Source inspection: what it is and how a supplier gets ready

Written for the manufacturer whose customer inspects at the factory before shipment: where source inspection sits among the inspection types, a pre-inspection meeting agenda, and a checklist for the day.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

Source inspection is an inspection of the product at the supplier's factory, by the customer or its representative, before the product ships. This guide is for the supplier being inspected. The inspector checks the item and its records against the purchase order, so getting ready means proving every record is complete before the visit.

Key Takeaways

  • Source inspection happens at your works, before shipment, instead of or as well as the customer's receiving inspection.
  • The pre-inspection meeting sets the rules: which stages, how much notice, which documents.
  • The inspector accepts the item on its records as much as on its condition.
  • OdysseyGPT's Inspection Readiness Check (beta) checks those records before you invite the inspector.

What source inspection is

This guide is for manufacturers of engineered equipment and machined or fabricated parts whose purchase order calls for source inspection. If you are looking for an agency to inspect goods for you, or for a source inspector job, it is written from the other side of the table.

In a source inspection, the customer inspects at the source: your factory. The customer's own quality engineer, a contracted source inspector or a government representative checks the product and its records before it is packed. The reason is cost. A fault found at your works can be fixed there. The same fault found at the customer's goods-in, or on site, means return freight, delay and a formal rejection.

Customer source inspection is common for long-lead and high-value items, for first articles, and for parts that cannot be fully checked once assembled. On defence contracts in the United States, government source inspection is carried out by the Defense Contract Management Agency when the contract requires it.

Check your records before you invite the source inspector

Bring the evidence for one item that is due for source inspection: drawings, certificates, calibration records and the NCR register. We run the readiness check live and show what would stop the visit.

Request a demo

Source inspection and the three types of inspection

Quality textbooks describe three types of inspection by when they happen: incoming, in-process and final. Source inspection is not a fourth type. It is any of those stages carried out by the customer at the supplier's works.

Where source inspection fits
Type of inspectionWhenDone by the supplierAs source inspection by the customer
Incoming (receiving)When material or bought-out parts arriveCertificate review, identification and dimensional checksReview of material certificates before production starts
In-processDuring manufactureChecks at the stages on the ITPWitnessing a weld, a heat treatment chart or a first-off part
FinalBefore packing and shipmentFinal dimensional, visual and functional checks, and record reviewFinal source inspection and release for shipment

When the customer uses an independent agency instead of its own staff, the same visit is a third-party inspection. The preparation is the same.

The pre inspection meeting: what to agree

A pre inspection meeting, often shortened to PIM, is held between the supplier, the customer and the inspector before manufacture or before the first inspection. It turns the quality clauses of the order into working arrangements. Use this agenda.

Pre-inspection meeting agenda
TopicWhat to agreeRecord
ScopeWhich items and which purchase order lines are subject to source inspectionMinutes, referenced to the PO
Governing documentsSpecification, drawing and procedure revisions, and agreed deviationsDocument list with revisions
Inspection stagesEach hold, witness and review point on the ITPApproved ITP
NoticeHow notice is given, to whom, and how many working days aheadNotification procedure
SamplingWhether every piece is inspected or a sample, and how the sample is chosenSampling plan
RecordsWhich records the inspector reviews at each stage, and in what formRecord list
NonconformanceHow a nonconformance is reported and who approves the dispositionNCR procedure
ReleaseWhat document releases the goods for shipmentRelease note format
Sub-suppliersWhich sub-supplier items need inspection at their worksSub-order list

Issue the minutes within a few days and have the customer confirm them. Points agreed in the meeting and never written down are the ones argued about at final inspection.

Source inspection checklist for the supplier

  1. Confirm the purchase order revision and the drawing revision the item was built to.
  2. Complete your own final inspection first, and sign it. The source inspector verifies your inspection; they do not replace it.
  3. Gather the records for the item: material certificates, process records, NDE and test reports, dimensional report.
  4. Check every record carries the right part number, serial or heat number and purchase order number.
  5. Check each measuring instrument used has a calibration certificate valid on the day it was used.
  6. Close every nonconformance on the item, or hold the customer's written approval of the disposition.
  7. Check that agreed deviations are recorded and referenced on the records they affect.
  8. Send the notice with the agreed lead time, and attach the record list.
  9. Set out the item, the drawings, the gauges and a clean place to work.
  10. Prepare the release document for signature.

A worked example. A supplier calls a source inspector to release ten machined valve bodies. The parts measure correctly. The inspector then asks for the material certificates and finds two bodies marked with a heat number that is on no certificate in the pack. The visit ends without release. The parts were right, and the records were not ready.

What the source inspector does on the day

A quality inspector in manufacturing checks that a product meets its drawing and specification: measuring, examining, witnessing tests and reviewing records. A source inspector does the same job on the customer's behalf. A typical visit follows a set order:

  • Opening: confirm the scope, the order revision and any open actions from the last visit.
  • Record review: certificates, process records and your own inspection reports.
  • Product verification: selected dimensions, visual condition, marking and identification.
  • Witnessing: any test the order asks them to see.
  • Closing: findings, any nonconformance, and release or a list of points to clear.

The source inspection report or inspection release note they sign is your proof that the customer accepted the goods before shipment.

How OdysseyGPT checks you are ready for source inspection

Inspection Readiness Check (beta) confirms whether an inspection stage can go ahead. You upload approved drawings and procedures, material certificates, calibration certificates, welder qualifications and the open NCR register. The check requires the previous stage to be released, flags evidence that expires before the planned inspection date and blocks on open NCRs.

  • One readiness verdict for the stage.
  • Hard blockers kept separate from advisory items.
  • A quote from the document behind each blocker.
  • A CSV or JSON export you can attach to the inspection notice or keep in your QA log.

Where the question is whether a heat number links to the right certificate, Material Traceability Check (beta) follows it from tag to certificate. Your team decides what to do with every finding.

Watch the readiness check run on a real inspection stage

Send the record pack for an item awaiting source inspection. You will see the verdict, each blocker and the exact document line behind it, before the inspector's diary is booked.

Request a demo

See it on your own documents

Know the answer before the source inspector asks the question

Choose one item due for inspection this month. Bring its drawings, certificates and NCR register to a demo and leave with a list of what to clear first.

Request a demo

Frequently asked questions

What is source inspection?

Source inspection is an inspection of a product at the supplier's factory, carried out by the customer or its representative before shipment. The inspector checks the item and its records against the purchase order. It lets faults be found and fixed where the product is made, before freight and delivery dates are at stake.

What are the three types of inspection?

The three types are incoming inspection, when materials and bought-out parts arrive; in-process inspection, during manufacture; and final inspection, before packing and shipment. Source inspection is not a fourth type. It is any of these stages carried out by the customer at the supplier's works.

What does a quality inspector do in manufacturing?

A quality inspector checks that parts and assemblies meet the drawing and specification. They measure dimensions, examine surfaces and markings, witness tests, review certificates and records, and report nonconformances. A source inspector does the same work at a supplier's factory on behalf of the customer who placed the order.

What is a pre inspection meeting?

A pre inspection meeting is held between the supplier, the customer and the inspector before manufacture or before the first inspection. It agrees the scope, the document revisions, the hold and witness points, the notice period, the records to be reviewed and the document that will release the goods. The minutes become a reference for every later visit.

What is the difference between source inspection and receiving inspection?

The place and the timing. Source inspection is done at the supplier's factory before shipment. Receiving inspection is done at the customer's premises after delivery. Some orders use both. Where source inspection has released the goods, receiving inspection is often reduced to a check of identity, quantity and transit damage.

References

ISO 9001, Quality management systems: Requirements

International Organization for Standardization

AS9100, Quality Management Systems: Requirements for Aviation, Space and Defense Organizations

SAE International

Federal Acquisition Regulation, Part 46, Quality Assurance

United States General Services Administration