The short answer

A pressure vessel ITP lists every inspection and test on a welded vessel, in order, from material receipt to the final dossier. This free Excel template gives each step a reference document, where its acceptance criteria come from, the record it produces and hold, witness, review or monitor points for the manufacturer, the customer and the third-party inspector.

Key Takeaways

  • The steps are a starting point. The design code and the purchase order decide which apply; check them before you issue the plan.
  • Acceptance criteria cells point to the code, the approved procedure or the drawing. They never copy values from the code.
  • Intervention codes are H (hold), W (witness), R (review) and M (monitor). Use the customer's legend if the purchase order defines one.
  • The example has 19 steps for an invented vessel order (PO-EX-4410).

Download the pressure vessel ITP

Both files are free under CC BY 4.0, with no form to fill in. The XLSX opens in Excel, Google Sheets, LibreOffice and Numbers. The CSV carries the table only; the header block is in the XLSX.

What it is for and who uses it

An inspection and test plan (ITP) is agreed with the customer before manufacture starts. This one has the steps a welded pressure vessel usually goes through: material identification, fit-up, welding, NDE, heat treatment where required, dimensional inspection, the pressure test, the nameplate, the data report and the final dossier. The general ITP template has the same columns with a valve example.

  • Quality engineers at vessel manufacturers, who write the plan and send it for approval.
  • Welding and NDE coordinators, who own the welding and examination steps.
  • Customer and third-party inspectors, who mark their hold, witness and review points on it.

Used as a pressure vessel inspection checklist, the Status column shows what is done and what is open. Which steps a code requires, and what the inspector must attend, differ between codes such as ASME Section VIII and EN 13445. Check the governing code or contract. See also pressure vessel manufacturers.

Header block

Header block fields, with the invented example values
FieldExample
ProjectExample Process Skid (fictional)
CustomerExample EPC Contractor Ltd (fictional)
Purchase orderPO-EX-4410 (fictional)
Equipment / packageWelded pressure vessel V-4410 (fictional)
Design codeAs stated in the PO (for example ASME Section VIII Division 1 or EN 13445)
Third party / inspectorAs the code and the PO require (fictional)
ITP no.ITP-EX-4410
RevisionB
Date2026-12-10
Prepared byQuality engineer
Approved by (customer)

Example steps: a welded pressure vessel

Invented example steps for PO-EX-4410 (some columns omitted)
StepActivityReference documentAcceptance criteriaRecordMfrCustomerThird partyRemarks
1Design documents approved: calculations, general arrangement and detail drawingsVDR-EX-4410Per code and POReturned drawings with review codeRRR
2Material certificates for pressure parts reviewed against the PO and the material specificationQP-01 section 4Per code, material specification and POCertificate review checklistsHRR
3Material identification: marking and heat numbers checked, and transferred before cuttingQP-03Per code and approved procedureMaterial traceability recordH-M
4Welding procedures (WPS, PQR) and welder qualifications checked against the weld mapWeld map WM-EX-4410Per code and approved procedureWPS/PQR/WPQ cross-check matrixHRRWPS approval by the customer where the PO requires it.
5Forming of shell and heads: shape and thickness after formingDrawing GA-EX-4410Per code and drawingForming and dimensional reportH-M
6Fit-up of seams and nozzles before welding: alignment, gap and joint preparationWPS; drawing GA-EX-4410Per code and approved procedureFit-up inspection recordH-W
7Welding: consumable control, and preheat and interpass control where the WPS requires themWPS; weld map WM-EX-4410Per code and approved procedureWeld logHMM
8Visual examination of completed weldsVT procedure NDT-01Per code and approved procedureVisual examination reportH-M
9Weld repairs, where needed: recorded, re-welded to an approved WPS and re-examinedQP-09; WPSPer code and approved procedureRepair record; weld logHRROnly if a weld is rejected.
10Post-weld heat treatment (PWHT), where the code, WPS or PO requires itPWHT procedure HT-EX-02Per code and approved procedureHeat treatment chart and reportHRRDelete the step if PWHT is not required. Check the governing code and the PO.
11NDE of welds, by the methods and to the extent the code and drawing requireNDE procedures NDT-02 to NDT-05Per code and approved procedureNDE reportsHRRTiming relative to PWHT as the code and procedure require. Operator qualifications on file.
12Visual and dimensional inspection before the pressure test, including nozzle orientation and projectionsDrawing GA-EX-4410Per code and drawingDimensional reportHWW
13Test equipment: gauges and recorders calibrated and suited to the testTest procedure TP-EX-07Per code and approved procedureCalibration certificatesHRR
14Hydrostatic pressure testTest procedure TP-EX-07Per code and approved procedurePressure test report and chartHHWGive the notice period the PO requires.
15Inspection after the test: draining, drying and internal cleanlinessTest procedure TP-EX-07Per approved procedure and POFinal inspection reportH-M
16Surface preparation and painting, where specifiedPainting procedure PP-EX-01Per painting specification and approved procedureCoating inspection reportHM-
17Nameplate: content checked against the drawing and the data report, and stampingNameplate drawing NP-EX-4410Per code and approved drawingNameplate rubbing or photographHRW
18Manufacturer's data report or declaration completed and certified, as the code requiresQP-01 section 9Per codeData reportHRH
19Final dossier (manufacturing record book) reviewed and released for shipmentMRB index MRB-EX-4410Per PO document requirementsInspection release noteHHRShipment held until the release note is signed.

The file also has columns for stage, record number and status. The intervention points shown are invented for the example and are not what any code or customer requires. Every example value is invented: the project, customer, bidders, purchase order, prices and every document, certificate, serial and report number do not exist. Standards are named but not quoted.

Intervention codes

CodeCommon meaning
H (hold)Work does not go past this step until the named party has attended or released it in writing.
W (witness)The named party is notified and may attend. If they do not attend after due notice, work may go on.
R (review)The named party reviews the record (certificate, report or procedure) rather than attending.
M (monitor)The named party may observe the activity at any time, without a fixed notification.
-No intervention by that party at this step.

These are common meanings. Customers define their own legends, and some use other letters. Use the definitions in your purchase order.

Columns and what to write

ColumnWhat to write
StepStep number, in the order the work happens.
Activity / characteristicThe inspection or test, and what it checks.
StageWhen it happens: before manufacture, material receipt, forming, welding, heat treatment, NDE, testing, final, documentation.
Reference documentThe procedure, drawing or document that says how the check is done.
Acceptance criteria referenceWhere the pass/fail criteria come from: the code, the approved procedure, the drawing or a PO clause. Point to them; do not copy values from the code.
Record producedThe record the step produces, such as a certificate, report, chart or checklist.
ManufacturerManufacturer's intervention: H, W, R, M or - (drop-down).
CustomerCustomer's intervention: H, W, R, M or - (drop-down).
Third party / inspectorIntervention of the third-party or authorised inspector: H, W, R, M or - (drop-down).
Record no.Number of the record once it exists.
StatusNot started, Notified, Done, Released or NCR raised (drop-down). NCR rows turn red.
RemarksNotice period, whether the step applies, or anything else the inspector needs.

How to use the template

  1. Fill in the header block: purchase order, the design code the PO names, who the third-party or authorised inspector is, and the ITP number and revision.
  2. List every inspection and test in the order the work happens, from design approval and material receipt to the final dossier. One check per row.
  3. Delete the steps that do not apply to your vessel, such as PWHT or painting, and add any the PO or the code asks for. Check the governing code or contract; this list is a starting point, not a statement of what any code requires.
  4. For each step, name the reference document and where the acceptance criteria come from. Point to the code, the approved procedure or the drawing; do not copy values from the code.
  5. Set the intervention for each party: H (hold), W (witness), R (review), M (monitor) or - (none). Use the customer's own codes if the PO defines them. The code or the inspector may set some points for you.
  6. Send the ITP for approval before manufacture starts. Do not pass a hold point without written release.
  7. As work goes on, add the record number and status for each step. Rows with an NCR raised turn red.
  8. Before release, filter Status for anything that is not Done or Released. Every such row needs an answer before shipment.

Checking the plan against the customer's requirements

In OdysseyGPT's Inspection & Testing module, ITP Validator (beta) reads your ITP and the customer's quality requirements and shows which required inspections and tests the plan covers and which it misses. NDE Coverage Review (beta) does the same for the NDE the drawings and specification call for. Every finding cites the page it came from, and your engineers decide what to do with it. Tools marked beta are open on request, and we onboard each team ourselves.

Want us to run the check for you?

Send your ITP and the customer's quality requirements. We send back what is covered, what is missing and what still needs evidence before the FAT.

Get the free ITP and FAT readiness check

New templates by email (optional)

Your download does not depend on this.

We use your email only for this. See our privacy policy.

Frequently asked questions

What is a pressure vessel ITP?

An inspection and test plan for a pressure vessel: a table of every inspection and test during manufacture, in order, with the document that governs each one, the record it produces and who holds, witnesses or reviews it.

Which inspections does a pressure vessel need?

That depends on the design code, the vessel and the purchase order. The template lists steps that are common on a welded vessel, from material identification to the pressure test and data report, as a starting point. Check the governing code or contract and delete or add steps to match.

Why do the acceptance criteria only say per code and approved procedure?

Because the limits belong in the code and in your approved procedures, and they differ between codes and editions. The ITP points to where the criteria are; it does not restate them. Put the code clause or procedure number in the cell if your customer asks for it.

Is post-weld heat treatment always a step?

No. Whether PWHT is required depends on the code, the material, the thickness, the welding procedure and the purchase order. The template includes the step so it is not forgotten; delete it if it does not apply.

Is there a free pressure vessel ITP template in Excel?

Yes. This XLSX template has a blank plan, a filled-in example for an invented vessel order and a How to use sheet. A CSV of the same columns is also free under CC BY 4.0.

References