HVAC submittal checklist: is the technical submittal complete? (Excel and CSV)

For HVAC equipment manufacturers and their representatives: one row per item the specification asks for, marked required, included and referenced, with every deviation written down.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

An HVAC submittal checklist confirms that an equipment technical submittal contains everything the specification asks for before it goes to the reviewer. This free Excel template has one row per item, from the duty point and selection printout to sound data, electrical data, controls, dimensions, filters, warranty and manuals, each marked required, included, referenced and checked for deviations.

Key Takeaways

  • Take the rows from the specification's submittals paragraph first, then add what the schedule and the products paragraphs imply.
  • Compare the selection with the equipment schedule one line at a time.
  • Put every deviation on the cover sheet yourself.
  • The example has 12 rows for an invented air handling unit submittal (M240-003), with two items missing and four deviations.

Download the HVAC submittal checklist

Both files are free under CC BY 4.0, with no form to fill in. The XLSX opens in Excel, Google Sheets, LibreOffice and Numbers. The CSV carries the table only; the header block is in the XLSX.

Use it on one submittal, before it leaves

An HVAC submittal is the pack of data an equipment manufacturer sends, through the contractor, to the design engineer to show that the unit selected meets the specification and the schedule. Reviewers send packs back for the same few reasons: something the specification listed is not there, the selection does not match the scheduled duty, or a difference was not declared. Each return costs a review cycle. This checklist is a last look at a single pack against the specification section it answers.

  • Application and sales engineers at manufacturers and their representatives, who assemble the pack.
  • Mechanical contractors' project engineers, who can run the same rows before forwarding a supplier's pack.
  • Design engineers, as a first sort of what has come in.

It is not a register. To track many submittals with their dates and review actions, use the submittal log template. What a submittal must contain, and which performance certification or test method applies, is set by the project specification: some name an AHRI certification programme, others a different scheme. Check the governing standard or contract. See also HVAC equipment manufacturers.

Header block

Header block fields, with the invented example values
FieldExample
ProjectExample Office Building, Level 3 fit-out (fictional)
Mechanical contractorExample Mechanical Contractor Ltd (fictional)
Purchase orderPO-EX-8815 (fictional)
Specification sectionM-240 Air handling units, Rev 2 (invented project specification)
Equipment scheduleDrawing M-601 Rev B (invented)
EquipmentAir handling unit AHU-03 (fictional)
Submittal no. and revisionM240-003 Rev 0
Date2027-04-06
Prepared byApplication engineer
Checked bySales engineer

Example rows: an air handling unit submittal

Invented example rows for submittal M240-003
ItemWhat the specification asks forSpecification sectionRequiredIncludedDocument referenceDeviationRemark
1Duty point matches the equipment schedule: airflow, external static pressure, coil duties and motor sizeM-240 2.1; schedule M-601YYSelection printout SP-EX-AHU-03 p.1Supply fan motor is one frame size larger than scheduledTell the electrical contractor. List it on the submittal cover sheet.
2Selection printout from the manufacturer's selection software, at the scheduled conditionsM-240 1.4 AYYSP-EX-AHU-03, 6 pagesNone
3Performance certification reference, under the programme the specification namesM-240 1.5 BYNCertificate reference for the cooling coil is not in the pack. Add it before issue.
4Sound data at the duty point, by octave band, to the method the specification namesM-240 2.6YYSP-EX-AHU-03 p.5Discharge sound power is above the scheduled figure in two bandsPrice a discharge attenuator as an option and flag it for the acoustic consultant.
5Casing construction, with leakage and strength classes as specifiedM-240 2.2YYCasing datasheet CD-EX-11 Rev CNone
6Electrical data: supply, full-load current, starting method, drive type and wiring diagramM-240 2.7YYElectrical datasheet ED-EX-AHU-03; diagram WD-EX-03NoneFull-load current reflects the larger motor in item 1.
7Controls: sequence of operation and points list for the building management systemM-240 2.8YNPoints list is with the controls subcontractor. Hold the submittal or agree a partial submittal in writing.
8Dimensions, section split, operating weights and service clearancesM-240 1.4 B; layout M-301YYGeneral arrangement GA-EX-AHU-03 Rev AUnit is longer than the space shown on layout M-301; access side unchangedAsk the contractor to check the plant room layout before approval.
9Filters: type, size and filter classes as specifiedM-240 2.5YYFilter datasheet FD-EX-07None
10Accessories: dampers, flexible connections, vibration isolators, access doors and lightsM-240 2.9YYAccessory list AL-EX-AHU-03None
11Warranty statementM-240 1.7YYWarranty statement WS-EX-01Warranty period runs from delivery; the specification counts from practical completionRaise with the contractor before the submittal goes in.
12Operation and maintenance manualM-240 1.6NNAsked for at handover, not with this submittal. Enter it in the submittal log as its own item.

The casing, leakage and filter rows say "as specified" because those classes belong to the project specification, and the template states none. The specification section, the schedule and the unit are invented. Every example value is invented: the project, customer, bidders, purchase order, prices and every document, certificate, serial and report number do not exist. Standards are named but not quoted.

Columns and what to write

ColumnWhat to write
ItemRunning number.
What the specification asks forOne item the specification section, the schedule or the contract requires in the submittal.
Specification sectionThe section and paragraph, or the schedule and drawing, that asks for it.
RequiredY if the specification asks for the item in this submittal, N if it does not or asks for it later (drop-down).
IncludedY if the item is in the pack, N if it is not (drop-down). Rows that are required and not included turn red.
Document referenceThe document in the pack that covers the item, with its number, revision and page.
DeviationWhere what you submit differs from what is specified or scheduled, say how. Write None if it does not. Rows with a deviation turn amber.
RemarkWhat is still to do, and who needs to be told.

How to check a submittal with it

  1. Fill in the header block: the specification section and its revision, the equipment schedule drawing, the unit tag and the submittal number.
  2. Read the submittals paragraph of the specification section and write one row for each thing it asks for. Then read the products paragraphs and the schedule for anything else that has to be shown.
  3. Set Required to Y or N. Use N for items the specification asks for at another stage, and say when in the remark.
  4. Go through the pack you are about to send. Set Included, and write the document, revision and page that covers each item.
  5. Compare the selection with the equipment schedule line by line. Where your unit differs from what is scheduled or specified, write the difference in the Deviation column, or None.
  6. Sort out every row that is required and not included, which turns red, before the submittal leaves.
  7. List every deviation on the submittal cover sheet. A deviation the reviewer finds first costs more than one you declared.
  8. Keep the checklist with your copy of the submittal, and update it when the submittal is revised.

Comparing the selection with the specification and schedule

Confirming that a document is in the pack is quick. Confirming that its contents agree with the specification takes longer: a motor size on the selection printout against the schedule, a sound figure against the acoustic clause. In OdysseyGPT's Tender & Quotation module, Datasheet Comparison (beta) sets your datasheet values beside the customer's, and Document Review reads the specification section and your submittal documents and lists where they differ, quoting the page on each side. The application engineer decides which differences are deviations. Tools marked beta are open on request, and we onboard each team ourselves.

See how OdysseyGPT reviews a tender

Tell us how your team reviews tenders today. We can walk through an example together.

Book a call

New templates by email (optional)

Your download does not depend on this.

We use your email only for this. See our privacy policy.

Frequently asked questions

What is an HVAC submittal?

The technical documents an HVAC equipment supplier provides for the design team's review before the equipment is released for manufacture: selection data, performance, sound, electrical and control information, drawings and similar items, as the specification lists them.

What should an HVAC submittal include?

What the submittals paragraph of the project specification lists, plus anything needed to show the scheduled duty is met. The rows in this template are common examples. Delete the ones your specification does not ask for and add the ones it does.

What is the difference between a submittal checklist and a submittal log?

The checklist looks inside one submittal and asks whether it is complete. The log lists all the submittals on a project and tracks their dates and review outcomes.

Do deviations have to be shown in a submittal?

Most specifications require deviations to be identified, and many say that approval does not cover a deviation nobody pointed out. Read the wording of your own contract. Check the governing standard or contract.

Does the template check performance certification?

It has a row to confirm that the certification reference the specification asks for is in the pack. Whether a unit falls within a programme's scope and is correctly listed is something to confirm in that programme's own directory.

References

Creative Commons Attribution 4.0 International