Download the pressure vessel ITP
XLSX
Pressure vessel ITP (Excel)
Header block, 12 columns, drop-downs for intervention codes and status, NCR rows in red, frozen header row, filters and a How to use sheet.
CSV
Pressure vessel ITP (CSV)
The example rows as plain CSV (UTF-8), for Google Sheets or any other tool.
Both files are free under CC BY 4.0, with no form to fill in. The XLSX opens in Excel, Google Sheets, LibreOffice and Numbers. The CSV carries the table only; the header block is in the XLSX.
What it is for and who uses it
An inspection and test plan (ITP) is agreed with the customer before manufacture starts. This one has the steps a welded pressure vessel usually goes through: material identification, fit-up, welding, NDE, heat treatment where required, dimensional inspection, the pressure test, the nameplate, the data report and the final dossier. The general ITP template has the same columns with a valve example.
- Quality engineers at vessel manufacturers, who write the plan and send it for approval.
- Welding and NDE coordinators, who own the welding and examination steps.
- Customer and third-party inspectors, who mark their hold, witness and review points on it.
Used as a pressure vessel inspection checklist, the Status column shows what is done and what is open. Which steps a code requires, and what the inspector must attend, differ between codes such as ASME Section VIII and EN 13445. Check the governing code or contract. See also pressure vessel manufacturers.
Header block
| Field | Example |
|---|---|
| Project | Example Process Skid (fictional) |
| Customer | Example EPC Contractor Ltd (fictional) |
| Purchase order | PO-EX-4410 (fictional) |
| Equipment / package | Welded pressure vessel V-4410 (fictional) |
| Design code | As stated in the PO (for example ASME Section VIII Division 1 or EN 13445) |
| Third party / inspector | As the code and the PO require (fictional) |
| ITP no. | ITP-EX-4410 |
| Revision | B |
| Date | 2026-12-10 |
| Prepared by | Quality engineer |
| Approved by (customer) |
Example steps: a welded pressure vessel
| Step | Activity | Reference document | Acceptance criteria | Record | Mfr | Customer | Third party | Remarks |
|---|---|---|---|---|---|---|---|---|
| 1 | Design documents approved: calculations, general arrangement and detail drawings | VDR-EX-4410 | Per code and PO | Returned drawings with review code | R | R | R | |
| 2 | Material certificates for pressure parts reviewed against the PO and the material specification | QP-01 section 4 | Per code, material specification and PO | Certificate review checklists | H | R | R | |
| 3 | Material identification: marking and heat numbers checked, and transferred before cutting | QP-03 | Per code and approved procedure | Material traceability record | H | - | M | |
| 4 | Welding procedures (WPS, PQR) and welder qualifications checked against the weld map | Weld map WM-EX-4410 | Per code and approved procedure | WPS/PQR/WPQ cross-check matrix | H | R | R | WPS approval by the customer where the PO requires it. |
| 5 | Forming of shell and heads: shape and thickness after forming | Drawing GA-EX-4410 | Per code and drawing | Forming and dimensional report | H | - | M | |
| 6 | Fit-up of seams and nozzles before welding: alignment, gap and joint preparation | WPS; drawing GA-EX-4410 | Per code and approved procedure | Fit-up inspection record | H | - | W | |
| 7 | Welding: consumable control, and preheat and interpass control where the WPS requires them | WPS; weld map WM-EX-4410 | Per code and approved procedure | Weld log | H | M | M | |
| 8 | Visual examination of completed welds | VT procedure NDT-01 | Per code and approved procedure | Visual examination report | H | - | M | |
| 9 | Weld repairs, where needed: recorded, re-welded to an approved WPS and re-examined | QP-09; WPS | Per code and approved procedure | Repair record; weld log | H | R | R | Only if a weld is rejected. |
| 10 | Post-weld heat treatment (PWHT), where the code, WPS or PO requires it | PWHT procedure HT-EX-02 | Per code and approved procedure | Heat treatment chart and report | H | R | R | Delete the step if PWHT is not required. Check the governing code and the PO. |
| 11 | NDE of welds, by the methods and to the extent the code and drawing require | NDE procedures NDT-02 to NDT-05 | Per code and approved procedure | NDE reports | H | R | R | Timing relative to PWHT as the code and procedure require. Operator qualifications on file. |
| 12 | Visual and dimensional inspection before the pressure test, including nozzle orientation and projections | Drawing GA-EX-4410 | Per code and drawing | Dimensional report | H | W | W | |
| 13 | Test equipment: gauges and recorders calibrated and suited to the test | Test procedure TP-EX-07 | Per code and approved procedure | Calibration certificates | H | R | R | |
| 14 | Hydrostatic pressure test | Test procedure TP-EX-07 | Per code and approved procedure | Pressure test report and chart | H | H | W | Give the notice period the PO requires. |
| 15 | Inspection after the test: draining, drying and internal cleanliness | Test procedure TP-EX-07 | Per approved procedure and PO | Final inspection report | H | - | M | |
| 16 | Surface preparation and painting, where specified | Painting procedure PP-EX-01 | Per painting specification and approved procedure | Coating inspection report | H | M | - | |
| 17 | Nameplate: content checked against the drawing and the data report, and stamping | Nameplate drawing NP-EX-4410 | Per code and approved drawing | Nameplate rubbing or photograph | H | R | W | |
| 18 | Manufacturer's data report or declaration completed and certified, as the code requires | QP-01 section 9 | Per code | Data report | H | R | H | |
| 19 | Final dossier (manufacturing record book) reviewed and released for shipment | MRB index MRB-EX-4410 | Per PO document requirements | Inspection release note | H | H | R | Shipment held until the release note is signed. |
The file also has columns for stage, record number and status. The intervention points shown are invented for the example and are not what any code or customer requires. Every example value is invented: the project, customer, bidders, purchase order, prices and every document, certificate, serial and report number do not exist. Standards are named but not quoted.
Intervention codes
| Code | Common meaning |
|---|---|
| H (hold) | Work does not go past this step until the named party has attended or released it in writing. |
| W (witness) | The named party is notified and may attend. If they do not attend after due notice, work may go on. |
| R (review) | The named party reviews the record (certificate, report or procedure) rather than attending. |
| M (monitor) | The named party may observe the activity at any time, without a fixed notification. |
| - | No intervention by that party at this step. |
These are common meanings. Customers define their own legends, and some use other letters. Use the definitions in your purchase order.
Columns and what to write
| Column | What to write |
|---|---|
| Step | Step number, in the order the work happens. |
| Activity / characteristic | The inspection or test, and what it checks. |
| Stage | When it happens: before manufacture, material receipt, forming, welding, heat treatment, NDE, testing, final, documentation. |
| Reference document | The procedure, drawing or document that says how the check is done. |
| Acceptance criteria reference | Where the pass/fail criteria come from: the code, the approved procedure, the drawing or a PO clause. Point to them; do not copy values from the code. |
| Record produced | The record the step produces, such as a certificate, report, chart or checklist. |
| Manufacturer | Manufacturer's intervention: H, W, R, M or - (drop-down). |
| Customer | Customer's intervention: H, W, R, M or - (drop-down). |
| Third party / inspector | Intervention of the third-party or authorised inspector: H, W, R, M or - (drop-down). |
| Record no. | Number of the record once it exists. |
| Status | Not started, Notified, Done, Released or NCR raised (drop-down). NCR rows turn red. |
| Remarks | Notice period, whether the step applies, or anything else the inspector needs. |
How to use the template
- Fill in the header block: purchase order, the design code the PO names, who the third-party or authorised inspector is, and the ITP number and revision.
- List every inspection and test in the order the work happens, from design approval and material receipt to the final dossier. One check per row.
- Delete the steps that do not apply to your vessel, such as PWHT or painting, and add any the PO or the code asks for. Check the governing code or contract; this list is a starting point, not a statement of what any code requires.
- For each step, name the reference document and where the acceptance criteria come from. Point to the code, the approved procedure or the drawing; do not copy values from the code.
- Set the intervention for each party: H (hold), W (witness), R (review), M (monitor) or - (none). Use the customer's own codes if the PO defines them. The code or the inspector may set some points for you.
- Send the ITP for approval before manufacture starts. Do not pass a hold point without written release.
- As work goes on, add the record number and status for each step. Rows with an NCR raised turn red.
- Before release, filter Status for anything that is not Done or Released. Every such row needs an answer before shipment.
Checking the plan against the customer's requirements
In OdysseyGPT's Inspection & Testing module, ITP Validator (beta) reads your ITP and the customer's quality requirements and shows which required inspections and tests the plan covers and which it misses. NDE Coverage Review (beta) does the same for the NDE the drawings and specification call for. Every finding cites the page it came from, and your engineers decide what to do with it. Tools marked beta are open on request, and we onboard each team ourselves.
Want us to run the check for you?
Send your ITP and the customer's quality requirements. We send back what is covered, what is missing and what still needs evidence before the FAT.