Download the wind tower section ITP
XLSX
Wind tower section ITP (Excel)
Header block, 12 columns including Applies to and an OEM column, drop-downs for intervention codes and status, NCR rows in red, frozen header row, filters and a How to use sheet.
CSV
Wind tower section ITP (CSV)
The example rows as plain CSV (UTF-8), for Google Sheets or any other tool.
Both files are free under CC BY 4.0, with no form to fill in. The XLSX opens in Excel, Google Sheets, LibreOffice and Numbers. The CSV carries the table only; the header block is in the XLSX.
One plan per section, agreed with the OEM
Tower sections are built in series, but each one ships with its own dossier and each is released by the turbine OEM. The OEM's tower specification, written within the framework of the IEC 61400 series and the fabrication standards it lists, says what must be inspected and how flat, round and straight the result has to be. An inspection and test plan turns that specification into a sequence a shop can follow. Prepare it for the first section of a project, have the OEM approve it, then copy it for every section that follows and fill in the record numbers as you go.
- Quality engineers at tower fabricators, who write the plan and keep it current.
- The OEM's supplier quality inspectors, who choose their hold and witness points.
- Third-party inspectors appointed by the OEM or the project owner.
The steps differ from other fabrication plans. Compared with the structural steel ITP template, there is no piece-marking or trial assembly, and there are steps for can rolling, flange flatness and each coating layer. NDE methods, their extent and all tolerances come from the OEM specification. Check the governing standard or contract. See also wind tower fabricators.
Header block
| Field | Example |
|---|---|
| Project | Example Onshore Wind Farm (fictional) |
| Customer (turbine OEM) | Example Wind Turbine OEM Ltd (fictional) |
| Purchase order | PO-EX-9640 (fictional) |
| Tower and section | Tower EX-WT-014, section T2 (middle section) (fictional) |
| OEM tower specification | TS-EX-TWR-01 Rev 4 (invented) |
| Fabrication, welding and coating standards | As listed in the OEM specification, with their editions |
| Third party | As the contract requires (fictional) |
| ITP no. | ITP-EX-9640-T2 |
| Revision | A |
| Date | 2027-03-08 |
| Prepared by | Quality engineer |
| Approved by (OEM) |
Example operations: a middle tower section
| Seq. | Operation and what is checked | Applies to | Reference document | Acceptance criteria reference | Record produced | Fabricator | OEM | Third party | Remarks |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Welding, NDE and coating procedures and this plan approved by the OEM | Whole section | Document list DL-EX-9640 | Per OEM specification | Approved procedures; approved ITP | H | H | R | |
| 2 | Plate receipt: grade, thickness and heat number against the order and the inspection certificate; plate testing where the specification asks for it | Each plate | TS-EX-TWR-01 section 3; goods-in procedure QP-EX-03 | Per OEM specification | Goods-in record; certificate review | H | R | R | |
| 3 | Flange receipt: forged ring flanges with certificates, heat treatment record and the flange maker's dimensional report | Both flanges | TS-EX-TWR-01 section 4; flange drawing FL-EX-T2 | Per OEM specification | Flange receipt record | H | R | R | Do not machine or weld a flange whose certificate is still in query. |
| 4 | Traceability: heat numbers transferred to each plate before cutting and entered on the can map | Each plate | Traceability procedure QP-EX-05 | Per OEM specification and QP-EX-05 | Can map with heat numbers | H | - | M | |
| 5 | Cutting and bevelling: plate size, diagonals and bevel geometry | Each plate | Cutting plan CP-EX-T2; WPS | Per approved drawing and WPS | Cutting and bevel record | H | - | - | |
| 6 | Can rolling: diameter, roundness and the shape at the longitudinal joint before welding | Each can | Rolling instruction RI-EX-02 | Per OEM specification | Can rolling record | H | M | - | |
| 7 | Longitudinal seam welding: procedure, welder or operator, consumable batch and preheat where the procedure gives one | Each longitudinal seam | WPS-EX-41; welding plan WP-EX-T2 | Per OEM specification and approved WPS | Welding record | H | M | M | |
| 8 | Can-to-can fit-up: offset between cans, gap, and the position of the longitudinal seams as the drawing shows it | Each circumferential joint | Section drawing TD-EX-T2 Rev C | Per OEM specification | Fit-up record | H | W | M | |
| 9 | Circumferential welding: procedure, welder or operator, consumable batch and welding sequence | Each circumferential seam | WPS-EX-42; WP-EX-T2 | Per OEM specification and approved WPS | Welding record | H | M | M | |
| 10 | Flange fit-up and welding: flange orientation marks, fit-up and the welding sequence used to limit flange distortion | Both flanges | WPS-EX-43; flange welding instruction FI-EX-01 | Per OEM specification | Flange fit-up and welding record | H | W | W | The OEM asks for notice before each flange is welded. |
| 11 | Visual inspection of finished welds | Every weld | Visual inspection procedure VT-EX-01 | Per OEM specification | Visual inspection report | H | R | W | |
| 12 | NDE of welds, by the methods and to the extent the specification states | As the OEM specification states | NDE procedures UT-EX-02 and MT-EX-03 | Per OEM specification | NDE reports | H | R | R | Methods, extent and any waiting time after welding come from the OEM specification and the standards it names. |
| 13 | Dimensional survey: section length, diameters and straightness; flange flatness, flange tilt and bolt hole pattern | Whole section; both flanges | Survey procedure DM-EX-04; TD-EX-T2 Rev C | Per OEM specification | Dimensional report; flange flatness report | H | H | W | Measure the flanges after all welding on them is finished. The limits are in the OEM specification. |
| 14 | Internals welding: brackets and bosses for platforms, ladder and cable supports, with inspection of the attachment welds | Every attachment on the drawing | Internals drawing TI-EX-T2; WPS-EX-44 | Per OEM specification | Internals checklist; weld inspection report | H | M | - | No welding on the shell after coating without the OEM's written agreement. |
| 15 | Blasting: surface cleanliness and profile, and the ambient conditions at the time | Inside and outside surfaces | Coating procedure CT-EX-02 | Per OEM coating specification | Surface preparation record | H | W | - | |
| 16 | Coating: thickness of each layer, the interval before the next layer, final thickness and appearance; flange faces treated as specified | Each layer | Coating procedure CT-EX-02 | Per OEM coating specification | Coating inspection report | H | W | M | One line per layer in the report. |
| 17 | Final inspection: marking, internals fitted, flange protection, transport supports and damage | Whole section | Final inspection checklist FC-EX-06 | Per OEM specification | Final inspection report | H | H | W | |
| 18 | Section dossier checked against the OEM's document list and released | Every record above | Dossier index SD-EX-9640-T2 | Per OEM document requirements | Release note; section dossier | H | H | R | The section does not leave the works before the OEM signs the release note. |
Record number and status columns are in the file and left out here. The intervention letters are an illustration for an invented OEM; yours come from the contract. Every acceptance cell reads "per OEM specification" or names a procedure, and none holds a tolerance. Every example value is invented: the project, customer, bidders, purchase order, prices and every document, certificate, serial and report number do not exist. Standards are named but not quoted.
Intervention codes
| Code | Common meaning |
|---|---|
| H (hold) | The section stays where it is until the party has inspected the step or released it in writing. |
| W (witness) | The party gets notice of the step and may attend. With notice given and nobody present, the fabricator goes on. |
| R (review) | The party reads the record afterwards. No attendance. |
| M (monitor) | The party may watch the work on any visit, with no notice required. |
| - | The party has no role at this step. |
OEMs often issue their own inspection legend with the supplier quality manual. If yours does, replace this table with it.
Columns and what to write
| Column | What to write |
|---|---|
| Seq. | Sequence number, in the order the section is built. |
| Operation and what is checked | The fabrication operation and the points inspected at it. |
| Applies to | Each plate, each can, each seam, both flanges or the whole section. |
| Reference document | The drawing, procedure or clause of the OEM specification the operation is done to. |
| Acceptance criteria reference | Where the limits are written, normally the OEM specification or a procedure the OEM approved. Name the document. The tolerance values stay in it. |
| Record produced | The report, chart or checklist the operation leaves for the section dossier. |
| Fabricator | Fabricator's intervention: H, W, R, M or - (drop-down). |
| OEM | The turbine OEM's intervention: H, W, R, M or - (drop-down). |
| Third party | Third-party inspector's intervention: H, W, R, M or - (drop-down). |
| Record no. | The record's number, entered when the operation is finished. |
| Status | Not started, Notified, Done, Released or NCR raised (drop-down). NCR rows turn red. |
| Remarks | Notice the OEM needs, what the step depends on, or what is still open. |
How to prepare the plan
- Fill in the header block: the tower and section, the OEM's tower specification with its revision, and the standards it lists.
- Read the OEM specification section by section and check that each inspection it asks for has a step. Add steps for anything missing, such as a door frame on a bottom section, and delete steps the specification does not ask for.
- Name the reference document for each step and where the acceptance criteria are written. Leave the tolerances in the OEM specification; the plan points to them.
- Fill in Applies to, so it is clear whether a step is done once per plate, per can, per seam, per flange or once for the section.
- Agree the H, W, R and M points with the OEM and with any third party. Use the OEM's own legend if the contract gives one.
- Get the plan approved before the first plate is cut. A hold point needs a written release before the section moves on.
- Enter each record number as the operation finishes and update the status. A step with an NCR raised turns red.
- Before the section ships, filter Status for anything not Done or Released, close it, and file the plan in the section dossier.
Testing the plan against the OEM specification
An OEM tower specification can run to a hundred pages, with inspection duties in the welding chapter, the coating chapter and several annexes. In OdysseyGPT's Inspection & Testing module, ITP Validator (beta) reads that specification alongside your plan and names the inspections the plan has no step for, giving the page each one comes from. NDE Coverage Review (beta) checks the planned and reported examinations against the seams the specification says must be examined. What goes into the plan is still the quality engineer's call. Tools marked beta are open on request, and we onboard each team ourselves.
Want us to run the check for you?
Send your ITP and the customer's quality requirements. We send back what is covered, what is missing and what still needs evidence before the FAT.