One assembly, one set of welding documents
Rolling stock builders buy welded brackets, frames, tanks and housings from suppliers who have to show two things: that the works is certified for the kind of welding involved, and that each weld on each assembly was planned, made and inspected as its drawing requires. EN 15085 is the standard series most European orders name for this. The design assigns a class to each weld, and the documents that follow depend on that class. The checklist gathers those documents for a single assembly so the welding coordinator can see what is still open before signing the release.
- Responsible welding coordinators, who own the release.
- Quality engineers preparing a delivery pack or a customer audit.
- Buyers at vehicle builders, who can send the list to a new supplier as a statement of what will be asked for.
The template contains no classes, no inspection percentages and no tables from the standard. Every such cell reads "as stated on the drawing", because the drawing and the edition named in the order are where the answer is. Check the governing standard or contract. To match each joint to its procedure and welder in detail, use the WPS/PQR/WPQ cross-check template. See also rail component manufacturers.
Header block
| Field | Example |
|---|---|
| Project | Example Regional Train Fleet (fictional) |
| Customer | Example Rolling Stock Builder Ltd (fictional) |
| Purchase order | PO-EX-5530 (fictional) |
| Welded assembly | Equipment bracket frame, 24 welds (fictional) |
| Drawing and revision | DRG-EX-5530-02 Rev B |
| Welding standard named in the order | As stated in the PO (for example EN 15085), with its edition |
| Customer's welding specification | WS-EX-R-03 Rev 2 (invented) |
| Checklist no. | RWD-EX-5530-02 |
| Date | 2027-05-20 |
| Prepared by | Welding coordinator |
| Checked by | Quality engineer |
Example documents: an equipment bracket frame
| Item | Document or record | What the drawing and order require | What is on file | Document no. and revision | Status | Remark |
|---|---|---|---|---|---|---|
| 1 | Manufacturer's welding certification: scope | Certification at the level the PO and the drawing call for, with a scope that covers this assembly's processes and materials | Scope lists the welding processes and material groups used on the frame | CERT-EX-RW-017 | Complete | |
| 2 | Manufacturer's welding certification: validity | Valid on every day welding is done on this assembly | Certificate expires 2027-05-31; welding is planned to 2027-06-18 | CERT-EX-RW-017 | Query | The renewal audit is booked. Hold welding past the expiry date until the new certificate is in hand. |
| 3 | Welding coordinator | Responsible welding coordinator and deputies named, as the certification and the order require | Coordinator named on the certificate; the deputy has changed since it was issued | Appointment letter AL-EX-04 | Query | Report the change as the certification scheme requires, and tell the customer. |
| 4 | Weld performance class for each weld | As stated on the drawing, weld by weld | Weld list gives a class for 22 of 24 welds | WL-EX-5530-02 Rev A | Query | The drawing shows no class for welds 17 and 18. Raise a technical query. Do not assume a class. |
| 5 | Inspection class for each weld | As stated on the drawing, or as the standard named in the order links it to the performance class | Entered in the weld list for the 22 welds that have a performance class | WL-EX-5530-02 Rev A | Query | Open until item 4 is answered. |
| 6 | Welding procedure specification (WPS) for each joint | A WPS for every joint on the weld list, covering its process, material, thickness and position | Three WPS cover all 24 welds | WPS-EX-31, -32, -35 | Complete | |
| 7 | Qualification record behind each WPS | A qualification record supporting each WPS, by a route the standard named in the order accepts | Records on file for WPS-EX-31 and -32. None found for WPS-EX-35 | WPQR-EX-31, -32 | Missing | Find the record or qualify the procedure. Welds made to WPS-EX-35 stay on hold. |
| 8 | Welder and operator qualifications | Each welder qualified for the process, material and position, and valid on the day the weld was made | Four welders. The certificate of welder W-EX-12 ran out on 2027-04-30; the weld log shows W-EX-12 welding on 2027-05-06 | Welder list WQ-EX-5530 | Query | Check whether the qualification was prolonged in time. If it was not, raise a nonconformance for the welds made after 2027-04-30. |
| 9 | Welding consumable certificates | A certificate of the type the order states for each batch of filler material, and for shielding gas where asked | Certificates for both wire batches and for the gas supply | CC-EX-771, -772; GC-EX-19 | Complete | |
| 10 | Visual inspection reports | Extent as stated on the drawing for each weld's inspection class | One report covers all 24 welds | VT-EX-0412 | Complete | |
| 11 | Non-destructive examination (NDE) reports | Methods and extent as stated on the drawing for each weld's inspection class; examiner qualified as the order states | Surface examination report covers six welds. The drawing calls for volumetric examination of welds 3 and 4, and there is no report | MT-EX-0398 | Missing | Examine welds 3 and 4 before the frame is coated. |
| 12 | Repair records | Each repair recorded with its location, cause, the procedure used and the re-inspection | One repair, on weld 9, with re-examination | RR-EX-007 | Complete | |
| 13 | Production weld tests or work samples | Only where the drawing or the order asks for them | Not asked for on this assembly | Not applicable | Confirmed against PO-EX-5530 and WS-EX-R-03. | |
| 14 | Release | Signed by the responsible welding coordinator, with the declaration or certificate the order asks for | Not signed | Missing | Sign only when items 2 to 11 are closed. |
The frame, its 24 welds, the certificate number and the customer's welding specification WS-EX-R-03 do not exist. The example leaves two welds without a class on purpose: the supplier raises a query and does not pick one. Every example value is invented: the project, customer, bidders, purchase order, prices and every document, certificate, serial and report number do not exist. Standards are named but not quoted.
Status values
| Status | Use it when |
|---|---|
| Complete | The document is on file, covers this assembly and agrees with the drawing and the order. |
| Query | A document is on file, but something about it is open: a date, a scope, a name or a missing entry. Say what in the remark. |
| Missing | Nothing is on file yet, or what is on file does not cover the welds it should. The assembly is not ready for release. |
| Not applicable | Neither the order nor the drawing asks for this document on this assembly. Say why. |
Columns and what to write
| Column | What to write |
|---|---|
| Item | Running number. |
| Document or record | One welding document the order, the drawing or the standard named in the order asks you to hold for this assembly. |
| What the drawing and order require | Where the requirement is written and what it asks for. For classes and inspection extent write "as stated on the drawing" and the drawing number; do not copy a class or a percentage from memory. |
| What is on file | What you actually hold: its scope, dates and the welds it covers. |
| Document no. and revision | The number and revision of the document on file. |
| Status | Complete, Query, Missing or Not applicable (drop-down). Missing rows turn red; Query rows amber. |
| Remark | What is open, who closes it and by when. |
How to build the document set
- Fill in the header block: the assembly, its drawing and revision, the welding standard and edition the order names, and the customer's own welding specification if there is one.
- Read the drawing first. Write down, weld by weld, the performance class and the inspection class it states. Where the drawing is silent, raise a query; the class is the designer's decision.
- Check your certification: that its level and scope cover this work, and that it stays valid until the last weld.
- Go down the weld list and match each joint to a WPS, each WPS to its qualification record, and each welder to a qualification valid on the weld date.
- Gather the consumable certificates for the batches actually used.
- Compare the inspection and NDE reports with the weld list. Every weld needs the examination its class calls for on the drawing.
- File a record for every repair, with its re-inspection.
- Set the status of each row. Missing rows turn red and Query rows amber. The welding coordinator signs the release when none is left.
Checking welder and procedure records against the weld list
The slow part is the dates and ranges: does this welder's certificate cover that position, and was it in force on the day in the log? In OdysseyGPT's Manufacturing QA module, Welding Qualification Review (beta) reads the weld list, the procedures, their qualification records and the welder certificates and reports the joints where something does not line up, quoting the page. NDE Coverage Review (beta) compares the examination reports with what the drawing calls for on each weld. The welding coordinator remains the person who judges and signs. Tools marked beta are open on request, and we onboard each team ourselves.