Class certificate checklist for a marine equipment order (Excel and CSV)

For suppliers to shipyards: one row per equipment item, showing the approval route, type approval certificate, drawing approvals, surveys, product and material certificates and the wheel mark.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

A class certificate checklist tracks what a marine equipment supplier owes the classification society and the yard before delivery. This free Excel template has one row per equipment item: required class and notation, approval route, type approval certificate and expiry, drawings submitted, surveys and witnessed tests, product certificate, material certificate type and Marine Equipment Directive wheel mark.

Key Takeaways

  • A type approval certificate has an expiry date and a scope. Check both against the delivery date and the size you supply.
  • Type approval of a design does not by itself mean each unit ships without a product certificate.
  • Bought-in motors, valves and panels need their own rows.
  • The example has 9 items for an invented auxiliary equipment package (PO-EX-2260), four of them still waiting for a product certificate.

Download the class certificate checklist

Both files are free under CC BY 4.0, with no form to fill in. The XLSX opens in Excel, Google Sheets, LibreOffice and Numbers. The CSV carries the table only; the header block is in the XLSX.

What the yard expects with each item

A ship is built under the rules of a classification society, and much of the equipment on board has to be approved or certified under those rules before the yard will accept it. For a supplier, that turns into a set of questions per item: is the design type approved or approved for this order, has the surveyor seen the tests, is there a product certificate, and which material certificates go with it? Some items also fall under the Marine Equipment Directive and carry the wheel mark. The checklist puts those answers in one row per item, starting when the order is reviewed.

  • Project engineers at pump, valve, heat exchanger, panel and package suppliers, who run the order.
  • Quality managers, who book the surveyor and collect the certificates.
  • Purchasing staff at shipyards, who can ask each supplier to return the list filled in.

The template does not say which equipment needs approval, a survey or a particular certificate. Each classification society publishes its own rules, they differ by item, rating and notation, and the yard's specification may add to them. Check the governing rules or contract, and ask the society's local office where the answer is not clear. See class type approval and marine equipment manufacturers.

Header block

Header block fields, with the invented example values
FieldExample
VesselExample Offshore Supply Vessel, hull EX-412 (fictional)
ShipyardExample Shipyard Ltd (fictional)
Purchase orderPO-EX-2260 (fictional)
Yard's specificationYS-EX-412 Rev 2 (invented)
Class society and class notationAs stated in YS-EX-412 section 1.2
Flag and statutory requirementsAs stated in YS-EX-412 section 1.3
Scope of supplyEngine room auxiliary equipment package (fictional)
Checklist no.CCC-EX-2260
Date2027-02-01
Prepared byProject engineer
Checked byQuality manager

Example items: an engine room auxiliary package

Invented example rows for order PO-EX-2260 (the class and notation column is omitted)
ItemEquipment itemApproval routeType approval certificate no. and expiryDrawings submitted and statusSurvey and witnessed testsProduct certificate receivedMaterial certificate type for stated partsMED wheel mark and moduleRemarks
1Bilge pump BP-01Type approvalTA-EX-10432; expires 2028-03-31None needed for approval; datasheet sent for informationWorks test attended by the surveyor, as the class rules and YS-EX-412 5.1 stateNAs YS-EX-412 4.3 states for casing and shaftNProduct certificate follows the witnessed test. Book the surveyor.
2Sea water cooling pump CW-01Type approvalTA-EX-09871; expires 2027-02-28None needed for approvalWorks test attended by the surveyor, as the class rules and YS-EX-412 5.1 stateNAs YS-EX-412 4.3 states for casing and shaftNThe type approval runs out before the delivery date of 2027-04-15. Ask the pump maker for the renewed certificate.
3Plate heat exchanger HE-02Case-by-case design approval-DRG-EX-2260-11 to -14 sent 2027-01-18; returned with commentsPressure test attended by the surveyor, as the class rules and YS-EX-412 5.2 stateNAs YS-EX-412 4.3 states for pressure partsNAnswer the comments and resubmit. No plates are to be ordered before approval.
4Compressed air receiver AR-01Case-by-case design approval-DRG-EX-2260-21 and calculation CAL-EX-2260-21; approved 2027-01-25Pressure test attended by the surveyor, as the class rules and YS-EX-412 5.2 stateYAs YS-EX-412 4.3 states for shell and headsN
5Electric motor M-BP-01 for the bilge pumpType approvalTA-EX-11208; expires 2029-06-30None needed for approvalMaker's routine test report reviewed; attendance as the class rules state for the motor's ratingNot requiredNot statedNConfirmed with the yard under YS-EX-412 5.4.
6Control panel CP-01Case-by-case design approval-Circuit diagrams ED-EX-2260-01 to -06 sent 2027-01-22; still with the class societyFunction test attended by the surveyor, as YS-EX-412 5.5 statesNNot statedNChase the approval. The panel build is planned for 2027-02-15.
7Ship-side valves SV-01 to SV-04Type approvalTA-EX-08815; expires 2028-09-30None needed for approvalPressure test attended by the surveyor, as the class rules and YS-EX-412 5.2 stateYAs YS-EX-412 4.3 states for valve bodiesN
8Fire dampers FD-01 to FD-06Type approvalMED certificate MED-EX-5521; expires 2027-11-30None needed for approvalNone at works; production is covered under the MED module shownNot requiredNot statedY: B with D, as the declaration of conformity statesCheck the declaration of conformity and the wheel mark on each nameplate at dispatch.
9Lubricating oil filter LF-01Not class relevant-NoneNoneNot requiredNot statedNYard confirmed by e-mail of 2027-01-20, filed with YS-EX-412.

No classification society is named: the cells say "the class society" and point to an invented yard specification, YS-EX-412. The surveys, certificate types and the wheel mark module shown are what that invented specification asks for, and are not a statement of any society's rules or of the Directive. Every example value is invented: the project, customer, bidders, purchase order, prices and every document, certificate, serial and report number do not exist. Standards are named but not quoted.

Approval routes

RouteWhat it means for the row
Type approvalThe design already holds a type approval certificate from the class society the yard names. Check the certificate number, its scope and its expiry date.
Case-by-case design approvalThe class society approves the drawings for this order. List what was submitted and where each submission stands.
Not class relevantThe yard's specification or the class society confirms the item needs no class approval. Keep the confirmation.

Columns and what to write

ColumnWhat to write
ItemRunning number.
Equipment itemOne item or group of identical items in your scope, with its tag.
Class society and notation required by the yardThe class society and class notation the yard's specification states, with the clause. Add any statutory requirement the yard passes on.
Approval routeType approval, Case-by-case design approval or Not class relevant (drop-down).
Type approval certificate no. and expiryThe certificate number and its expiry date. Check that it is still valid on the delivery date and that its scope covers the size and rating you supply.
Drawings submitted for approval and statusThe drawings and documents sent to the class society, the date, and whether they are approved, returned with comments or still with the society.
Survey and witnessed tests requiredThe inspections and tests the surveyor attends, as the class rules and the yard's specification state them for this item.
Product certificate receivedY, N or Not required (drop-down). Rows still at N turn amber.
Material certificate type required for stated partsThe certificate type the class rules or the yard's specification ask for, and for which parts. Write the clause.
MED wheel mark requiredY if the item needs approval under the Marine Equipment Directive and the wheel mark, N if it does not (drop-down). The yard's specification and the flag decide.
MED moduleThe conformity assessment modules named on the declaration of conformity. Leave a dash where no wheel mark is required.
RemarksWhat is open, and what has to happen before delivery.

How to run an order with it

  1. Fill in the header block from the yard's specification: the class society, the class notation, the flag and any statutory requirements it passes on.
  2. List every item in your scope, one row each. Include bought-in items such as motors, valves and panels; they need their own certificates.
  3. Choose the approval route for each item. Which items need approval, and by which route, is set by the class society's rules and the yard's specification. Check the governing rules or contract, and ask the society where you are unsure.
  4. For a type-approved item, enter the certificate number and expiry. Check that it is valid on the delivery date and that its scope covers what you supply.
  5. For a case-by-case item, list the drawings sent to the class society, the date and the status. Do not start manufacture on drawings that are not approved.
  6. Enter the surveys and witnessed tests the rules and the specification state for the item, and the material certificate type they ask for, with the parts it applies to.
  7. Mark whether the item needs the wheel mark under the Marine Equipment Directive, and copy the modules from the declaration of conformity.
  8. Set Product certificate received when the certificate is in your hands. Rows still at N turn amber. Nothing ships to the yard with an amber row.

Keeping class documents in step with the order

Class paperwork runs alongside the yard's own document list, and the two drift apart: a drawing approved by the society at one revision and issued to the yard at another, a certificate promised in the order and never logged. In OdysseyGPT's Order & Document Control module, VDRL/MDR Tracker (beta) reads the yard's document requirements and your register and shows which documents are due, late or at the wrong revision. Material Certificate Review (beta) compares each material certificate with the type and content the order asks for. Findings cite the page, and your project engineer decides what to do. Tools marked beta are open on request, and we onboard each team ourselves.

Want us to run the check for you?

Send your quotation and the customer's purchase order. We send back a list of what changed between them, each item cited to its page.

Get the free quotation-vs-PO check

New templates by email (optional)

Your download does not depend on this.

We use your email only for this. See our privacy policy.

Frequently asked questions

What is a class certificate for marine equipment?

A document issued by, or on behalf of, a classification society stating that an item of equipment was approved, surveyed or tested under the society's rules. Yards ask for it so the vessel can be classed.

What is the difference between a type approval certificate and a product certificate?

A type approval certificate covers a design or product type for a period of time. A product certificate covers the particular unit or batch delivered, usually after a survey or witnessed test. The society's rules say when each is needed.

Does type-approved equipment still need a survey?

Sometimes. It depends on the society, the kind of equipment, its rating and what the type approval certificate itself says. Read the certificate's conditions and the yard's specification. Check the governing rules or contract.

What is the wheel mark?

The conformity mark for equipment approved under the EU Marine Equipment Directive. It applies to the kinds of equipment the Directive lists, such as certain fire protection and life-saving items, on ships under the flags concerned.

The yard has changed the class society. What do I do?

Go through the list again from the top. A type approval from one society is not automatically accepted by another, and drawing approvals may have to be repeated. Agree the consequences with the yard in writing.