Pre-inspection checklist template: what to confirm before you call the inspector (Excel and CSV)

For equipment manufacturers, before a hold or witness point: approved drawings and procedures, material certificates, welding and NDE records, calibration, open NCRs, the inspector's pack and the notification.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

A pre-inspection checklist confirms, before you call the customer's or third-party inspector to a hold or witness point, that the inspection can go ahead: approved drawings and procedures, accepted material certificates, welding and NDE records, valid calibration, no open non-conformances and a notification sent in time. This free Excel template lists those checks with owners and due dates.

Key Takeaways

  • Use one checklist per hold or witness point, and complete it before the notification goes out.
  • Every row names the PO clause, specification clause or ITP step that asks for it, and the evidence.
  • If the inspection date moves, check calibration validity, welder qualifications and the notice period again.
  • The example has 14 checks before a hydrostatic test on an invented vessel order (PO-EX-4410).

Download the pre-inspection checklist

Both files are free under CC BY 4.0, with no form to fill in. The XLSX opens in Excel, Google Sheets, LibreOffice and Numbers. The CSV carries the table only; the header block is in the XLSX.

What it is for and who uses it

The inspection and test plan (ITP) says where the customer or a third-party inspector holds or witnesses the work. Calling an inspector to a point that is not ready costs a visit and often the slot. This checklist is the go/no-go before each notification. For a factory acceptance test, the FAT readiness checklist template covers the same ground with test-specific rows.

  • Quality engineers who close earlier ITP steps and NCRs.
  • Welding coordinators and NDE coordinators who confirm their records.
  • Project managers who send the inspection notification.

Header block

Header block fields, with the invented example values
FieldExample
ProjectExample Process Skid (fictional)
CustomerExample EPC Contractor Ltd (fictional)
Purchase orderPO-EX-4410 (fictional)
Equipment / packagePressure vessel and piping spool (fictional)
Inspection pointHydrostatic test of the vessel (ITP-EX-4410 step 14)
InterventionCustomer: H (hold). Third party: W (witness)
Planned inspection date2027-03-16
Notice period the PO requires10 working days (PO clause 12)
Checklist no.PIC-EX-4410-14
Date2027-02-26
Prepared byQuality engineer
Checked byProject manager

Example rows: before a witnessed hydrostatic test

Invented example rows for PO-EX-4410 (some columns omitted)
ItemCategoryCheckRequired byEvidenceStatusRemarks
1DocumentsDrawings approved by the customer, at the revision the item was built toVDRL A01GA-EX-4410 Rev C, returned code 1Ready
2DocumentsITP approved, every earlier step done, and earlier hold points released in writingITP-EX-4410 Rev BITP-EX-4410 Rev B, steps 1-13Not readyStep 11 (NDE) is open: see item 7.
3ProcedureTest procedure approved by the customer, at the revision that will be usedVDRL B02TP-EX-07 Rev A, returned code 1Ready
4MaterialMaterial certificates for pressure parts reviewed and accepted, with heat numbers traced to the partsITP-EX-4410 step 2Certificate review checklists MTRC-EX-4410-01 to -06Ready
5WeldingEvery weld on the weld map has an approved WPS with its supporting PQR on fileWM-EX-4410 Rev A; PO welding codeCross-check matrix WQX-EX-4410Not readyWPS-EX-015 for weld W3 is not yet approved by the customer.
6WeldingWelder qualifications cover the welds made and were current on the weld datesPO welding codeWQX-EX-4410; welder continuity log WCL-EX-2027Not readyContinuity record for welder WX-09 to be found for weld W2.
7NDENDE complete and reports accepted for the welds under test, with operator qualifications on fileITP-EX-4410 step 11RT reports RT-EX-041 to RT-EX-046Not readyRT-EX-042 (weld W2) is awaiting review.
8QualityVisual and dimensional inspection before the test complete and recordedITP-EX-4410 step 12Dimensional report DIM-EX-4410Ready
9CalibrationGauges and recorders calibrated, with certificates valid on the inspection date and ranges that suit the test pressureTP-EX-07 section 5Calibration certificates CAL-0418, CAL-0419ReadyBoth certificates run past the planned date. Check again if the date moves.
10QualityOpen non-conformances on the item closed, or concessions approved by the customerQP-01 section 10NCR log; NCR-EX-131 closed 2027-02-19Ready
11DocumentsAgreed deviations and concessions reflected in the procedure and in the inspector's packPO deviation listNot applicableNo agreed deviation affects this test.
12DocumentsInspector's pack ready: approved drawings, ITP, procedure, material certificates, weld map, NDE reports, calibration certificates and blank report formsITP-EX-4410Not ready
13NotificationInspection notification sent to the customer and the third party with the notice period the PO requires, naming the ITP step, date, place and contactPO clause 12Not readySend only when items 2, 5, 6 and 7 are Ready.
14LogisticsAccess, safety induction and PPE arranged for the visitorsSite rulesVisitor bookingReady

The file also has columns for owner and due date. Rows 2, 5, 6 and 7 are Not ready, so the notification in row 13 waits for them. Every example value is invented: the project, customer, bidders, purchase order, prices and every document, certificate, serial and report number do not exist. Standards are named but not quoted.

Columns and what to write

ColumnWhat to write
ItemRunning number.
CategoryDocuments, Procedure, Material, Welding, NDE, Calibration, Quality, Notification or Logistics (drop-down).
CheckWhat must be true before the inspector is called to this hold or witness point.
Required byThe PO clause, specification clause, ITP step or procedure that asks for it.
EvidenceThe document or record that shows it is done, with number and revision.
StatusReady, Not ready or Not applicable (drop-down). Not ready rows turn red.
OwnerWho closes the item.
DueDate it must be closed, before the notification goes out (YYYY-MM-DD).
RemarksWhat is missing, or anything the inspector should know.

How to use the template

  1. Fill in the header block: purchase order, the inspection point and its ITP step, who holds or witnesses it, the planned date and the notice period the PO requires.
  2. List every condition that must be true before the inspector is called: approved drawings and procedures, earlier ITP steps, material certificates, welding and NDE records, calibration, open NCRs, the inspector's pack and the notification.
  3. For each row, name the PO clause, specification clause, ITP step or procedure that asks for it, and the evidence that shows it is done.
  4. Set the status. Not ready rows turn red. Give each one an owner and a due date that falls before the notification must go out.
  5. Send the inspection notification only when every other row is Ready or Not applicable. Count the notice period from the day the customer receives it, as the PO defines it.
  6. If the date moves, check the date-dependent rows again: calibration validity, welder qualifications and the notice period.
  7. Keep the completed checklist with the inspection record. Use one checklist per hold or witness point.

Checking readiness from the documents

In OdysseyGPT's Inspection & Testing module, Inspection Readiness Check (beta) and Calibration Validity Check (beta) read the ITP, procedures, certificates and reports and show what is still missing or out of date before an inspection. Every finding cites the page it came from, and your engineers decide what to do with it. Tools marked beta are open on request, and we onboard each team ourselves.

Want us to run the check for you?

Send your ITP and the customer's quality requirements. We send back what is covered, what is missing and what still needs evidence before the FAT.

Get the free ITP and FAT readiness check

New templates by email (optional)

Your download does not depend on this.

We use your email only for this. See our privacy policy.

Frequently asked questions

What is a pre-inspection checklist?

A list of the conditions a manufacturer confirms before calling the customer's or third-party inspector to an inspection: approved documents, completed earlier steps, material, welding and NDE records, calibration, open non-conformances and the notification itself.

What is the difference between a hold point and a witness point?

At a hold point, work does not go on until the named party has attended or released it in writing. At a witness point, the party is notified and may attend; if they do not come after due notice, work may go on. Use the definitions in your purchase order.

How much notice does an inspector need?

The purchase order or the customer's quality requirements set the notice period, and it differs between customers. Enter it in the header and count back from the planned date to find when the notification must go out.

Is there a free pre-inspection checklist template in Excel?

Yes. This XLSX template has a blank checklist, a filled-in example for an invented vessel order and a How to use sheet. A CSV of the same columns is also free under CC BY 4.0.