The short answer

A wind tower section ITP lists every inspection on one tower section: plate and flange receipt, cutting, can rolling, longitudinal and circumferential welding, flange welding, NDE, the dimensional and flange flatness survey, internals, blasting, coating and the dossier. This free Excel template gives each operation a reference document, record and H, W, R or M codes.

Key Takeaways

  • The OEM's tower specification is the source of every tolerance. The plan names the clause and leaves the figure there.
  • Survey the flanges only after all welding on them is finished.
  • The Applies to column shows whether a step is done per plate, per can, per seam or once for the section.
  • The example has 18 operations for an invented middle section (PO-EX-9640).

Download the wind tower section ITP

Both files are free under CC BY 4.0, with no form to fill in. The XLSX opens in Excel, Google Sheets, LibreOffice and Numbers. The CSV carries the table only; the header block is in the XLSX.

One plan per section, agreed with the OEM

Tower sections are built in series, but each one ships with its own dossier and each is released by the turbine OEM. The OEM's tower specification, written within the framework of the IEC 61400 series and the fabrication standards it lists, says what must be inspected and how flat, round and straight the result has to be. An inspection and test plan turns that specification into a sequence a shop can follow. Prepare it for the first section of a project, have the OEM approve it, then copy it for every section that follows and fill in the record numbers as you go.

  • Quality engineers at tower fabricators, who write the plan and keep it current.
  • The OEM's supplier quality inspectors, who choose their hold and witness points.
  • Third-party inspectors appointed by the OEM or the project owner.

The steps differ from other fabrication plans. Compared with the structural steel ITP template, there is no piece-marking or trial assembly, and there are steps for can rolling, flange flatness and each coating layer. NDE methods, their extent and all tolerances come from the OEM specification. Check the governing standard or contract. See also wind tower fabricators.

Header block

Header block fields, with the invented example values
FieldExample
ProjectExample Onshore Wind Farm (fictional)
Customer (turbine OEM)Example Wind Turbine OEM Ltd (fictional)
Purchase orderPO-EX-9640 (fictional)
Tower and sectionTower EX-WT-014, section T2 (middle section) (fictional)
OEM tower specificationTS-EX-TWR-01 Rev 4 (invented)
Fabrication, welding and coating standardsAs listed in the OEM specification, with their editions
Third partyAs the contract requires (fictional)
ITP no.ITP-EX-9640-T2
RevisionA
Date2027-03-08
Prepared byQuality engineer
Approved by (OEM)

Example operations: a middle tower section

Invented example operations for PO-EX-9640, section T2 (some columns omitted)
Seq.Operation and what is checkedApplies toReference documentAcceptance criteria referenceRecord producedFabricatorOEMThird partyRemarks
1Welding, NDE and coating procedures and this plan approved by the OEMWhole sectionDocument list DL-EX-9640Per OEM specificationApproved procedures; approved ITPHHR
2Plate receipt: grade, thickness and heat number against the order and the inspection certificate; plate testing where the specification asks for itEach plateTS-EX-TWR-01 section 3; goods-in procedure QP-EX-03Per OEM specificationGoods-in record; certificate reviewHRR
3Flange receipt: forged ring flanges with certificates, heat treatment record and the flange maker's dimensional reportBoth flangesTS-EX-TWR-01 section 4; flange drawing FL-EX-T2Per OEM specificationFlange receipt recordHRRDo not machine or weld a flange whose certificate is still in query.
4Traceability: heat numbers transferred to each plate before cutting and entered on the can mapEach plateTraceability procedure QP-EX-05Per OEM specification and QP-EX-05Can map with heat numbersH-M
5Cutting and bevelling: plate size, diagonals and bevel geometryEach plateCutting plan CP-EX-T2; WPSPer approved drawing and WPSCutting and bevel recordH--
6Can rolling: diameter, roundness and the shape at the longitudinal joint before weldingEach canRolling instruction RI-EX-02Per OEM specificationCan rolling recordHM-
7Longitudinal seam welding: procedure, welder or operator, consumable batch and preheat where the procedure gives oneEach longitudinal seamWPS-EX-41; welding plan WP-EX-T2Per OEM specification and approved WPSWelding recordHMM
8Can-to-can fit-up: offset between cans, gap, and the position of the longitudinal seams as the drawing shows itEach circumferential jointSection drawing TD-EX-T2 Rev CPer OEM specificationFit-up recordHWM
9Circumferential welding: procedure, welder or operator, consumable batch and welding sequenceEach circumferential seamWPS-EX-42; WP-EX-T2Per OEM specification and approved WPSWelding recordHMM
10Flange fit-up and welding: flange orientation marks, fit-up and the welding sequence used to limit flange distortionBoth flangesWPS-EX-43; flange welding instruction FI-EX-01Per OEM specificationFlange fit-up and welding recordHWWThe OEM asks for notice before each flange is welded.
11Visual inspection of finished weldsEvery weldVisual inspection procedure VT-EX-01Per OEM specificationVisual inspection reportHRW
12NDE of welds, by the methods and to the extent the specification statesAs the OEM specification statesNDE procedures UT-EX-02 and MT-EX-03Per OEM specificationNDE reportsHRRMethods, extent and any waiting time after welding come from the OEM specification and the standards it names.
13Dimensional survey: section length, diameters and straightness; flange flatness, flange tilt and bolt hole patternWhole section; both flangesSurvey procedure DM-EX-04; TD-EX-T2 Rev CPer OEM specificationDimensional report; flange flatness reportHHWMeasure the flanges after all welding on them is finished. The limits are in the OEM specification.
14Internals welding: brackets and bosses for platforms, ladder and cable supports, with inspection of the attachment weldsEvery attachment on the drawingInternals drawing TI-EX-T2; WPS-EX-44Per OEM specificationInternals checklist; weld inspection reportHM-No welding on the shell after coating without the OEM's written agreement.
15Blasting: surface cleanliness and profile, and the ambient conditions at the timeInside and outside surfacesCoating procedure CT-EX-02Per OEM coating specificationSurface preparation recordHW-
16Coating: thickness of each layer, the interval before the next layer, final thickness and appearance; flange faces treated as specifiedEach layerCoating procedure CT-EX-02Per OEM coating specificationCoating inspection reportHWMOne line per layer in the report.
17Final inspection: marking, internals fitted, flange protection, transport supports and damageWhole sectionFinal inspection checklist FC-EX-06Per OEM specificationFinal inspection reportHHW
18Section dossier checked against the OEM's document list and releasedEvery record aboveDossier index SD-EX-9640-T2Per OEM document requirementsRelease note; section dossierHHRThe section does not leave the works before the OEM signs the release note.

Record number and status columns are in the file and left out here. The intervention letters are an illustration for an invented OEM; yours come from the contract. Every acceptance cell reads "per OEM specification" or names a procedure, and none holds a tolerance. Every example value is invented: the project, customer, bidders, purchase order, prices and every document, certificate, serial and report number do not exist. Standards are named but not quoted.

Intervention codes

CodeCommon meaning
H (hold)The section stays where it is until the party has inspected the step or released it in writing.
W (witness)The party gets notice of the step and may attend. With notice given and nobody present, the fabricator goes on.
R (review)The party reads the record afterwards. No attendance.
M (monitor)The party may watch the work on any visit, with no notice required.
-The party has no role at this step.

OEMs often issue their own inspection legend with the supplier quality manual. If yours does, replace this table with it.

Columns and what to write

ColumnWhat to write
Seq.Sequence number, in the order the section is built.
Operation and what is checkedThe fabrication operation and the points inspected at it.
Applies toEach plate, each can, each seam, both flanges or the whole section.
Reference documentThe drawing, procedure or clause of the OEM specification the operation is done to.
Acceptance criteria referenceWhere the limits are written, normally the OEM specification or a procedure the OEM approved. Name the document. The tolerance values stay in it.
Record producedThe report, chart or checklist the operation leaves for the section dossier.
FabricatorFabricator's intervention: H, W, R, M or - (drop-down).
OEMThe turbine OEM's intervention: H, W, R, M or - (drop-down).
Third partyThird-party inspector's intervention: H, W, R, M or - (drop-down).
Record no.The record's number, entered when the operation is finished.
StatusNot started, Notified, Done, Released or NCR raised (drop-down). NCR rows turn red.
RemarksNotice the OEM needs, what the step depends on, or what is still open.

How to prepare the plan

  1. Fill in the header block: the tower and section, the OEM's tower specification with its revision, and the standards it lists.
  2. Read the OEM specification section by section and check that each inspection it asks for has a step. Add steps for anything missing, such as a door frame on a bottom section, and delete steps the specification does not ask for.
  3. Name the reference document for each step and where the acceptance criteria are written. Leave the tolerances in the OEM specification; the plan points to them.
  4. Fill in Applies to, so it is clear whether a step is done once per plate, per can, per seam, per flange or once for the section.
  5. Agree the H, W, R and M points with the OEM and with any third party. Use the OEM's own legend if the contract gives one.
  6. Get the plan approved before the first plate is cut. A hold point needs a written release before the section moves on.
  7. Enter each record number as the operation finishes and update the status. A step with an NCR raised turns red.
  8. Before the section ships, filter Status for anything not Done or Released, close it, and file the plan in the section dossier.

Testing the plan against the OEM specification

An OEM tower specification can run to a hundred pages, with inspection duties in the welding chapter, the coating chapter and several annexes. In OdysseyGPT's Inspection & Testing module, ITP Validator (beta) reads that specification alongside your plan and names the inspections the plan has no step for, giving the page each one comes from. NDE Coverage Review (beta) checks the planned and reported examinations against the seams the specification says must be examined. What goes into the plan is still the quality engineer's call. Tools marked beta are open on request, and we onboard each team ourselves.

Want us to run the check for you?

Send your ITP and the customer's quality requirements. We send back what is covered, what is missing and what still needs evidence before the FAT.

Get the free ITP and FAT readiness check

New templates by email (optional)

Your download does not depend on this.

We use your email only for this. See our privacy policy.

Frequently asked questions

What does a wind tower ITP cover?

Every inspection between steel arriving and the section leaving: incoming plate and flanges, cutting, rolling, the seams, flange welding, weld examination, the dimensional survey, internals, surface treatment and the final document check.

Why is flange flatness its own check?

The flanges are the bolted joints between sections, and the OEM sets limits on how flat and how tilted they may be after welding. Welding heat moves them, which is why the survey comes after the last weld on the flange. The limits are in the OEM specification.

Who decides the hold and witness points?

The OEM, in its specification or supplier quality manual, with the fabricator proposing and the OEM approving. A project owner or certifier may add a third-party inspector with points of its own.

Does the plan say how much NDE to do?

No. The template leaves methods and extent to the OEM specification and the standards it lists, and tells you to cite the clause. Check the governing standard or contract.

Can one plan cover a whole tower?

It can, but a plan per section is easier to close. Each section has its own plates, flanges, records and release note, and a bottom section has extra steps such as the door frame.

References