Mill test certificate (MTC): what it is and what each field means

A plain guide to the mill cert: who issues it, what every block on it tells you, how MTC, MTR and material test certificate relate, and how to check one against your order.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

A mill test certificate (MTC) is the document a steel or alloy producer issues with a batch of material. It states the grade, the heat number, the chemical analysis and the mechanical test results, and declares that the material meets the ordered specification. Buyers use it to accept material and to prove traceability.

Key Takeaways

  • Mill test certificate, mill cert, MTC, MTR and CMTR all name the same kind of document.
  • The heat number is the link between the certificate and the metal in your hands.
  • Meeting the material standard is one check. Meeting your purchase order is a second one.
  • The EN 10204 type on the certificate says who validated the results.

What is a mill test certificate?

A mill test certificate is a quality record from the mill that melted or formed the material. It travels with plate, bar, pipe, forgings, castings and fittings. It reports what the material is made of, how strong it is, what heat treatment it had and which standard it was made to. One certificate covers one or more heats, and each heat has its own number.

For an equipment manufacturer the mill cert does two jobs. At goods-in it is the evidence for accepting the material. At handover it goes into the record book to show the customer that each pressure part or structural part is the grade the order required.

You get a mill test certificate from the supplier of the material. Ask for it on the purchase order, state the certificate type you need, and require the heat number to be marked on the material. A stockist passes on the mill's certificate, usually with its own delivery reference added. A certificate cannot be created afterwards for material with unknown origin.

Check a stack of mill certs against the order

Bring the certificates from one closed order with the purchase order and the bill of materials. We run them and show each value beside the requirement it was checked against.

Request a demo

MTC, MTR, mill cert and material test certificate: the names

The names differ by region and by habit. The document is the same.

Names you will see for the same document
NameWhere it is commonNotes
Mill test certificate (MTC)Europe, Middle East, AsiaOften used with an EN 10204 type, such as an MTC 3.1
Mill test report (MTR)North AmericaThe usual term with ASTM and ASME materials
Certified material test report (CMTR)North America, pressure equipmentStresses that the report is certified by the producer
Mill certEverywhere, informalShop-floor shorthand for any of the above
Material test certificateGeneralA wider term that can also cover certificates from a test laboratory or a forge
Inspection certificate 3.1 or 3.2EuropeThe EN 10204 name for the two most requested types

So the difference between a mill certificate and a material certificate is one of scope. A mill certificate comes from the producing mill. A material certificate is any certificate of a material's properties, including one issued by a processor or laboratory after further work. See the glossary entry for the certified material test report.

What each field on an MTC certificate means

Mill test certificate fields (own summary)
FieldWhat it tells youWhat to compare it with
Producer and worksWho made the material and whereApproved manufacturer list, if the order has one
Certificate number and dateThe identity of this certificateThe delivery note and your goods-in record
Customer and order referenceWho the mill made it forYour purchase order, or the stockist's order
Product form and sizePlate, bar, pipe or forging, with dimensionsThe bill of materials line
Specification, grade and editionThe standard and grade the mill certifiesThe grade and edition your order names
Heat numberThe melt the material came fromThe marking on the material itself
Chemical analysisThe percentage of each elementThe ranges in the standard and any tighter ones in the order
Mechanical testsYield strength, tensile strength, elongation, and hardness where requiredThe standard and the order
Impact testsAbsorbed energy at a stated temperatureThe test temperature and energy the order requires
Heat treatmentCondition such as normalised or quenched and temperedThe delivery condition ordered
Supplementary testsUltrasonic examination, corrosion tests and similarSupplementary requirements in the order
Certificate typeThe EN 10204 type, such as 2.2, 3.1 or 3.2The type the order requires
Statement and signatureThe declaration of conformity and who signed itThe party the certificate type calls for

The certificate type matters as much as the numbers. In broad terms, a 3.1 certificate is validated by the manufacturer's own representative who is independent of production, and a 3.2 certificate adds an independent inspector or the purchaser's representative. The full comparison is in EN 10204 3.1 vs 3.2.

How to check a mill cert against the order

A certificate can meet the material standard and still fail your order. Customer specifications often add a colder impact test, a hardness cap for sour service, a tighter carbon content or a 3.2 certificate. Work through this checklist for each certificate.

  1. Match the heat number on the certificate to the marking on the material.
  2. Match the product form, size and quantity to the bill of materials line.
  3. Confirm the specification, grade and edition are the ones the order names.
  4. Confirm the certificate type is the one the order requires and that the right party signed it.
  5. Check every element in the chemical analysis against the standard and the order.
  6. Check yield, tensile, elongation and hardness against the standard and the order.
  7. Check impact tests were done at the temperature the order requires.
  8. Check the heat treatment condition matches the delivery condition ordered.
  9. Check each supplementary test in the order has a result on the certificate.
  10. Record the result and file the certificate against the part and its heat number.

For the reasoning behind each step, with common failures, read how to review a material test report. A printable version of the checklist is in the MTR review checklist template.

A worked example: right grade, wrong order

A valve maker orders forged bodies in a low-temperature carbon steel grade. The customer's specification adds two things: a hardness maximum for sour service and a 3.2 certificate. The forgings arrive with a certificate that shows the right grade, chemistry inside the standard and impact results that pass. It is a 3.1 certificate, and it reports no hardness.

Measured against the material standard, the certificate passes. Measured against the order, it has two gaps. Found at goods-in, the fix is a hardness test and a conversation with the supplier. Found when the record book is reviewed, the fix can mean holding finished valves.

How OdysseyGPT does this check

Material Certificate Review (beta) reads your certificate PDFs and checks each one against the purchase requirements, the material specification and the bill of materials. It verifies grade, heat number, chemical composition, mechanical tests, heat treatment, supplementary tests and the EN 10204 certificate type.

  • An inventory of every certificate and heat number it read.
  • A finding for each required property, with the certificate value and the requirement quoted side by side.
  • Conflicts called out: wrong certificate type, out-of-range results, missing heat treatment, or a grade that differs from the bill of materials.
  • A CSV or JSON export for your incoming inspection records.

Every finding cites the page it came from, and a quality engineer decides each one. To link the heats to parts and tags afterwards, use the Material Traceability Check (beta).

See the order check on your own certificates

Send us ten certificates and the purchase order they belong to. In the demo you will see which ones meet the standard but miss something the order added.

Request a demo

See it on your own documents

Bring your hardest mill certs

Scanned, multi-heat or dual-certified: pick the certificates that take longest to review by hand. We read them with you against the order and you keep the findings.

Request a demo

Frequently asked questions

What is a mill test certificate?

A mill test certificate is a document issued by the producer of a metal product. It records the specification and grade, the heat number, the chemical analysis, the mechanical test results and the heat treatment, and it declares that the material meets the standard it was ordered to. It is also called an MTC, mill cert or mill test report.

Where can I get a mill test certificate?

From whoever supplied the material. The mill issues it, and a stockist or distributor passes it on with the delivery. Ask for it on the purchase order and state the certificate type you need. If material arrives without one, ask the supplier for the certificate by heat number, which should be marked on the material.

How to get a mill certificate for material I already have?

Read the heat number and any other marking on the material, then ask the supplier for the certificate that matches. If the supplier cannot provide one, the material has no documented origin. Testing a sample can show its chemistry and strength, but a test report from a laboratory is a different document from the mill's own certificate.

What is the difference between a mill certificate and a material certificate?

A mill certificate is issued by the mill that produced the material. A material certificate is a wider term for any certificate of a material's properties, and it can come from a mill, a forge, a processor or a laboratory. In daily use on equipment orders, people use both names for the same document.

Is an MTC the same as an MTR?

Yes. MTC stands for mill test certificate and MTR for mill test report or material test report. The first is more common in Europe, the Middle East and Asia, the second in North America. Both report the heat number, chemistry and mechanical results for a batch of material and both serve as proof of conformity.

What does 3.1 mean on a mill test certificate?

It is the certificate type under EN 10204. A 3.1 certificate reports results from tests on the delivered material and is validated by the manufacturer's authorised representative, who is independent of the production department. A 3.2 certificate adds validation by an independent inspector or the purchaser's representative. Orders state which type is required.

References

EN 10204:2004 Metallic products. Types of inspection documents

CEN

ASTM A370 Standard Test Methods and Definitions for Mechanical Testing of Steel Products

ASTM International