Download the pre-inspection checklist
XLSX
Pre-inspection checklist (Excel)
Header block, 9 columns, drop-downs for category and status, Not ready rows in red, frozen header row, filters and a How to use sheet.
CSV
Pre-inspection checklist (CSV)
The example rows as plain CSV (UTF-8), for Google Sheets or any other tool.
Both files are free under CC BY 4.0, with no form to fill in. The XLSX opens in Excel, Google Sheets, LibreOffice and Numbers. The CSV carries the table only; the header block is in the XLSX.
What it is for and who uses it
The inspection and test plan (ITP) says where the customer or a third-party inspector holds or witnesses the work. Calling an inspector to a point that is not ready costs a visit and often the slot. This checklist is the go/no-go before each notification. For a factory acceptance test, the FAT readiness checklist template covers the same ground with test-specific rows.
- Quality engineers who close earlier ITP steps and NCRs.
- Welding coordinators and NDE coordinators who confirm their records.
- Project managers who send the inspection notification.
Header block
| Field | Example |
|---|---|
| Project | Example Process Skid (fictional) |
| Customer | Example EPC Contractor Ltd (fictional) |
| Purchase order | PO-EX-4410 (fictional) |
| Equipment / package | Pressure vessel and piping spool (fictional) |
| Inspection point | Hydrostatic test of the vessel (ITP-EX-4410 step 14) |
| Intervention | Customer: H (hold). Third party: W (witness) |
| Planned inspection date | 2027-03-16 |
| Notice period the PO requires | 10 working days (PO clause 12) |
| Checklist no. | PIC-EX-4410-14 |
| Date | 2027-02-26 |
| Prepared by | Quality engineer |
| Checked by | Project manager |
Example rows: before a witnessed hydrostatic test
| Item | Category | Check | Required by | Evidence | Status | Remarks |
|---|---|---|---|---|---|---|
| 1 | Documents | Drawings approved by the customer, at the revision the item was built to | VDRL A01 | GA-EX-4410 Rev C, returned code 1 | Ready | |
| 2 | Documents | ITP approved, every earlier step done, and earlier hold points released in writing | ITP-EX-4410 Rev B | ITP-EX-4410 Rev B, steps 1-13 | Not ready | Step 11 (NDE) is open: see item 7. |
| 3 | Procedure | Test procedure approved by the customer, at the revision that will be used | VDRL B02 | TP-EX-07 Rev A, returned code 1 | Ready | |
| 4 | Material | Material certificates for pressure parts reviewed and accepted, with heat numbers traced to the parts | ITP-EX-4410 step 2 | Certificate review checklists MTRC-EX-4410-01 to -06 | Ready | |
| 5 | Welding | Every weld on the weld map has an approved WPS with its supporting PQR on file | WM-EX-4410 Rev A; PO welding code | Cross-check matrix WQX-EX-4410 | Not ready | WPS-EX-015 for weld W3 is not yet approved by the customer. |
| 6 | Welding | Welder qualifications cover the welds made and were current on the weld dates | PO welding code | WQX-EX-4410; welder continuity log WCL-EX-2027 | Not ready | Continuity record for welder WX-09 to be found for weld W2. |
| 7 | NDE | NDE complete and reports accepted for the welds under test, with operator qualifications on file | ITP-EX-4410 step 11 | RT reports RT-EX-041 to RT-EX-046 | Not ready | RT-EX-042 (weld W2) is awaiting review. |
| 8 | Quality | Visual and dimensional inspection before the test complete and recorded | ITP-EX-4410 step 12 | Dimensional report DIM-EX-4410 | Ready | |
| 9 | Calibration | Gauges and recorders calibrated, with certificates valid on the inspection date and ranges that suit the test pressure | TP-EX-07 section 5 | Calibration certificates CAL-0418, CAL-0419 | Ready | Both certificates run past the planned date. Check again if the date moves. |
| 10 | Quality | Open non-conformances on the item closed, or concessions approved by the customer | QP-01 section 10 | NCR log; NCR-EX-131 closed 2027-02-19 | Ready | |
| 11 | Documents | Agreed deviations and concessions reflected in the procedure and in the inspector's pack | PO deviation list | Not applicable | No agreed deviation affects this test. | |
| 12 | Documents | Inspector's pack ready: approved drawings, ITP, procedure, material certificates, weld map, NDE reports, calibration certificates and blank report forms | ITP-EX-4410 | Not ready | ||
| 13 | Notification | Inspection notification sent to the customer and the third party with the notice period the PO requires, naming the ITP step, date, place and contact | PO clause 12 | Not ready | Send only when items 2, 5, 6 and 7 are Ready. | |
| 14 | Logistics | Access, safety induction and PPE arranged for the visitors | Site rules | Visitor booking | Ready |
The file also has columns for owner and due date. Rows 2, 5, 6 and 7 are Not ready, so the notification in row 13 waits for them. Every example value is invented: the project, customer, bidders, purchase order, prices and every document, certificate, serial and report number do not exist. Standards are named but not quoted.
Columns and what to write
| Column | What to write |
|---|---|
| Item | Running number. |
| Category | Documents, Procedure, Material, Welding, NDE, Calibration, Quality, Notification or Logistics (drop-down). |
| Check | What must be true before the inspector is called to this hold or witness point. |
| Required by | The PO clause, specification clause, ITP step or procedure that asks for it. |
| Evidence | The document or record that shows it is done, with number and revision. |
| Status | Ready, Not ready or Not applicable (drop-down). Not ready rows turn red. |
| Owner | Who closes the item. |
| Due | Date it must be closed, before the notification goes out (YYYY-MM-DD). |
| Remarks | What is missing, or anything the inspector should know. |
How to use the template
- Fill in the header block: purchase order, the inspection point and its ITP step, who holds or witnesses it, the planned date and the notice period the PO requires.
- List every condition that must be true before the inspector is called: approved drawings and procedures, earlier ITP steps, material certificates, welding and NDE records, calibration, open NCRs, the inspector's pack and the notification.
- For each row, name the PO clause, specification clause, ITP step or procedure that asks for it, and the evidence that shows it is done.
- Set the status. Not ready rows turn red. Give each one an owner and a due date that falls before the notification must go out.
- Send the inspection notification only when every other row is Ready or Not applicable. Count the notice period from the day the customer receives it, as the PO defines it.
- If the date moves, check the date-dependent rows again: calibration validity, welder qualifications and the notice period.
- Keep the completed checklist with the inspection record. Use one checklist per hold or witness point.
Checking readiness from the documents
In OdysseyGPT's Inspection & Testing module, Inspection Readiness Check (beta) and Calibration Validity Check (beta) read the ITP, procedures, certificates and reports and show what is still missing or out of date before an inspection. Every finding cites the page it came from, and your engineers decide what to do with it. Tools marked beta are open on request, and we onboard each team ourselves.
Want us to run the check for you?
Send your ITP and the customer's quality requirements. We send back what is covered, what is missing and what still needs evidence before the FAT.