Requirements traceability matrix (RTM) template for equipment suppliers (Excel and CSV)

Link each customer requirement to the design document that meets it, the check that verifies it and the record that proves it. Free XLSX and CSV with a filled-in valve example.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

A requirements traceability matrix (RTM) links each requirement to the design, test and document that proves it was met. This free Excel template has columns for requirement ID, source clause, design reference, verification method, evidence and status. Equipment suppliers use it when a tender or programme asks for traceability beyond a compliance matrix.

Key Takeaways

  • Each row is one requirement with an ID that never changes.
  • Columns run requirement → design reference → verification method → evidence → status.
  • Agreed deviations are recorded on the row, so you verify what was agreed, not the original wording.
  • The example has 8 rows for an invented valve order, including a failed check and a concession.

Download the RTM template

Both files are free under CC BY 4.0, with no form to fill in. The CSV carries the table only; the header block is in the XLSX.

What a requirements traceability matrix is

An RTM comes from systems and software engineering. Each row is one requirement. Forward traceability follows it to the design that meets it and the check that verifies it. Backward traceability follows any design item or test back to the requirement it serves. For the definition and the difference from a bid compliance matrix, see the requirements traceability matrix glossary entry.

RTM or compliance matrix?

Compliance matrixRequirements traceability matrix
WhenAt bid stage, sent with the offerAfter award, kept during design, build and test
QuestionDoes the offer meet each requirement?Was each requirement designed, verified and recorded?
ColumnsRequirement, offered, status, evidenceRequirement, design reference, verification method, evidence, status
TemplateCompliance matrix templateThis template

A good compliance matrix is the natural first column of an RTM: the same requirement rows, carried forward after award. See compliance matrix vs traceability matrix.

Example rows: ball valve order PO-EX-3105

Invented example rows (some columns omitted)
Req IDSourceRequirementAgreed deviationDesign referenceMethodVerification referenceEvidenceStatus
R-001PS-VAL-001 Rev 2, 3.1Valves shall be designed, manufactured and tested to API 6D.GA-BV-0600 Rev B; DS-BV-0600 Rev BReviewITP-BV-01 step 1 (design review)GA-BV-0600 Rev B returned code 1Verified
R-002PS-VAL-001 Rev 2, 3.4The design minimum temperature shall be −46 °C.EX-01 (clarified)DS-BV-0600 Rev B line 9ReviewITP-BV-01 step 1TQ-EX-007 answer: −46 °C governsVerified
R-003PS-VAL-001 Rev 2, 4.2Body and closures shall be forged ASTM A350 LF2 Class 1.BOM-BV-0600 Rev A items 1–3InspectionITP-BV-01 step 3 (material certificate review)MTR set MTR-BV-SET, heats H-1001 to H-1004In progress
R-004PS-VAL-001 Rev 2, 4.5Seat inserts shall be PEEK.EX-03 (accepted: RPTFE)DS-BV-0600 Rev B line 18InspectionITP-BV-01 step 5 (assembly check)Concession
R-005PS-VAL-001 Rev 2, 7.2Pressure-containing parts shall have EN 10204 type 3.2 certificates.QP-01 Rev CInspectionITP-BV-01 step 3Planned
R-006PS-VAL-001 Rev 2, 9.4Valves shall be pressure tested (shell and seat).EX-08 (accepted: API 6D tests)TP-BV-02 Rev ATestITP-BV-01 step 8 (witness point)Planned
R-007PS-VAL-001 Rev 2, 10.2Gear operators shall be sized for 1.5 times maximum breakaway torque.Torque calculation TQ-BV-06 Rev BAnalysisITP-BV-01 step 2TQ-BV-06 Rev B returned code 3Failed
R-008MR-VAL-001 Rev 1, 7.1Vendor documents shall be submitted as listed in the VDRL.Vendor document register VDR-EX-3105ReviewMonthly register reviewVDR-EX-3105 Rev CIn progress

The file also has Type, Owner and Remarks columns. Row R-004 shows an accepted deviation verified as a concession; R-007 shows a calculation returned for resubmission. Every example value is invented: the project, customer, purchase order PO-EX-3105, specification PS-VAL-001 and every document, transmittal and report number do not exist. Standards are named but not quoted.

Columns and what to write

ColumnWhat to write
Req IDA unique ID that never changes, even if the clause is renumbered.
Source documentThe document the requirement comes from, with revision.
ClauseClause, datasheet line or PO item.
RequirementThe requirement in the source's words, or a short faithful summary for long clauses.
TypeMandatory (shall), Advisory (should) or Information (drop-down).
Agreed deviationThe agreed deviation or concession that changes this requirement, if any.
Design referenceThe drawing, datasheet, calculation or procedure that meets the requirement.
Verification methodTest, Inspection, Analysis, Demonstration or Review (drop-down).
Verification referenceWhere the check is planned: ITP step, test procedure or review step.
Evidence (record)The record that proves it: report, certificate or returned document, with number.
StatusOpen, Planned, In progress, Verified, Failed or Concession (drop-down). Failed rows turn red; Concession rows amber.
OwnerWho closes the row.
RemarksAnything a reviewer needs, such as a linked change or open NCR.

Verification methods

MethodMeaning
TestMeasure the item under set conditions, such as a pressure or leak test.
InspectionLook at or measure the item or its records, such as a dimensional check or certificate review.
AnalysisShow by calculation or model, such as a wall-thickness or torque calculation.
DemonstrationOperate the item and show it works, without detailed measurement.
ReviewCheck a document against the requirement, such as a drawing or procedure approval.

Test, analysis, demonstration and inspection are the classic systems-engineering set. Review is added here because so many equipment requirements are met by an approved document.

How to use the template

  1. Fix the baseline: the purchase order, the specification and datasheet revisions, and the agreed deviation list. Put them in the header block.
  2. Give every requirement its own row and a unique ID that never changes. Split clauses that hold more than one requirement.
  3. Where an agreed deviation or concession changes a requirement, note it in the Agreed deviation column, so you verify what was agreed, not the original wording.
  4. For each row, name the design document that meets it and the verification method: test, inspection, analysis, demonstration or review.
  5. Link each row to where the check is planned, usually an inspection and test plan (ITP) step or a test procedure.
  6. When the check is done, add the record number in Evidence and set the status. Failed rows turn red and Concession rows amber.
  7. When a specification or drawing changes, filter the Source document or Design reference column to find every row it affects.
  8. Before handover, filter Status for anything that is not Verified or Concession. Every such row needs an action or an agreed deviation.

What OdysseyGPT does, and does not do

OdysseyGPT is not a requirements traceability or requirements management tool, and it does not build or maintain an RTM. What it does is check requirements against documents with citations: at bid stage, Document Review checks the customer's specification against your datasheets and drafts a compliance matrix with the clause and page for every requirement. Those rows are a sound starting point for the Requirement column here. For dedicated traceability software, look at requirements management tools.

Frequently asked questions

Is there a free requirements traceability matrix template in Excel?

Yes. This XLSX template has a blank RTM, a filled-in example for an invented valve order and a How to use sheet, with drop-downs for type, verification method and status. A CSV of the same columns is also free under CC BY 4.0.

What columns should a requirements traceability matrix have?

At least a requirement ID, the source and clause, the requirement, the design reference, the verification method, the evidence and a status. This template adds type, agreed deviation, verification reference, owner and remarks.

Does OdysseyGPT build traceability matrices?

No. OdysseyGPT checks requirements against documents with citations and drafts a bid compliance matrix. It is not a traceability tool, and it does not maintain an RTM.

References

Requirements traceability

Wikipedia

Visit source

Technical requirements definition (bidirectional traceability)

NASA Systems Engineering Handbook

Visit source

Creative Commons Attribution 4.0 International

Creative Commons

Visit source