FAT punch list template: fields, categories and a worked example

A punch list for the factory acceptance test of manufactured equipment: the columns to use, how to split category A from category B, and how to close each item with evidence.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

This punch list template is for the factory acceptance test (FAT) of manufactured equipment, not a building site. Give each item a number, tag, description, category, owner, due date and closing evidence. Category A items close before shipment. Category B items close later, by written agreement with the customer.

Key Takeaways

  • One row per open item, each with an owner, a due date and the evidence that closes it.
  • Agree the category rules with the customer before the test, not during it.
  • Both sides sign the punch list at the end of the FAT. It becomes part of the test record.
  • An item is closed when the customer accepts the evidence, not when the work is done.

What a FAT punch list is

Most punch list pages are written for building sites: rooms, trades and paint. This one is for the factory acceptance test of manufactured equipment, such as a pump skid, a valve package or a pressure vessel. A FAT punch list records every open item found before or during the test: a missing nameplate, a gauge with the wrong range, a drawing that still shows an old revision. Each item gets an owner and a date. The customer's inspector and the manufacturer both sign the list when the test ends.

The punch list is not the same as a nonconformance report. A punch item is unfinished or untidy work that needs no engineering decision. A nonconformance is a failure against a requirement, and it goes through your NCR process. For the test itself, see the factory acceptance test guide and the FAT checklist.

Check your punch list before the inspector does

Bring one FAT procedure, the punch list and the NCR register for a real order. We run the readiness check and show you which open items block the test, with the line each one came from.

Request a demo

Punch list template you can copy

Copy these columns into a spreadsheet. One row is one item. Keep the list as a single file for the order, so nobody works from an old copy.

FAT punch list template: one row per open item
ColumnWhat to writeExample
Item no.A running number that never changesPL-014
Date raisedThe day the item was found12 Nov 2026
Raised byName and companyCustomer inspector
Tag or serialThe equipment the item is onP-101A
DescriptionWhat is wrong, in one plain sentenceDischarge gauge range is 0 to 10 bar, datasheet asks 0 to 25 bar
ReferenceDrawing, datasheet, procedure step or specification clauseDatasheet DS-101 rev C, line 42
CategoryA or B, by the rule agreed with the customerA
ActionWhat will be doneReplace gauge and repeat the reading
OwnerOne named personTest engineer
Due dateA date, or a milestone such as before shipmentBefore shipment
Closing evidencePhoto, record or revised document that proves itPhoto and calibration certificate
Closed by and dateWho accepted the closure, and whenCustomer inspector, 14 Nov 2026

What a punch list typically includes: a worked example

Here is a short punch list from the FAT of a pump skid. It shows the three kinds of item you will meet: the equipment, the test and the documents.

Example punch list from a pump skid FAT (illustrative)
No.DescriptionCategoryActionClosing evidence
PL-001Nameplate shows the wrong purchase order numberAFit corrected nameplatePhoto of the new nameplate
PL-002Vibration reading taken with a probe whose certificate was not in the test packASupply the certificate or repeat the readingCalibration certificate valid on the test date
PL-003Paint damage on the baseplate lifting lugBTouch up after packing trialPhoto and paint record
PL-004General arrangement drawing does not show the relocated drainBRevise the drawing to as-builtRevised drawing, approved
PL-005Two flange bolts are short of full thread engagementAReplace boltsPhoto and bolt certificate

Category A and category B items

Most projects split punch items into two groups. The names vary, and the rule comes from the customer or the contract, so agree it in the FAT procedure before the test day.

  • Category A: items that must close before a milestone, usually release for shipment. They affect safety, function, the test result or a contract requirement.
  • Category B: items that can close later, by a date both sides agree in writing. They are cosmetic or documentary and do not change how the equipment works.
  • No category: an item that turns out to be a failure against a requirement moves to a nonconformance report and leaves the punch list.

How to run the punch list on the FAT day

  1. Walk the equipment yourself a few days before the test, and raise your own items first.
  2. Bring the list to the opening meeting, with the items you have already closed.
  3. Give one person the pen. Every item raised during the test goes on the same list, at once.
  4. Write each item so a stranger could find it: tag, location, reference.
  5. Agree the category of each item before the closing meeting ends.
  6. Have the customer's inspector and your test lead sign and date the list.
  7. Attach the signed list to the FAT report, and carry open items into the inspection release note.

Closing punch items with evidence

An item is closed when the person who raised it accepts the evidence. Send the photo, record or revised drawing with the item number on it. Keep the closed list, because the customer will ask for it in the manufacturing record book. Open category B items that ship with the equipment should be listed on the release note, so the site team knows what is still to come.

How OdysseyGPT checks the punch list before a FAT

The FAT Readiness Check (beta) reads the documents a test depends on and tells you if the test is ready to run. You upload the FAT procedure. You can add the punch list, the NCR register, the ITP, approved drawings, datasheets and calibration certificates. PDF, Word, Excel and CSV files all work, so a punch list kept in a spreadsheet goes in as it is.

  • A readiness verdict for the test.
  • Hard blockers, such as an open NCR on the equipment or an expired test instrument, listed apart from review items such as a minor punch item.
  • A quote from the procedure, register or certificate behind every finding.
  • A CSV or JSON export for your FAT preparation tracker.

Your test and quality engineers decide what to do with each finding. Run it before the first FAT, and again before a re-test, when the punch list is the main thing standing between you and shipment.

See a readiness verdict for your next FAT

Send us the procedure and registers for a test you have coming up. On the call you will see the blockers and review items for that test, each quoted from your own documents.

Request a demo

See it on your own documents

Walk into the FAT with a short punch list

Pick one order with a witnessed test ahead. We check its procedure, punch list, NCRs and calibration evidence in front of you, and you keep the export.

Request a demo

Frequently asked questions

What does a punch list typically include?

A punch list typically includes an item number, the date raised, who raised it, the equipment tag, a one-sentence description, a reference to the drawing or requirement, a category, the action, an owner, a due date and the evidence that closes the item. On a FAT it also carries the signatures of the customer's inspector and the manufacturer.

What is another word for punch list?

Other names are snag list or snagging list, which are common in the UK, plus deficiency list, open items list and outstanding works list. On equipment orders you will also see FAT punch list or exception list. They all mean the same thing: a signed list of open items, each with an owner and a date.

Can you provide me with a free checklist format template for Excel?

Yes. Copy the twelve columns in the template table on this page into Excel, one column each, and add a filter on category and status. That gives you a working punch list for a factory acceptance test. Freeze the header row and keep one file per order so every party works from the same list.

How do you prepare a punch list template?

Start from the FAT procedure and the contract. Write down the category rule the customer uses, then build one row per item with a number, tag, description, reference, category, action, owner, due date and closing evidence. Add signature boxes for both parties. Agree the format with the customer before the test day, so nobody argues about it afterwards.

Can equipment ship with open punch list items?

Often yes, if the open items are category B and the customer agrees in writing. Category A items normally have to close before the customer releases the equipment for shipment. The rule comes from the contract and the FAT procedure, so check both. List any open items on the release note that travels with the equipment.

References

IEC 62381: Automation systems in the process industry. Factory acceptance test (FAT), site acceptance test (SAT) and site integration test (SIT)

IEC

ISO 9001:2015 Quality management systems. Requirements

ISO