What are the ISA-20 specification forms?
ISA-20 is the common name for ISA-20-1981, Specification Forms for Process Measurement and Control Instruments, Primary Elements, and Control Valves. It is a collection of blank forms. Each form covers one type of device, such as a pressure instrument, a temperature instrument or a control valve, and gives numbered lines for the details a buyer and a supplier need to agree.
The ISA20 committee states its aim as promoting uniformity of instrument specifications, in both content and form. ISA lists the benefits of using the forms: they help the engineer prepare a complete specification, they promote uniform terminology, they make quoting, purchasing, receiving and ordering easier, and they give a permanent record of what was installed.
The forms do not set technical requirements. A form has a line for accuracy; it does not say what the accuracy must be. The requirement comes from what the engineer writes on the line, and from the project specification behind it.
ISA-20-1981 and ISA-TR20.00.01
| Document | What it is | What to know |
|---|---|---|
| ISA-20-1981 | The original set of short-form specifications, which its own scope calls check sheets | Standards resellers list it as withdrawn. The forms are still in wide use, and ISA still sells them in spreadsheet format |
| ISA-TR20.00.01 | A technical report, Specification Forms for Process Measurement and Control Instruments, Part 1: General Considerations, with a much larger set of forms | First issued in 2001 and extended with new forms in later updates. ISA also publishes picklists of standard entries for the forms |
Catalogue descriptions say the technical report's forms go beyond the limits of the 1981 sheets, and that further forms were added in later updates. Check ISA's catalogue for the current issue before you cite a year.
In practice you will meet three things in an enquiry: a true ISA form, an owner or contractor template that follows the ISA layout, and an export from an instrument database. All three do the same job. When a tender says "ISA datasheet", confirm which form set and which revision the customer means only if you are asked to return your data on it.
What an instrument datasheet holds
| Block | Typical entries | Who fills it in |
|---|---|---|
| Identification | Tag number, service description, P&ID and line or equipment reference, quantity | Buyer |
| Process conditions | Fluid, state, pressure, temperature and flow at minimum, normal and maximum, density and viscosity | Buyer |
| Measurement | Range, calibrated span, accuracy, response time | Buyer, confirmed by supplier |
| Output and power | Signal type, communication protocol, supply voltage | Buyer, confirmed by supplier |
| Construction | Process connection, wetted materials, housing material, ingress protection | Buyer states needs; supplier states what is offered |
| Area and approvals | Hazardous area classification, protection concept, certification scheme, any SIL requirement | Buyer |
| Options and accessories | Manifolds, seals, displays, mounting hardware, tagging | Either |
| Purchase data | Manufacturer, model code, notes and revision history | Supplier |
Tag numbers on datasheets normally follow the identification rules of ANSI/ISA-5.1, the ISA standard for instrumentation symbols and identification. The tag is the key that ties the datasheet to the instrument index and to the P&ID. See instrument datasheet and instrument index for both terms.
How instrument datasheets are used in a tender
- The buyer issues a requisition with an instrument index or tag list, a datasheet for each tag or group of tags, and the project instrument specification.
- The supplier selects a model for each tag and completes the supplier lines of each datasheet, or returns its own datasheet beside the buyer's.
- The supplier checks each datasheet against the specification and lists what it cannot meet as deviations and what is unclear as clarifications.
- The buyer compares the returned datasheets across bidders in a technical bid evaluation.
- After the order, the agreed datasheet becomes a controlled document. It is revised when anything changes and is checked again at inspection and at handover.
The datasheet and the specification often disagree. The datasheet may show one wetted material and the specification another, or the specification may require a certification scheme the datasheet does not mention. The order of precedence in the enquiry says which wins. If it does not, ask. Do not pick the cheaper reading and stay silent.
What to check on an instrument datasheet in a tender
| Check | Why it matters |
|---|---|
| Every tag in the index has a datasheet, and every datasheet has a tag in the index | A missing sheet is an unpriced instrument |
| Datasheet revision matches the revision listed in the requisition | Quoting to a superseded sheet is a common cause of rework |
| Process conditions are complete at minimum, normal and maximum | A blank maximum pressure or temperature cannot be sized against |
| Units are stated and consistent across sheets | Gauge and absolute pressure are easily confused |
| Range, span and accuracy against the specification's general requirements | The specification may be tighter than the sheet |
| Wetted materials against the fluid and any sour-service clause | Material changes alter the model code and the certificates |
| Hazardous area classification, protection concept and certification scheme | The certificate must match the scheme the site accepts |
| SIL requirement, if the tag is part of a safety function | Evidence and a safety manual will be requested; see IEC 61508 and IEC 61511 |
| Signal and protocol version | A protocol mismatch is found late, at integration |
| Calibration and certificate requirements for each tag | Certificates per instrument add cost and lead time |
| Notes at the foot of the sheet | Notes often carry the requirements that differ from the standard form |
Datasheet Comparison (beta) checks the buyer's datasheet against yours field by field and lists each material difference with the cell it came from. Document Review checks your datasheets against the written requirements in the project specification and quotes the clause for each finding. OdysseyGPT reads datasheets as text and tables. It does not read P&IDs or loop drawings, and it does not select or size instruments.
Talk through your tender review