What is a third party inspection?
If you are looking for an inspection agency to hire, or for a building inspection programme, this is not that page. This guide is for manufacturers of engineered equipment whose customer has sent, or will send, an independent inspector to the factory.
In a third party inspection, a body that is independent of both buyer and seller checks that the product meets the order. The first party is you, the manufacturer. The second party is your customer. The third party is the inspection agency. Third-party inspection services include witnessing tests, reviewing documents, checking dimensions and markings, and issuing a report or release. The same activity is often called vendor inspection when it is described from the buyer's side.
| Party | Who it is | What their inspection proves |
|---|---|---|
| First party | The manufacturer's own quality department | The manufacturer has checked its own work |
| Second party | The customer's own inspector | The customer has checked the supplier directly |
| Third party | An independent inspection agency or authorised body | Someone with no stake in the sale has checked the product |
Check the evidence before the third-party inspector travels
Bring the documents for one inspection stage: drawings, procedures, material and calibration certificates, welder qualifications and your open NCR list. We run the readiness check and show each blocker with its source.
What the third-party inspector asks for
The inspector's scope comes from the purchase order and the approved inspection and test plan. At each hold or witness point they will usually ask for these documents before they look at the item.
| Document | What the inspector checks | Common reason for rejection |
|---|---|---|
| Purchase order and specification | The revision in force and any agreed deviations | The shop is working to an older revision |
| Approved ITP | The stage, acceptance reference and intervention level | ITP not approved, or the stage was passed without notice |
| Approved drawings | Revision and approval status | Drawing still marked for comment, not approved |
| Procedures | Welding, NDE, heat treatment, test and coating procedures and their approval | Procedure revision used is not the approved one |
| Material certificates | Heat number, grade, certificate type and results against the order | Heat number on the part does not match the certificate |
| Welder and NDE personnel qualifications | Validity on the date of the work | Qualification expired or does not cover the process |
| Calibration certificates | Each instrument used, in date on the test day | Gauge calibration expired before the test |
| Earlier inspection records | Sign-off of the stages before this one | Previous stage not released |
| NCR register | Open nonconformances on the item | An open NCR with no approved disposition |
Third party inspection checklist for the manufacturer
Run this checklist before you send the inspection notice. Every line you cannot tick is a reason the inspector may refuse to sign.
- The ITP is approved and the stage is on it with the right hold or witness code.
- Notice has been sent with the period the order requires, naming the item, stage, date and place.
- The previous stages are signed off, or waivers are on file.
- Drawings and procedures for the stage are at their approved revision.
- Material certificates are on hand for every part in the stage, and the heat numbers match the markings.
- Welder, operator and NDE personnel qualifications are valid on the dates of the work.
- Every instrument to be used has a calibration certificate in date on the inspection day.
- No NCR is open on the item, or each open one has a disposition the customer has approved.
- The item is accessible, clean, identified with its tag and safe to inspect.
- The record form for the stage is prepared, ready for the result and the signatures.
A printable version is in the pre-inspection checklist template.
What gets a third-party inspection rejected
An inspector can reject the item, or decline to carry out the inspection at all. The second is more common than most teams expect, and it costs a visit fee and days of schedule. The usual causes:
- Evidence dated after the work it is meant to support, such as a procedure approved after the weld was made.
- A certificate that expires between the day you checked it and the day of the inspection.
- A mismatch between documents: the tag on the nameplate, the drawing and the test record do not agree.
- A deviation that was agreed by email but never recorded on the deviation list.
- Sub-supplier records that have not arrived.
What a third party inspection certificate is
After a successful visit the inspector issues a record. It may be a visit report, a signed ITP stage, an inspection certificate or an inspection release note that allows shipment. A third party inspection certificate states what was inspected, against which documents, and that it was found to conform, with any open points listed.
Material certificates have their own version. An EN 10204 type 3.2 certificate is validated by the manufacturer's authorised representative and by an independent inspector. See EN 10204 3.1 vs 3.2.
How OdysseyGPT checks you are ready for a third-party inspection
Inspection Readiness Check (beta) runs the document side of the checklist above. You upload the evidence the stage depends on: approved drawings and procedures, material certificates, calibration certificates, welder qualifications and the open NCR register. It requires the previous stage to be released, flags evidence that expires before the planned date and blocks on open NCRs.
- A single readiness verdict for the inspection stage.
- Hard blockers listed separately from advisory items.
- A quote from the document behind each blocker, such as a drawing status or a certificate date.
- A CSV or JSON export for the inspection notice or your QA log.
Your inspection coordinator clears the blockers and decides when the notice goes out.
See which documents would stop your next inspection
Send the evidence for a stage the agency is due to attend. During the call you will see the verdict, the hard blockers and the quoted line in each document, ready to hand to the people who can fix them.
See it on your own documents
Make the inspector's visit a signature, not a list of findings
Bring one upcoming hold point and its documents to a demo. We check the evidence against the planned date and you keep the blocker list.