plan guide and the ITP template.

Hold points in construction

In construction the idea is the same and the stages differ. A hold point in construction is a stop before work is covered up or made permanent: before concrete is poured over reinforcement, before a trench is backfilled, before a wall is closed over services. The site ITP names the party who must release each one. If you make equipment that is installed on such a site, your factory ITP and the site ITP are two separate plans.

How OdysseyGPT checks hold and witness points on your ITP

ITP Validator (beta) reads the customer's quality specification and your proposed ITP. You can add the purchase-order quality clauses, the standards the specification names and the inspection agency's requirements. It checks every stage for the right intervention level, acceptance criteria, procedure reference and record.

  • One finding per ITP stage or missing stage, with the requirement it was checked against.
  • Gaps sorted by type: missing stage, wrong intervention level, weak or missing acceptance criteria, missing record.
  • A quote from the quality specification, PO clause or ITP for each finding.
  • A CSV or JSON export for your ITP revision log.

Your quality engineer reviews each finding and decides what changes on the plan before it goes to the customer for approval.

See a downgraded hold point caught before the ITP is submitted

Send one order's quality specification and ITP ahead of the call. You will see the stages where the plan and the customer disagree, with both documents quoted side by side.

Request a demo

See it on your own documents

Submit an ITP the customer approves first time

Choose an ITP you are about to send for approval. Bring it and the customer's quality requirements to a demo, and leave with a stage-by-stage list of what to fix.

Request a demo

Frequently asked questions

What is a witness point?

A witness point is a stage on an inspection and test plan that a named party, usually the customer's inspector, has the right to watch. The manufacturer must give notice. If the inspector does not attend after proper notice, the work goes ahead and the record is sent to them afterwards.

What is an inspection hold point?

An inspection hold point is a stage where work must stop until a named party has inspected and signed, or has waived attendance in writing. It is used where the next step would hide the work or make a fault costly to fix, such as before a pressure test, before painting or before final release.

What is the difference between a hold point and a witness point?

The difference is what happens when the inspector is absent. At a hold point the work waits until the inspector attends or gives a written waiver. At a witness point the work continues once the notice period has passed, and the manufacturer records the result and sends it on.

What are hold points in construction?

Hold points in construction are stops before work is covered or made permanent, such as before concrete is poured over reinforcement or before a trench is backfilled. The site inspection and test plan names who must inspect and release each one. The rule is the same as in manufacturing: no release, no next step.

Who decides the hold and witness points?

The customer decides. The points are set in the quality specification, the purchase-order quality clauses and any inspection agency requirements. The manufacturer adds its own internal holds, writes the ITP and submits it for approval. The customer can add or change points before approving the plan.

Can a hold point be waived?

Yes, but only by the party that holds it, and in writing. Keep the waiver with the inspection record for that stage and reference it on the ITP sign-off. A verbal waiver, or silence after a notification, does not release a hold point. Silence only allows work to continue at a witness point.

References

ISO 9001, Quality management systems: Requirements

International Organization for Standardization

ISO 10005, Quality management: Guidelines for quality plans

International Organization for Standardization

API Specification Q1, Quality Management System Requirements for Manufacturing Organizations for the Petroleum and Natural Gas Industry

American Petroleum Institute